Home / Browse projects / Pune, Maharashtra / Kiarah Terrazo phase -II

Registration lapsed No litigation declared Others project

Kiarah Terrazo phase -II

By Wellwisher Apartment

RG-MH-87228 · RERA P52100019202 · Last updated on MahaRERA portal: 21 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
0 of 11Construction stages donefurthest along: Excavation, 20%
1Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Kiarah Terrazo phase -II is a Others project by Wellwisher Apartment in Pune, Maharashtra, registered with MahaRERA as P52100019202 on 9 Jan 2019. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKiarah Terrazo phase -II
  • TypeOthers
  • Location
    • hadpsar
    • pune
    • Hadapsar
    • Haveli
    • 411013
  • Pincode411013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100019202
  • ReraGenie IDRG-MH-87228

Builder

  • NameWellwisher Apartment
  • Entity typePartnership
  • PartnerBHANSALI INFOTECH LLP BHANSALI INFOTECH LLP
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredJan 2019PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Jan 2019
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building no 1 wing ANA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 20%.

Building no 1 wing A: 3% average across the applicable activities

ActivityProgress
Excavation20%
Basement (if any)8%
Podiums (if any)0%
Plinth8%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed58

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots58
Closed/Covered58

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,705 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s. Ahura FluxHadapsarPune

Approvals and building plan

Permissible FSI11257.18
Proposed, not sanctioned3,423 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI - TURBHE NAVI MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLaxman Thite
EngineerGA Bhilare Consultants Pvt Ltd
PartnerRole in project
Wellwisher Apartment-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000064464SHRIKRISHNA SHRIRAMM/s Well wisher Apartment through partner Mr. Abhijit C. Bhansali31/07/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jul 2022

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3-WA-Q2- 2023_Signed.pdf21 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: download-WA-F Y 2017-18.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Annual Report-F Y 2018-19-WA.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 F Y 2022-23-WA.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5-WA-F Y 2021-22.pdf19 Apr 2023
Building plan approvalFile: Layout with 2 shop_compressed.pdf10 Feb 2023
Building Plan Approval (IOD)File: Layout with 2 shop_compressed.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5-WA-F Y 2020-21.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3 KT PHASE II MARCH 2022.pdf19 Dec 2022
Certificates of CA (Form 3)File: FORM 3 KT PHASE II JUNE 2022.pdf19 Dec 2022
Certificates of CA (Form 3)File: FORM 3 KT PHASE II SEPT 2022.pdf19 Dec 2022
Proforma of Agreement for saleFile: Draft agreement - KT II.pdf19 Dec 2022
Certificates of CA (Form 3)File: FORM 3 KT PHASE II MARCH 2022.pdf25 Nov 2022
Certificates of CA (Form 3)File: FORM 3 KT PHASE II JUNE 2022.pdf25 Nov 2022
Certificates of CA (Form 3)File: FORM 3 KT PHASE II SEPT 2022.pdf25 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf24 Nov 2022
Proforma of Allotment letterFile: Draft agreement - KT.pdf4 Aug 2022
Proforma of Allotment letterFile: Draft Agreement.pdf3 Aug 2022
Details of encumbrancesFile: img044.pdf2 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 9 Shop OC.pdf18 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA LETTER001_compressed (1).pdf17 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 2021.pdf25 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 16-Phase-II.pdf6 Dec 2021
Proforma of Allotment letterFile: A Wing latest Interest Free.pdf6 Jul 2021
Certificates of CA (Form 3)File: Form 3-Sept 2020.pdf3 Jul 2021
Certificates of CA (Form 3)File: Form 3-Dec 2020.pdf3 Jul 2021
Certificates of CA (Form 3)File: Form 3- March 2021-Phase-II.pdf3 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Annual F Y 2019-20-WA Phase-II.pdf19 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 14-Phase-II-24012020_compressed.pdf28 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15-Phase-19022020.pdf28 Sep 2020
Certificates of CA (Form 3)File: Form 3_compressed.pdf28 Sep 2020
Certificates of CA (Form 3)File: FOMR 3-MARCH 2020.pdf28 Sep 2020
Certificates of CA (Form 3)File: FOMR 3-JUNE 2020.pdf28 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf9 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf9 Nov 2019
Form 2AFile: form 2A quality assurance.pdf26 Jul 2019
Declaration in FORM BFile: B form WA.pdf5 Jan 2019
Proforma of Allotment letterFile: Kt Phase II Rera draft - Copy-ilovepdf-compressed.pdf5 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf3 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: CC-.pdf3 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE (2).pdf3 Jan 2019
Layout approvalFile: layout.pdf2 Jan 2019
Building plan approvalFile: sanction plan-1-4.pdf2 Jan 2019
Building plan approvalFile: sanction plan-5-8.pdf2 Jan 2019
Building plan approvalFile: sanction plan-9-11.pdf2 Jan 2019
Building plan approvalFile: sanction plan-12-14.pdf2 Jan 2019
Details of encumbrancesFile: encrubrance certificate.pdf2 Jan 2019
Copy of Layout Approval (in case of layout)File: layout.pdf2 Jan 2019
Building Plan Approval (IOD)File: sanction plan-1-4.pdf2 Jan 2019
Building Plan Approval (IOD)File: sanction plan-5-8.pdf2 Jan 2019
Building Plan Approval (IOD)File: sanction plan-9-11.pdf2 Jan 2019
Building Plan Approval (IOD)File: sanction plan-12-14.pdf2 Jan 2019
Certificates of CA (Form 3)File: CA Certificate -.pdf2 Jan 2019
Proforma of Allotment letterFile: allotment letter.pdf2 Jan 2019
PAN CardFile: Pan Card WA.pdf29 Dec 2018
Copy of the legal title reportFile: Title Report.pdf29 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-ilovepdf-compressed (6).pdf29 Dec 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kiarah Terrazo phase -II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pune13,700+ in Pune

2 kmKiarah Terrazo phase -IICompleted 17Lapsed / revoked 7Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: Wellwisher Apartment

Wellwisher Apartment has 2 registrations on MahaRERA, including Kiarah Terrazo and Kiarah Terrazo phase -II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Kiarah Terrazo phase -II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Kiarah Terrazo phase -II is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kiarah Terrazo phase -II?

The registered promoter entity is Wellwisher Apartment, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kiarah Terrazo phase -II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kiarah Terrazo phase -II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kiarah Terrazo phase -II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kiarah Terrazo phase -II?

The professionals named in the filing: Architect: Laxman Thite; Engineer: GA Bhilare Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kiarah Terrazo phase -II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kiarah Terrazo phase -II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kiarah Terrazo phase -II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.