KERALA VILLAGE
By JOHN MATHEW
RG-MH-24620 · RERA P51700006990 · Last updated on MahaRERA portal: 20 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- Completion date moved by 27 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KERALA VILLAGE is a Residential / Group Housing project by JOHN MATHEW in Thane, Maharashtra, registered with MahaRERA as P51700006990 on 17 Aug 2017. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 27 months from the original filing.
At a glance
Project
- NameKERALA VILLAGE
- TypeResidential / Group Housing
- Location
- Satgaon
- Shahapur
- Thane
- 421601
- Pincode421601
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700006990
- ReraGenie IDRG-MH-24620
Builder
- NameJOHN MATHEW
- Entity typeIndividual
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 30 Dec 2022)
- Buildings48 building records
- Documents filed100 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 1 | 0 | 0 | 0 | 0 |
| A2 | NA | 1 | 0 | 0 | 0 | 0 |
| A3 | NA | 1 | 0 | 0 | 0 | 0 |
| A4 | NA | 1 | 0 | 0 | 0 | 0 |
| A5 | NA | 1 | 0 | 0 | 0 | 0 |
| A6 | NA | 1 | 0 | 0 | 0 | 0 |
| A7 | NA | 1 | 0 | 0 | 0 | 0 |
| A8 | NA | 1 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| A14 | NA | 1 | 0 | 0 | 0 | 0 |
| A13 | NA | 1 | 0 | 0 | 0 | 0 |
| A18 | NA | 1 | 0 | 0 | 0 | 0 |
| A17 | NA | 1 | 0 | 0 | 0 | 0 |
| A16 | NA | 1 | 0 | 0 | 0 | 0 |
| A15 | NA | 1 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| B1 | NA | 2 | 0 | 0 | 0 | 0 |
| B2 | NA | 2 | 0 | 0 | 0 | 0 |
| B3 | NA | 2 | 0 | 0 | 0 | 0 |
| B4 | NA | 2 | 0 | 0 | 0 | 0 |
| B5 | NA | 2 | 0 | 0 | 0 | 0 |
| B6 | NA | 2 | 0 | 0 | 0 | 0 |
| B7 | NA | 2 | 0 | 0 | 0 | 0 |
| C1 | NA | 2 | 0 | 0 | 0 | 0 |
| C2 | NA | 2 | 0 | 0 | 0 | 0 |
| STUDIO APARTMENT - 1 | NA | 5 | 0 | 0 | 0 | 0 |
| STUDIO APARTMENT - 2 | NA | 5 | 0 | 0 | 0 | 0 |
| STUDIO APARTMENT - 3 | NA | 5 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| B8 | NA | 2 | 0 | 0 | 0 | 0 |
| B9 | NA | 2 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 48 buildings; the table lists the first 20.
262 of 528 construction stages are filed complete across 48 buildings. The stage furthest along is Slabs of Super Structure, at 20%.
A1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A14100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A13100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A18100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A17100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A16100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A15100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
091%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B164%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | John Varghese |
| Architect | Suresh Babu |
| Engineer | Ajay Mahale MAHALE |
| Chartered Accountant | R.D.Patel & Co |
| Chartered Accountant | P C Parvadiya & Associates |
| Partner | Role in project |
|---|---|
| JOHN MATHEW | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, We request to grant extension for completion of the Project by 30th December , 2023 with the occupation certificate and accordingly we are applying for extension of time. We would like to convey that due to force majeure events, certain unavoidable circumstances and lastly due to the prevailing pandemic Covid-19, the completion of the Project has been delayed. There has been delay from the contractor due to shortage and highly interrupted supply of construction material at area of Shahapur, acute shortage of Sand and Royalty issues. The pandemic period significantly affected the week
Reason as filed by the promoterDear Sir, Regarding Project Kerala Village registered with Maharera with Registration Number P51700006990, We would like to convey that due to certain unavoidable circumstances, the completion of the Project has been delayed. The primary cause of this delay is attributed to challenges faced by our contractors, such as a shortage and highly interrupted supply of construction materials, labour issues which we face at Shahpur. Out of the 26 bungalows, 24 Bungalows are 100% completed, 2 bungalows are nearing completion with 80% work completed. Studio Apartment No. 2 with 72 flats and Studio Apartm
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Jan 2025
Documents filed100
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Completion.pdf | 20 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kerala Village OC-min.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate Ph1 compressed.pdf | 17 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 ER CA Certificate Phase 1.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Phase 1 ENGINEERS CERTIFICATE.pdf | 17 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rera Phase 1 ENGINEERS CERTIFICATE.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 RERA Audit PH 2324.pdf | 17 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ER PH 1 ARCHITECTS CERTIFICATE 300624 compressed.pdf | 26 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Ph 1Engineers certificate 300624.pdf | 26 Jul 2024 |
| Certificates of CA (Form 3)File: Elixir Realty CA Certificate Phase 1 300624.pdf | 26 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Adobe Scan Apr 19, 2024 (3)_compressed.pdf | 20 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Kv phase 1 engnr.pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Kv phase 1 quality.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Phase 1 RERA - Disclosure of sold _compressed.pdf | 20 Apr 2024 |
| Certificates of CA (Form 3)File: Kerala Village_compressed.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Ph 1 kv.pdf | 22 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Ph1.pdf | 22 Jan 2024 |
| Certificates of CA (Form 3)File: kerala village- CA certificate Ph 1 compressed.pdf | 22 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Elixir realty Form 5.pdf | 8 Jan 2024 |
