Home / Browse projects / Dakshina Kannada, Karnataka / Keerthana Pearls City

Registration approved Residential/Group Housing project

Keerthana Pearls City

By Keerthana Developers

RG-KA-22691 · RERA PRM/KA/RERA/1257/335/PR/190724/002721 · Last updated on RERA Karnataka portal: 29 May 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 33 months
  • 3 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 33 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 56 documents Report an error

Keerthana Pearls City is a Residential/Group Housing project by Keerthana Developers in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/335/PR/190724/002721 on 24 Jul 2019. Possession is promised by 30 Dec 2023. The completion date has moved by 33 months from the original filing.

At a glance

Project

  • NameKeerthana Pearls City
  • TypeResidential/Group Housing
  • Location
    • Puttur
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/335/PR/190724/002721
  • ReraGenie IDRG-KA-22691

Builder

  • NameKeerthana Developers
  • Entity typePartnership Firm
  • Authorized SignatoryVeena Kumari
  • Other registrations2 more →

Key dates

this monthRegisteredJul 2019First promiseMar 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Jul 2019
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 31 Mar 2021)
  • Buildings2 building records
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---30030
Block B---10010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 29 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,310 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.00 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Dec 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1257/335/PR/220928/002721Dec 2021 → Dec 2022

Reason as filed by the promoterShortage of Labour

ExtensionDec 2022 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/335/PR/190724/002721 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form BFile: From B Afidvit REvs.pdf29 May 2022
NOC Water DeptFile: Water NOC.pdf29 May 2022
NOC Power SupplyFile: Mescom NOC.pdf29 May 2022
2. 2) Breakup Development detailsFile: % comple.pdf14 Jan 2022
2. 3) Proforma Agreement of saleFile: Sale Agrmt.pdf14 Jan 2022
2. 4) Proforma Sale deedFile: Sale Deed.pdf14 Jan 2022
Affidavit in Form EX-7File: Form Ex7 Affidavit.pdf16 Dec 2021
Revised Form-BFile: Form B lat.pdf16 Dec 2021
KSPCBFile: KSPC Appr KPC.pdf16 Dec 2021
Breakup Development DetailsFile: KPC Devlpnt.pdf16 Dec 2021
Architect/Structural Engg/Contractor detailFile: Contract dtls.pdf16 Dec 2021
Project MemberFile: Membr dtls.pdf16 Dec 2021
Commencement certificateFile: Commence cer KPC.pdf26 Oct 2021
Affidavit under sec 18(i)File: Afiidavit.pdf26 Oct 2021
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex1 Arch.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5 Engg.pdf-
CA Certificate for Funds UtilizationFile: Form Ex3 CA fund uti.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex2 Arch.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6 Engg.pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex4 CA fund req.pdf-
AffidavitFile: Form Ex7 Affidavit.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Alotee consent.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.pdf-
approved building plan-
sale deed-
approved building plan-
19 Project Specif-
8 EC-
Affidavit-
22 Khata-
mou-
conversion-
Balance Sheet 2017 - 2018File: BS 2018.pdf-
Balance Sheet 2016 - 2017File: BS 2017.pdf-
Balance Sheet 2015 - 2016File: BS 2016.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L 2018.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L 2016.pdf-
Cash Flow Statement 2017 - 2018File: CF 2018.pdf-
Cash Flow Statement 2016 - 2017File: CF 2017.pdf-
Auditor's Report 2017 - 2018File: Aud rprt 2018.pdf-
Auditor's Report 2016 - 2017File: Aud rprt 2017.pdf-
Auditor's Report 2015 - 2016File: Aud rprt 2016.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR V 17-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR V 16-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR V-15-16.pdf-
form-b_compressed-
Prospectus/BrochureFile: 17 Brochure.pdf-
Advertisement Copy 1File: Advertisment.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1257_335_PR_190724_002721.xlsx-
Occupancy CertificateFile: Occupency Certfit KPC.pdf-
Completion certificate issued by the competent authorityFile: Compltn Cert KPC.pdf-
Registered Agreement of SaleFile: Sale deed KPC.pdf-
Registered conveyance deed for an individual unitFile: Reconvynce deed KPC-.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 33 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Keerthana Pearls City on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmKeerthana Pearls CityOther 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: Keerthana Developers

Keerthana Developers has 3 registrations on RERA Karnataka, including KEERTHANAS RADHA RESIDENCY and Keerthana Pearls City. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Keerthana Pearls City is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Keerthana Pearls City?

The registered promoter entity is Keerthana Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Keerthana Pearls City?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Keerthana Pearls City?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Keerthana Pearls City. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Keerthana Pearls City to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.