ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / KESHAR GOLD

Registered No litigation declared Mixed project

KESHAR GOLD

By KESHAR GROUP

RG-MH-16624 · RERA P52100026834 · Last updated on MahaRERA portal: 30 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
13 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 189 documents Report an error

KESHAR GOLD is a Mixed project by KESHAR GROUP in Pune, Maharashtra, registered with MahaRERA as P52100026834 on 28 Oct 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 35 of the 48 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameKESHAR GOLD
  • TypeMixed
  • Location
    • LOHEGAON
    • SATHE VASTI
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • RERA no.P52100026834
  • ReraGenie IDRG-MH-16624

Builder

  • NameKESHAR GROUP
  • Entity typePartnership
  • GSTIN27AATFK2211L1Z3
  • PartnersGAURAV BABULAL CHOUDHARY, VHAMPALAL VARADRAM CHOUDHARY, RAMESH DEVRAM CHOUDHARY, PRAKASH KUMAR JEEVARAM CHOUDHARY, CHETAN GHISARAM CHOUDHARY

Key dates

this monthRegisteredOct 2020First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Oct 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed189 files

Current status

73%35 of 48 units booked
100.0%Work done, per cost certificate

Figures as on 30 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KESHAR GOLDNA10740848

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

KESHAR GOLD: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,394 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Jul 2026

Approvals and building plan

Sanctioning authorityPOONA MUNCIPAL CORPORATION
Permissible FSI2329.69
Proposed, not sanctioned956 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP BIG BAZAR PUNE411015
Estimated costRs 6.52 cr
Cost incurredRs 6.52 cr
Work done100.0%
BuildingWingEstimatedIncurred
KESHAR GOLDNARs 5.22 crRs 5.22 cr
-NARs 1.30 crRs 1.30 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA GAIKWAD
EngineerASHOK THOSAR
Chartered AccountantCA SACHIN SHARMA
Chartered AccountantDipali Shelar
Chartered AccountantABSB and Associates
Chartered AccountantAgrawal Goyal Jain & Associates
Chartered AccountantPatel and Sharma
Chartered AccountantAGARWAL SARAWGI AND ASSOCIATES
PartnerRole in project
KESHAR GROUP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29072621929Dec 2024 → Dec 2026

Reason as filed by the promoterThe Full Occupation Certificate (OC) for the project was duly obtained on 18th February 2025, confirming that the construction was completed in accordance with the then-approved sanctioned plan and applicable building regulations. However, it is observed that the sanctioned built-up area has not been updated on the portal in line with the latest sanctioned plan. Further, for the purpose of applying for change in FSI, it is mandatory to obtain an extension of the project. Failing this, the project status may lapse, and the project will not be available in the correction module for carrying out

