Home / Browse projects / Thane, Maharashtra / KARRM RESIDENCY -4

Registration lapsed No litigation declared Residential / Group Housing project

KARRM RESIDENCY -4

By KARRM INFRASTRUCTURE PRIVATE LIMITED

RG-MH-21276 · RERA P51700003215 · Last updated on MahaRERA portal: 6 Apr 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 71 months past the filed date
  • 46 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2020Possession promised71 months past this date
86 of 154Construction stages doneacross 14 buildings; furthest along: External plumbing and external plaster, 95%
46Complaints at MahaRERAon this registration
Jump to the 13 documents Report an error

KARRM RESIDENCY -4 is a Residential / Group Housing project by KARRM INFRASTRUCTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700003215 on 5 Aug 2017. Possession was promised by 30 Nov 2020 and is now 71 months past that date. The completion date has moved by 18 months from the original filing. 46 complaints are on record with the regulator.

At a glance

Project

  • NameKARRM RESIDENCY -4
  • TypeResidential / Group Housing
  • Location
    • Dhasai
    • Shahapur
    • Thane
    • 421601
  • Pincode421601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003215
  • ReraGenie IDRG-MH-21276

Builder

  • NameKARRM INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorKETAL BABULAL PATEL
  • Other registrations4 more →
  • No longer live5 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

71 months past promisethis monthRegisteredAug 2017First promiseMay 2019Revised toNov 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Nov 2020
  • Revised completionRevised to 30 Nov 2020 (originally 31 May 2019)
  • Buildings14 building records
  • Documents filed13 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DARPANNA50000
SATHINA50000
AAZADNA50000
ANURODHNA50000
ANCHALNA50000
ANDAAZNA50000
AMRITNA50000
SANGAMNA50000
PAWANNA50000
NASEEBNA50000
ZINDAGINA50000
KRANTINA50000
ARPANNA50000
JYOTINA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building14

As on 6 Apr 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

86 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

DARPAN73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SATHI69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
AAZAD71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ANURODH71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ANCHAL65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ANDAAZ67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
AMRIT67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SANGAM74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PAWAN73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NASEEB72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ZINDAGI73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
KRANTI77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
ARPAN72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
JYOTI72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities20

As on 6 Apr 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes18%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes45%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes15%
Solid Waste Management And DisposalYes55%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Club HouseYes0%
Nana Nani ParkYes0%
Organic Waste CompositeYes0%
GardenYes0%
Swimming poolYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area36,867 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S. KARRM BUILDCONMumbai CityMumbai City

Approvals and building plan

Permissible FSI30605.2
Proposed, not sanctioned30,605 sq m
Buildings approved14
Buildings sanctioned14

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI, FORT - 400001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFOUZI AND ASSOCIATES (MR AAMIR)
EngineerFOUZI AND ASSOCIATES (MR ALIM FOUZI)
PartnerRole in project
KARRM INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001826May 2019 → May 2020

Reason as filed by the promoterWe state that due to unavoidable circumstances and that to beyond the control of the promoter we shall be unable to deliver the above mentioned project or on before 31/05/2019 as per registration granted under section 5 of the Real Estate (regulation and Development) Act,2016.further ,adding to that due to lack of liquidity and defaulter allottees we are lagging behind to complete the project or on before 31/05/2019. We expect to deliver the project on or before 31/05/2020

Litigation declared1

CaseCourtStatus
Special Civil Suit no 125/2009/2009Civil Judge S D Kalyan CourtAMENDED PLAINT

