Home / Browse projects / Nagpur, Maharashtra / KDR PRIME
KDR PRIME
By KDR BUILDERS
RG-MH-04075 · RERA P50500034978 · Last updated on MahaRERA portal: 19 Apr 2024
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 19 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KDR PRIME is a Residential / Group Housing project by KDR BUILDERS in Nagpur, Maharashtra, registered with MahaRERA as P50500034978 on 28 Apr 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date.
At a glance
Project
- NameKDR PRIME
- TypeResidential / Group Housing
- Location
- -
- SHEET NO 218/42 JARIPATKA
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440014
- Pincode440014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500034978
- ReraGenie IDRG-MH-04075
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on28 Apr 2022
- Promised completion31 Mar 2025
- Revised completionNone
- Buildings1 building record
- Documents filed49 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KDR PRIME | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 10%.
KDR PRIME: 83% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 19 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ANIL BALKRISHNA DHARGAVE | Nagpur (M Corp.) | Nagpur |
| USHA GUPTAMANYU MESHRAM | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JITENDRA INGULKAR |
| Engineer | JITENDRA INGULKAR |
| Chartered Accountant | SAMEER DIVECHA |
| Partner | Role in project |
|---|---|
| KDR BUILDERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE DEC 23.pdf | 19 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KDR ARCHITECTS CERTIFICATE.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KDR ENGINEER CERIFICATE.pdf | 15 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: annual report.pdf | 3 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate d registration.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate d-registration.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate d registration.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate d -registration.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate d registration.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engi certi.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.pdf | 2 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENG CERT.pdf | 2 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENG CERT.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory june 22.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold sep 22.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold dec 22.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold march 23.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory june 23.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certi d registration.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certi d registration.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KDR PRIME ARCHITECT CERTI.pdf | 28 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng certificate.pdf | 28 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: sold booked inventory.pdf | 28 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf | 28 Dec 2023 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf | 15 Apr 2022 |
| Declaration in FORM BFile: KDR FORM B.pdf | 15 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate new.pdf | 15 Apr 2022 |
| Details of encumbrancesFile: non encumrance certificate of lawyer.pdf | 6 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Building Permit Commencement certificate.pdf | 6 Apr 2022 |
| Declaration about Commencement CertificateFile: DELARATION ABOUT COMMENCEMENT CERTIFICATE.pdf | 6 Apr 2022 |
| OtherFile: KDR_compressed (1).pdf | 6 Apr 2022 |
| Layout approvalFile: Building Permit Commencement certificate.pdf | 5 Apr 2022 |
| Details of encumbrancesFile: NON ENCUMBERANCE CERTIFICATE.pdf | 5 Apr 2022 |
| Copy of Layout Approval (in case of layout)File: Building Permit Commencement certificate.pdf | 5 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE .pdf | 5 Apr 2022 |
| CERSAI detailsFile: order no 19 Report from CERSAI.pdf | 5 Apr 2022 |
| CERSAI detailsFile: CERSAI REPLY.PDF | 5 Apr 2022 |
| Proforma of Allotment letterFile: Draft Sale Deed.pdf | 5 Apr 2022 |
| Proforma of Allotment letterFile: allotment letter.pdf | 5 Apr 2022 |
| Building plan approvalFile: BUILDING PLAN MAP_compressed.pdf | 4 Apr 2022 |
| PAN CardFile: KDR PAN.pdf | 4 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN MAP_compressed.pdf | 4 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect report kdr .pdf | 4 Apr 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| KDR PRIME | PNO 169 CTS 1683 | 10 | Ongoing | Mar 2025 | Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
Keep KDR PRIME on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHEET NO 218/42 JARIPATKA2,800+ in Nagpur
Filed coordinates, straight-line distance. 31 registered projects within 2 km.
JARRY EMPERIO
JARRY PREMIER LLP
RACHNA HEIGHTS
SHAKUNTALA INFRA
KRISHNA LEELAA-3
JARRY PROFITS
LEVERAGE GREEN PARKS PHASE-II
LEVERAGE REALTORS PRIVATE LIMITED
GOVIND RESIDENCY-III
BHAVYA INFRAVENTURES PRIVATE LIMITED
RAJVAIBHAV HARMONY
RAJVAIBHAV INFRA
See every Nagpur project, with the district possession charts
Builder: KDR BUILDERS
KDR BUILDERS has 2 registrations on MahaRERA, including KDR PRIME and KDR ROYALE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that KDR PRIME shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KDR PRIME is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KDR PRIME?
The registered promoter entity is KDR BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KDR PRIME?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KDR PRIME?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KDR PRIME?
The professionals named in the filing: Architect: JITENDRA INGULKAR; Engineer: JITENDRA INGULKAR; Chartered Accountant: SAMEER DIVECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KDR PRIME?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback