Registration lapsed No litigation declared Others project

Krishna Classic

By Kwality Developers

RG-MH-11463 · RERA P52100003081 · Last updated on MahaRERA portal: 5 Aug 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 55 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
7 of 11Construction stages donefurthest along: External plumbing and external plaster, 70%
1Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Krishna Classic is a Others project by Kwality Developers in Pune, Maharashtra, registered with MahaRERA as P52100003081 on 4 Aug 2017. Possession was promised by 5 Jul 2024 and is now 27 months past that date. The completion date has moved by 55 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKrishna Classic
  • TypeOthers
  • Location
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003081
  • ReraGenie IDRG-MH-11463

Builder

  • NameKwality Developers
  • Entity typePartnership

Key dates

27 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion5 Jul 2024
  • Revised completionRevised to 5 Jul 2024 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Krishna ClassicNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 70%.

Krishna Classic: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes30%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered21
Open Space20

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Bharati Sudam NadhePimpri Chinchawad (M Corp.)Pune
Jaywant NadhePimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI2038.66
Proposed, not sanctioned1,116 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPimple Saudagar

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKhire Bhide Associates
EngineerG A Bhilare Consultants Pvt Ltd
PartnerRole in project
Kwality Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017167Dec 2019 → Jul 2024

Reason as filed by the promoterOur Flat Did Not Saled As Per Our Expectation We Are Also Facing Finatioal issue Due To Facing Challenges In Sale We Need Some More Time To Complete The Project Challenges In Sale We Need Some More Time To Complete The Project

EXT52100005837Dec 2019 → Dec 2020

Reason as filed by the promoterWe request you to please grant us extension for this project as we were unable to complete it in the given time as we were in financial crisis and due to low market there was absolutely no booking . Also there were TDR sanctioning issues which consumed more time . But now we assure you that we will complete the project within the extended date asked for . Please grant us extension for the same .

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000198088SANKET DILIP VAIDYAmanisha khemchand bhojwani11/01/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KD Form 5 CA 20-21.pdf5 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: KD Form 5 CA 21-22.pdf5 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KD Form 5 CA 22-23.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: KD Form 5 CA 17-18.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: KD Form 5 CA 18-19.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KD Form 5 CA 19-20.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KD Form 5 CA 20-21.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: KD Form 5 CA 21-22.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: KD Form 5 CA 22-23.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KD Form 5 CA 22-23.pdf5 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KD Architects Certificate 27-07-2023_001 (1).pdf29 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: kwality jun 23.pdf29 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold 26-07-2023_001.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KD Form 2A_001.pdf17 Jul 2023
Certificates of CA (Form 3)File: Form 3 signed_compressed.pdf15 Jul 2023
Details of encumbrancesFile: No Encumbrance Certifica Kwality.PDF31 Jul 2017
Declaration in FORM BFile: FormB Kwality.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Kwality.PDF31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Kwality Certificate Of Engineer.pdf31 Jul 2017
Certificates of CA (Form 3)File: Kwality CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Agreement to sale.pdf31 Jul 2017
Building plan approvalFile: Building Plan Approval (IOD).pdf26 Jul 2017
Layout approvalFile: Copy of layout approval.pdf26 Jul 2017
PAN CardFile: Pan Card.pdf26 Jul 2017
Copy of the legal title reportFile: legal title report.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of layout approval.pdf26 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval (IOD).pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf26 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 55 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Krishna Classic on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune

2 kmKrishna ClassicCompleted 73Lapsed / revoked 48Other 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 265 registered projects within 2 km.

Builder: Kwality Developers

Kwality Developers has 1 registration on MahaRERA, including Krishna Classic. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Krishna Classic shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Krishna Classic is delayed beyond 5 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Krishna Classic?

The registered promoter entity is Kwality Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Krishna Classic?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Krishna Classic?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Krishna Classic?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Krishna Classic?

The professionals named in the filing: Architect: Khire Bhide Associates; Engineer: G A Bhilare Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Krishna Classic?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Krishna Classic. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Krishna Classic to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.