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed189

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 189 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf30 Oct 2026
Withdrawal Update Form 130 Oct 2026
Withdrawal Update Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf30 Oct 2026
Withdrawal Update Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf30 Oct 2026
Withdrawal Update Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf30 Oct 2026
Withdrawal Update Form 2File: form-02.pdf30 Oct 2026
Withdrawal Update Form 230 Oct 2026
Withdrawal Update Form 2File: form-02.pdf30 Oct 2026
Withdrawal Update Form 2File: form-02.pdf30 Oct 2026
Withdrawal Update Form 2File: form-02.pdf30 Oct 2026
Withdrawal Update Form 3File: kesar Group Form 03.pdf30 Oct 2026
Withdrawal Update Form 330 Oct 2026
Withdrawal Update Form 3File: kesar Group Form 03.pdf30 Oct 2026
Withdrawal Update Form 3File: kesar Group Form 03.pdf30 Oct 2026
Withdrawal Update Form 3File: kesar Group Form 03.pdf30 Oct 2026
Form 5 (FY 2025-2026)File: Form 5 signed.pdf17 Sep 2026
Form 2A (FY 2025-2026)File: IMG_0003.pdf29 Jul 2026
Withdrawal Update Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf21 Jul 2026
Withdrawal Update Form 2File: form-02.pdf21 Jul 2026
Withdrawal Update Form 3File: form-03.pdf21 Jul 2026
Form 1File: 20 Architect Certificate of Percentage of Completion of Work Form 1.pdf13 Jul 2026
Form 3File: form-03.pdf13 Jul 2026
Form 2File: form-02.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: 14 30-12-2024.pdf13 Jul 2026
Form 5 (FY 2020-2021)File: Form-5 for FY2021-22_Keshar Gold.pdf4 Jul 2026
Form 5 (FY 2021-2022)File: Form-5 for FY2021-22_Keshar Gold.pdf4 Jul 2026
Form 5 (FY 2022-2023)File: Form-5 for FY2022-23_Keshar Gold_0001.pdf4 Jul 2026
Form 5 (FY 2023-2024)File: form 5 Recd.pdf4 Jul 2026
Form 5 (FY 2024-2025)File: form 05.pdf4 Jul 2026
Form 2A (FY 2020-2021)File: IMG_0004.pdf22 Nov 2025
Form 2A (FY 2021-2022)File: IMG_0004.pdf22 Nov 2025
Form 2A (FY 2022-2023)File: IMG_0001.pdf22 Nov 2025
Form 2A (FY 2023-2024)File: IMG_0002.pdf22 Nov 2025
Form 2A (FY 2024-2025)File: IMG_0003.pdf22 Nov 2025
Form 1File: 14 30-5-2024 DOC012-OK.pdf6 Nov 2025
Form 2File: form-2 june.pdf6 Nov 2025
Form 3File: 15 Form 3-30-06-2024.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: 13 30-06-2024.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: 14 30-09-2024.pdf6 Nov 2025
Form 3File: 16 Form 3-30-09-2024.pdf6 Nov 2025
Form 2File: form-2 sep.pdf6 Nov 2025
Form 1File: 14 30-5-2024 DOC012-OK.pdf6 Nov 2025
Form 1File: 15 31-03-2025.pdf6 Nov 2025
Form 2File: form-02.pdf6 Nov 2025
Form 3File: form-03 mar 25.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: 15 31-03-2025.pdf6 Nov 2025
Form 1File: 02 05-03-2021 DOC011-OK.pdf6 Nov 2025
Form 2File: 02- 31-03-2021-ok.pdf6 Nov 2025
Form 3File: 02 31-03-2021_0001-ok.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: 01 30-06-2021-ok.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: 01 30-06-2021-ok.pdf6 Nov 2025
Form 3File: 01 31-12-2020_0001-ok.pdf6 Nov 2025
Form 2File: 01- 31-12-2020-ok.pdf6 Nov 2025
Form 1File: 02 05-03-2021 DOC011-OK.pdf6 Nov 2025
Form 1File: 07 05-06-2022 DOC006-OK.pdf5 Nov 2025
Form 2File: 07- 30-06-2022-ok.pdf5 Nov 2025
Form 3File: 07 Form 3- 30-06-2022-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 05 30-06-2022-ok.pdf5 Nov 2025
Form 1File: 05 05-12-2021 DOC008-OK.pdf5 Nov 2025
Form 2File: 05- 31-12-2021-ok.pdf5 Nov 2025
Form 3File: 05 Form 3- 31-12-2021-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 03 31-12-2021-ok.pdf5 Nov 2025
Form 1File: 06 05-03-2022 DOC007-OK.pdf5 Nov 2025
Form 2File: 14 31-03-2022.pdf5 Nov 2025
Form 3File: 06 Form 3- 31-03-2022-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 04 31-03-2022-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 06 30-09-2022-ok.pdf5 Nov 2025
Form 3File: 08 Form 3- 30-09-2022-ok.pdf5 Nov 2025
Form 2File: 08- 30-09-2022-ok.pdf5 Nov 2025
Form 1File: 08 05-09-2022 DOC005-OK.pdf5 Nov 2025
Form 1File: 09 05-12-2022 DOC004-OK.pdf5 Nov 2025
Form 2File: 09- 31-12-2022-ok.pdf5 Nov 2025
Form 3File: 09 Form 3- 31-12-2022-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 07 31-12-2022-ok.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: 08 31-03-2023-ok.pdf5 Nov 2025
Form 3File: 10 Form 3-31-03-2023-ok.pdf5 Nov 2025
Form 2File: 15 31-03-2023.pdf5 Nov 2025
Form 1File: 10 25-5-2023 DOC002-OK.pdf5 Nov 2025
Form 1File: 11 10-07-2023 DOC001-OK.pdf5 Nov 2025
Form 2File: 11- 30-06-2023-ok.pdf5 Nov 2025

How this compares with Pune

73%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 24 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KESHAR GOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SATHE VASTI14,000+ in Pune

Builder: KESHAR GROUP

KESHAR GROUP has 1 registration on MahaRERA, including KESHAR GOLD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KESHAR GOLD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KESHAR GOLD?

The registered promoter entity is KESHAR GROUP, a partnership as per the filing. Its GSTIN 27AATFK2211L1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KESHAR GOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KESHAR GOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KESHAR GOLD?

The professionals named in the filing: Architect: RAJENDRA GAIKWAD; Engineer: ASHOK THOSAR; Chartered Accountant: CA SACHIN SHARMA; Chartered Accountant: Dipali Shelar; Chartered Accountant: ABSB and Associates; Chartered Accountant: Agrawal Goyal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KESHAR GOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KESHAR GOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KESHAR GOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.