Home / Browse projects / Nagpur, Maharashtra / KELZARE LAYOUT
KELZARE LAYOUT
By KELZARE BUILDERS AND DEVELOPERS
RG-MH-03661 · RERA P50500029744 · Last updated on MahaRERA portal: 9 Jun 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KELZARE LAYOUT is a Plotted project by KELZARE BUILDERS AND DEVELOPERS in Nagpur, Maharashtra, registered with MahaRERA as P50500029744 on 29 Jun 2021. The registration is recorded completed; possession was promised by 30 Dec 2024. The completion date has moved by 12 months from the original filing. 13 of the 17 units on this registration are recorded sold or booked.
At a glance
Project
- NameKELZARE LAYOUT
- TypePlotted
- Location
- WARDHA ROAD
- SHANKARPUR NAGPUR GRAMIN
- Shankarpur
- Nagpur (Rural)
- Nagpur
- 441108
- Pincode441108
- RERA no.P50500029744
- ReraGenie IDRG-MH-03661
Builder
- NameKELZARE BUILDERS AND DEVELOPERS
- Entity typePartnership
- PartnersMANJULA KELZARE, PRAMOD KELZARE, VINOD KELZARE
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Jun 2021
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2023)
- BuildingsNot stated in filing
- Documents filed119 files
Current status
Figures as on 9 Jun 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 9 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership6
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Manoj Kelzare | Nagpur (M Corp.) | Nagpur |
| VinoD Kelzare | Nagpur (M Corp.) | Nagpur |
| Pramod Kelzare | Nagpur (M Corp.) | Nagpur |
| Manju Kelzare | Nagpur (M Corp.) | Nagpur |
| Jayvantabai Kelzare | Nagpur (M Corp.) | Nagpur |
| Yashodhara Kelzare | Nagpur (M Corp.) | Nagpur |
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vijay B Bagde |
| Engineer | AMOL URKUDE |
| Chartered Accountant | G A D ASSOCIATES |
| Partner | Role in project |
|---|---|
| KELZARE BUILDERS AND DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDECLARATION AND UNDERTAKING Project Details : Registration Number : P50500029744. Kelzare Layout: Plot Nos. 2,3,6,10 To 23 Survey No.54, Mouza Shankarpur, Wardha Road, Shankarpur Nagpur Gramin, Village Shankarpur, Taluka and District: Nagpur -441108;. The undersigned Authorised Signatory/Promoter hereby do Declare and Undertake as under:- 1) That project Kelzare Layout on : Plot Nos. 2,3,6,10 To 23 Survey No.54, Mouza Shankarpur, Wardha Road, Shankarpur Nagpur Gramin, Village Shankarpur, Taluka and District: Nagpur -441108; is completed 60% and the promoter will be applying for the completion
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 May 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 May 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 9 Jun 2025
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion MAil.pdf | 9 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 (3) (1).pdf | 24 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_Dec-24.pdf | 24 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_Mar-25.pdf | 24 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kelzare Layout_Form-2-Engineers Certificate_Dec-24.pdf | 24 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kelzare Layout_Form-2-Engineers Certificate_Mar-25.pdf | 24 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Dec-24.pdf | 24 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-25.pdf | 24 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kelzare Layout_Form-1_Architect Certificate (1).pdf | 18 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RL-1.pdf | 18 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RL-2.pdf | 18 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM-4_Kelzare Layout (1).pdf | 18 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1.pdf | 17 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2.pdf | 17 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: kelzare form1 2 (1).pdf | 11 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Kelzare Layout Form 5.pdf | 9 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Sep-24.pdf | 5 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Sep-24.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_June-2024.pdf | 30 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_JUNE-24.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_June-24.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_KELZARE LAYOUT_JUNE-24.pdf | 8 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: KELZARE LAYOUT_Form-2A_MAR-24.pdf | 24 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kelzare_Form 3_Mar-24.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Mar-24.pdf | 18 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-24.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_Mar-24.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_cert_kelzareBuilders.pdf | 17 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KELZARE LAYOUT March 2024.pdf | 17 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Vinod.pdf | 4 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Pramod.pdf | 4 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Yashodhara.pdf | 4 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Manju.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5_KELZARE LAYOUT_FY-21-22.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kelzare_FORM-5_FY-22-23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Mar-22.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_June-22.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Sep-22.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Dec-22.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Mar-23.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_June-23.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Sep-23.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KELZARE LAYOUT_Form-2-Engineers Certificate_Dec-23.pdf | 28 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Manoj.pdf | 28 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_June-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_sep-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Dec-22.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-23.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_June-23.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_sep-23.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Dec-23.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUM_FINANCE_Prepared_Kelzare.pdf | 20 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUM_LEGAL_Prepared_Kelzare.pdf | 20 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUM_FINANCE_Prepared_Kelzare.pdf | 20 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUM_LEGAL_Prepared_Kelzare.pdf | 20 Feb 2024 |
| Declaration in FORM BFile: FORM-B_.pdf | 20 Feb 2024 |
| CERSAI detailsFile: Cersai Declaration-Kelzare.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_MAr-22.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_JUNE-22.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_SEP-22.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_Dec-22.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_MAr-23.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_JUNE-23.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_SEP-23.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kelzare_Form 3_Dec-23.pdf | 20 Feb 2024 |
| Proforma of Agreement for saleFile: Agreement to Sale -Kelzare.pdf | 20 Feb 2024 |
| Proforma of Allotment letterFile: Allotment Letter _Kelzare.pdf | 20 Feb 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 20 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report Allotment - Kelzare.pdf | 20 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: ATS DEVIATION REPORT -Kelzare.pdf | 20 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: KELZARE LAYOUT_Form-2A_MAR-22.pdf | 9 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KELZARE LAYOUT_Form-2A_MAR-23.pdf | 9 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_KELZARE LAYOUT_JUNE-21.pdf | 6 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_KELZARE LAYOUT_SEP-21.pdf | 6 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_KELZARE LAYOUT_SEP-21.pdf | 6 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 119 filed documents as one ZIP, foldered, with a manifest
Keep KELZARE LAYOUT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHANKARPUR NAGPUR GRAMIN2,800+ in Nagpur
Kanher Nagri Developers
KANHER NAGRI DEVELOPERS
MAHALAXMI NAGAR 6
MAHALAXMI ESTATE
MAHALAXMI NAGAR 4
PADMALAXMI DEVELOPERS
Moreshwar park 4
PRASANNA PLANNERS
PRIME PLATINUM
UMAKANT VITTHAL MENDHE
MAULI NAGAR 8
MAULI INFRATECH
See every Nagpur project, with the district possession charts
Builder: KELZARE BUILDERS AND DEVELOPERS
KELZARE BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including KELZARE LAYOUT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if KELZARE LAYOUT is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KELZARE LAYOUT?
The registered promoter entity is KELZARE BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KELZARE LAYOUT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KELZARE LAYOUT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KELZARE LAYOUT?
The professionals named in the filing: Architect: Vijay B Bagde; Engineer: AMOL URKUDE; Chartered Accountant: G A D ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KELZARE LAYOUT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback