Keerthana Pearls City
RG-KA-22691 · RERA PRM/KA/RERA/1257/335/PR/190724/002721 · Last updated on RERA Karnataka portal: 29 May 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 33 months
- 3 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Keerthana Pearls City is a Residential/Group Housing project by Keerthana Developers in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/335/PR/190724/002721 on 24 Jul 2019. Possession is promised by 30 Dec 2023. The completion date has moved by 33 months from the original filing.
At a glance
Project
- NameKeerthana Pearls City
- TypeResidential/Group Housing
- Location
- Puttur
- Dakshina Kannada
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/335/PR/190724/002721
- ReraGenie IDRG-KA-22691
Builder
- NameKeerthana Developers
- Entity typePartnership Firm
- Authorized SignatoryVeena Kumari
- Other registrations2 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Jul 2019
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 31 Mar 2021)
- Buildings2 building records
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A | - | - | - | 30 | 0 | 30 |
| Block B | - | - | - | 10 | 0 | 10 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 29 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 29 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Labour
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed56
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/335/PR/190724/002721 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form BFile: From B Afidvit REvs.pdf | 29 May 2022 |
| NOC Water DeptFile: Water NOC.pdf | 29 May 2022 |
| NOC Power SupplyFile: Mescom NOC.pdf | 29 May 2022 |
| 2. 2) Breakup Development detailsFile: % comple.pdf | 14 Jan 2022 |
| 2. 3) Proforma Agreement of saleFile: Sale Agrmt.pdf | 14 Jan 2022 |
| 2. 4) Proforma Sale deedFile: Sale Deed.pdf | 14 Jan 2022 |
| Affidavit in Form EX-7File: Form Ex7 Affidavit.pdf | 16 Dec 2021 |
| Revised Form-BFile: Form B lat.pdf | 16 Dec 2021 |
| KSPCBFile: KSPC Appr KPC.pdf | 16 Dec 2021 |
| Breakup Development DetailsFile: KPC Devlpnt.pdf | 16 Dec 2021 |
| Architect/Structural Engg/Contractor detailFile: Contract dtls.pdf | 16 Dec 2021 |
| Project MemberFile: Membr dtls.pdf | 16 Dec 2021 |
| Commencement certificateFile: Commence cer KPC.pdf | 26 Oct 2021 |
| Affidavit under sec 18(i)File: Afiidavit.pdf | 26 Oct 2021 |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form Ex1 Arch.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5 Engg.pdf | - |
| CA Certificate for Funds UtilizationFile: Form Ex3 CA fund uti.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form Ex2 Arch.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6 Engg.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form Ex4 CA fund req.pdf | - |
| AffidavitFile: Form Ex7 Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Consent letter from 2/3rd of AllotteesFile: Alotee consent.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.pdf | - |
| approved building plan | - |
| sale deed | - |
| approved building plan | - |
| 19 Project Specif | - |
| 8 EC | - |
| Affidavit | - |
| 22 Khata | - |
| mou | - |
| conversion | - |
| Balance Sheet 2017 - 2018File: BS 2018.pdf | - |
| Balance Sheet 2016 - 2017File: BS 2017.pdf | - |
| Balance Sheet 2015 - 2016File: BS 2016.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P&L 2018.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L 2017.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L 2016.pdf | - |
| Cash Flow Statement 2017 - 2018File: CF 2018.pdf | - |
| Cash Flow Statement 2016 - 2017File: CF 2017.pdf | - |
| Auditor's Report 2017 - 2018File: Aud rprt 2018.pdf | - |
| Auditor's Report 2016 - 2017File: Aud rprt 2017.pdf | - |
| Auditor's Report 2015 - 2016File: Aud rprt 2016.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR V 17-18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR V 16-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR V-15-16.pdf | - |
| form-b_compressed | - |
| Prospectus/BrochureFile: 17 Brochure.pdf | - |
| Advertisement Copy 1File: Advertisment.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_335_PR_190724_002721.xlsx | - |
| Occupancy CertificateFile: Occupency Certfit KPC.pdf | - |
| Completion certificate issued by the competent authorityFile: Compltn Cert KPC.pdf | - |
| Registered Agreement of SaleFile: Sale deed KPC.pdf | - |
| Registered conveyance deed for an individual unitFile: Reconvynce deed KPC-.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Keerthana Pearls City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: Keerthana Developers
Keerthana Developers has 3 registrations on RERA Karnataka, including KEERTHANAS RADHA RESIDENCY and Keerthana Pearls City. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Keerthana Pearls City is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Keerthana Pearls City?
The registered promoter entity is Keerthana Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Keerthana Pearls City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Keerthana Pearls City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.