| Declaration in FORM BFile: Affidavit cum Declaration .pdf | 5 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Ph 1.pdf | 5 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Ph 1.pdf | 5 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance certificate .pdf | 5 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold.pdf | 5 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 CA certificate _compressed.pdf | 5 Jan 2024 |
| Certificates of CA (Form 5)File: Form 5 Annual Report.pdf | 5 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Phase 1 KV.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engnr phase 1 kv.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: CA phase 1 KV.pdf | 20 Oct 2023 |
| Certificates of CA (Form 5)File: FORM 5 RERA AUDIT CERTIFICATE 2022-23.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Final Disclosure of sold inventory ph1.pdf | 20 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase1ArchCert.pdf | 19 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EngineerCertPhas1.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf | 19 Jul 2023 |
| Certificates of CA (Form 3)File: CA certificate form 3 ph 1 (2).pdf | 19 Jul 2023 |
| Proforma of Agreement for saleFile: Agreement for sale draft Revisedn.pdf | 19 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of unsold.pdf | 20 Apr 2023 |
| Certificates of CA (Form 3)File: Revised kerala village 310323 CA certcompressed.pdf | 20 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Elixir kerla Village Decon Architect Cert compressed.pdf | 17 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineers certificate form 2 310323.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: certificate for quality assurance 310323.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 13 Apr 2023 |
| Certificates of CA (Form 3)File: Elixir Realty_compressed.pdf | 13 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2 Certificates of CA (Form 5).pdf | 13 Apr 2023 |
| PAN CardFile: PAN_JM.pdf | 4 Jan 2023 |
| Details of encumbrancesFile: Financial No encumbrance self declaration revised .pdf | 4 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Legal No encumbrance self declaration revised .pdf | 4 Jan 2023 |
| Details of encumbrances concerned to LegalFile: Legal No encumbrance self declaration revised .pdf | 4 Jan 2023 |
| Declaration about Commencement CertificateFile: CC covering letter .pdf | 4 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineersertificatecompressed.pdf | 4 Jan 2023 |
| CERSAI detailsFile: Cersai declaration revised .pdf | 4 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of soldcompressed.pdf | 4 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Scan 04 Jan 23 · 15·07·40 (1).pdf | 4 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A separate bank account letter.pdf | 4 Jan 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation report on allotment letter revised.pdf | 4 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report on agreement for sale revised .pdf | 4 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecturecertificate011222.pdf | 3 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecturecertificate310322.pdf | 3 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineerscertificate011222.pdf | 3 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineerscertificate011222.pdf | 3 Jan 2023 |
| Certificates of CA (Form 3)File: Form3KeralaVillagecompressed.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERAAUDITCERTIFICATE202122FORM5PDF.pdf | 3 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 KVi.pdf | 4 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2KVi.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: AQKV.pdf | 4 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Audit Form.pdf | 30 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form.pdf | 30 Sep 2020 |
| Certificates of CA (Form 5)File: Elixir reality - P51700006990.pdf | 30 Sep 2019 |
| Layout approvalFile: Plan4Edit.pdf | 22 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Plan4Edit.pdf | 22 Feb 2019 |
| Layout approvalFile: Plan1.pdf | 1 Feb 2019 |
| Layout approvalFile: Plan5.pdf | 1 Feb 2019 |
| Layout approvalFile: Plan6.pdf | 1 Feb 2019 |
| Layout approvalFile: Plan7.pdf | 1 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Plan1.pdf | 1 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Plan5.pdf | 1 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Plan6.pdf | 1 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Plan7.pdf | 1 Feb 2019 |
| Certificates of CA (Form 5)File: Elixir Reality (Kerala Village).pdf | 13 Oct 2018 |
| Details of encumbrancesFile: Form1.pdf | 1 Feb 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 100 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep KERALA VILLAGE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shahapur7,600+ in Thane
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
BELLA VISTA PHASE 8
INDO ASIAN BUILDCON PVT LTD
RUSTOMJEE BELLE VUE
KEYSTONE REALTORS LIMITED
THE VENISCAPE
MIVAAN BUILDCON PRIVATE LIMITED
VISION SKY WORLD
M/S VISION SKY WORLD
Sunteck FORESTWorld 1
SUNTECK REALTY HOLDINGS PVT LTD
Sunteck FORESTWorld 2
SUNTECK REALTY HOLDINGS PVT LTD
See every Thane project, with the district possession charts
Builder: JOHN MATHEW
JOHN MATHEW has 2 registrations on MahaRERA, including KERALA VILLAGE and Kerala Village Phase-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that KERALA VILLAGE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KERALA VILLAGE is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KERALA VILLAGE?
The registered promoter entity is JOHN MATHEW, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KERALA VILLAGE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KERALA VILLAGE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KERALA VILLAGE?
The professionals named in the filing: Architect: John Varghese; Architect: Suresh Babu; Engineer: Ajay Mahale MAHALE; Chartered Accountant: R.D.Patel & Co; Chartered Accountant: P C Parvadiya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KERALA VILLAGE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback