ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / KCD Lumin

Registration lapsed No litigation declared Mixed project

KCD Lumin

By KCD Heritage Private Limited

RG-MH-43471 · RERA P51800017307 · Last updated on MahaRERA portal: 11 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
6 of 11Construction stages doneacross 2 buildings; furthest along: Staircases, 82%
1Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

KCD Lumin is a Mixed project by KCD Heritage Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017307 on 31 Jul 2018. Possession was promised by 28 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKCD Lumin
  • TypeMixed
  • Location
    • M.G. Road
    • Dahanukar Wadi
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800017307
  • ReraGenie IDRG-MH-43471

Builder

  • NameKCD Heritage Private Limited
  • Entity typeCompany
  • DirectorArun Kuttan
  • Other registrations3 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredJul 2018First promiseDec 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2018
  • Promised completion28 Dec 2024
  • Revised completionRevised to 28 Dec 2024 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kandivali Padma Kailash Co-operative Housing Society LimitedNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 82%.

Kandivali Padma Kailash Co-operative Housing Society Limited68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises66%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks82%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 11 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Closed/Covered64

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,681 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6133.05
Proposed, not sanctioned1,554 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSv Road Kandivali West Mumbai- 400067

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil S Jain and Sanjay S Jain
PartnerRole in project
KCD Heritage Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013745Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

EXT51800019390Dec 2022 → Dec 2024

Reason as filed by the promoterWe are not able complete project because of shortages of marital and lebour please grant us extension till 28/12/2024

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000079132SHEETALK T group03/05/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jul 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A DOI.pdf11 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Notice of resignation_-25042019-Manish Patel.pdf11 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank Details - KCD Lumin.pdf8 Apr 2024
Declaration in FORM BFile: Form B - KCD Lumin.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory disclousre - Lumin.pdf22 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual Audit Report 2223 KCD Lumin.pdf20 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Dec 23.pdf24 Jan 2024
Certificates of CA (Form 3)File: Form 3 Ca Certificate Dec 23.pdf24 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Arch cert - KCD Lumin - Dec 2023.pdf8 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Arch - KCD Lumin - Sep 2023.pdf19 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: fcc.pdf25 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - KCD Lumin - June 2023.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - KCD LUMIN - FY 2022-23.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf23 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Lumin 20-21.pdf27 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Lumin 21-22.pdf27 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert Lumin.pdf21 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engg cert- Lumin.pdf18 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2a.pdf7 Jan 2023
CERSAI detailsFile: CERSAI Declaration.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of innventory-lumin (1).pdf24 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A (4) (1).pdf15 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf13 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineers Certificate).pdf13 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2-A_1.pdf13 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: 2261987_FurtherCC_signed.pdf6 Aug 2021
Declaration about Commencement CertificateFile: 2261987_FurtherCC_signed.pdf6 Aug 2021
Proforma of Allotment letterFile: Draft Sale Agreement.pdf6 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: LUMIN 18-19.pdf26 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: LUMIN 19-20.pdf26 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate rera -padma.pdf19 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - padmakailash.pdf19 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCD LUMIN.pdf22 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: No progress letter.pdf14 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NO PROGRESS LETTER.pdf23 Apr 2019
Layout approvalFile: SECTION.pdf20 Jul 2018
Copy of Layout Approval (in case of layout)File: SECTION.pdf20 Jul 2018
Declaration in FORM BFile: Form B-Affidavit cum Declaration-ilovepdf-compressed.pdf20 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (1)-ilovepdf-compressed.pdf20 Jul 2018
Building plan approval or NA orderFile: 2118194_IOD_signed.pdf17 Jul 2018
Layout approvalFile: IOD issue plan.pdf17 Jul 2018
Copy of the legal title reportFile: Title Certificate KCD-ilovepdf-compressed.pdf17 Jul 2018
Details of encumbrancesFile: No encumbrances Certificate-ilovepdf-compressed.pdf17 Jul 2018
Copy of Layout Approval (in case of layout)File: IOD issue plan.pdf17 Jul 2018
Building Plan Approval (IOD)File: 2118194_IOD_signed.pdf17 Jul 2018
Certificates of CA (Form 3)File: CA certificate padmakailash Revised.pdf17 Jul 2018
Proforma of Allotment letterFile: Declaration for Agreement for Sale-ilovepdf-compressed.pdf17 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Declaration for CC.pdf16 Jul 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KCD Lumin on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dahanukar Wadi6,700+ in Mumbai Suburban

Builder: KCD Heritage Private Limited

KCD Heritage Private Limited has 4 registrations on MahaRERA, including KCD Lumin and KCD Jogesh Eva. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that KCD Lumin shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KCD Lumin is delayed beyond 28 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KCD Lumin?

The registered promoter entity is KCD Heritage Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KCD Lumin?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KCD Lumin?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KCD Lumin?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KCD Lumin?

The professionals named in the filing: Architect: Sunil S Jain and Sanjay S Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KCD Lumin?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KCD Lumin. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KCD Lumin to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.