Complaints filed with MahaRERA46

Case no.ComplainantRespondentFiled
CC006000000057253PRASAD PRABHAKAR JAYWANTKARRM INFRASTRUCTURE PVT. LTD.22/12/2018
CC006000000012159Mr Namdev Ramchandra GhadgeKarrm Infrastructure Pvt.Ltd.26/11/2017
CC006000000044226Amol Rohidas MirajkarKarrm Infrastructure Private Limited03/07/2018
CC006000000056354AMOL MIRAJKARKARRM INFRASTRUCTURE PVT LTD29/09/2018
CC006000000023226NAMDEO ABA ULMEKKARRM INFRASTRUCTURE PVT. LTD.07/02/2018
CC006000000044106Shamala Dilip PatilKarrm Infrastructure Private Limited08/05/2018
CC006000000056787Ms. Shamala Dilip PatilKarrm Infrastructure Private Limited02/11/2018
CC006000000055430Ratan Ramesh SalunkheKARRM INFRASTRUCTURE PRIVATE LIMITED18/07/2018
CC006000000068155Rashmi Nikhil AsharKarrm Infrastructure Pvt. Limited20/02/2019
CC006000000056594VINOD NAIRKARRM INFRASTRUCTURE PRIVATE LIMITED19/12/2018
CC006000000210246Mr. Dilip AlveKarrm Infrastructure Pvt. Ltd.07/03/2022
CC006000000057372SUDHEENDRA N PANDURANGIKARRM INFRASTRUCTURE PRIVATE LIMITED19/12/2018
CC006000000057498Satish BhirudKarrm Infrastructure Pvt. Ltd.04/01/2019
CC006000000057697SHRADDHA SHARAD NARVEKARKARRM INFRASTRUCTURE PRIVATE LIMITED17/01/2019
CC006000000078613Pradnya S SamantKarrm Infrastructure Pvt Ltd24/03/2019
CC006000000110743Abhijit BorawakeKarrm Infrastructure Pvt Ltd28/08/2019
CC006000000194727Umasankar NistalaKarrm Infrastructure Pvt. Ltd.30/10/2020
CC006000000194728Umasankar NistalaKarrm Infrastructure Pvt. Ltd.30/10/2020
CC006000000110667Shailendra Kumar JainKarrm Infrastructures Private Limited23/08/2019
CC006000000209764Anand KondalkarRamakant Jadhav30/01/2022
CC006000000181974Mahendra J GuptaKarrm Infrastructure Pvt. Ltd Shahapur25/12/2019
CC006000000193185Hardeep Singh SainiKarrm Infrastructure Pvt Ltd08/05/2020
CC006000000193309UMESH H RANEkarma infrastructure pvt ltd13/01/2021
CC006000000193389Archana ShelkeKetan Babulal Patel09/07/2020
CC006000000193550Vinod kumar Premjibhai PatelKETAN B PATEL22/07/2020
CC006000000193588Ketayun NalladaruKarrm infrastructure26/07/2020
CC006000000193834Vaibhav B BondeKetan Patel24/02/2021
CC006000000194729RAVI NARENDRA SURTANIKarrm Infrastructure Private Limited13/11/2020
CC006000000195384Mr. Nisar Ahmad IshaqKarrm Infrastructure Pvt ltd28/12/2020
CC006000000195427Mr. Prem Prakash NarsingKarrm Infrastructure Pvt ltd01/07/2021
CC006000000195942RAMESHRAMCHANDRA KADAMKARRM INFRASTRUCTURE PVT LTD12/02/2021
CC006000000196428Sridharan NarayananKARRM INFRASTRUCTURE PVT LTD21/03/2021
CC006000000196538Kailashben Jiteshkumar RathodKarrm Infrastructure Pvt Ltd29/03/2021
CC006000000197733SONALI MANOHAR GHOLAPKARRM RESIDENCY28/08/2021
CC006000000198296SHARMAINE DSOUZAKARRM INFRASTRUCTURE PVT. LTD.09/09/2021
CC006000000198507SANGEETA SAHADEV GADEKARKARRM INFRASTRUCTURE PVT. LTD.02/10/2021
CC006000000210061Yash Pravin SolankiSATISH GANGADHARRAO PILLANGWAD19/02/2022
CC006000000241291Mr Neelmanikant Kamlakant Mishra and Mrs Neelam Neelmani MishraM/s Karrm Infrastructure Pvt Ltd31/05/2022
CC006000000375098Vipin Kumar SinghKarrm Infrastructure Pvt. Ltd.17/04/2023
CC006000000395948Smita Raj OrkeKarrm Infrastructure Pvt Ltd11/06/2023
CC006000000439663vaishali ujjwal dekateramakanth subhash jadhav16/03/2024
CC006000000591242Sunny Narendra SurtaniKarrm Infrastructure Private Limited25/07/2024
CC12400968Rupali Dinesh SharmaKARRM INFRASTRUCTURE PRIVATE LIMITED01/12/2024
CC12501009Rajani ShettigarKARRM INFRASTRUCTURE PRIVATE LIMITED23/03/2025
CC12501537Sunanda Rajesh Agawane and Rajesh Jaysing AgawaneKARRM INFRASTRUCTURE PRIVATE LIMITED09/05/2025
CC12601191Anand Sitaram KambleKARRM INFRASTRUCTURE PRIVATE LIMITED05/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed13

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: KR-4cc21-03-2012.pdf6 Apr 2018
Layout approvalFile: KR layout.PDF29 Jul 2017
Building plan approvalFile: Building Plan Layout (IOD) KR.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: KR layout.PDF29 Jul 2017
Building Plan Approval (IOD)File: Building Plan Layout (IOD) KR.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE KR SECTOR 4.pdf29 Jul 2017
PAN CardFile: PAN CARD KIPL.pdf28 Jul 2017
Copy of the legal title reportFile: Legal titleReport KR 4.pdf28 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE KR.pdf28 Jul 2017
Declaration in FORM BFile: Declaration in Form B - Promoter KR.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate KR 4.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of ENGINEER (FORM 2) KR.pdf28 Jul 2017
Proforma of Allotment letterFile: AFS and ALLOTMENT KR.pdf28 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KARRM RESIDENCY SECTOR 3VILLAGE DHASAI TALUKA SHAHPUR840CompletedDec 2014Late, Jul 2017
KARRM RESIDENCY SECTOR 2Village Dhasai Taluka Shahpur District Thane1,020CompletedDec 2014Late, Feb 2016
KARRM RESIDENCY SECTOR 1VILLAGE DHASAI TALUKA SHAHPUR540CompletedDec 2014Late, Feb 2016
KARRM GARDENS PROJECT 2VILLAGE AMBARNATH MC I TALUKA AMBARNATH DISTRICT THANE119CompletedDec 2014Late, Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 18 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KARRM RESIDENCY -4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhasai7,600+ in Thane

2 kmKARRM RESIDENCY -4Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: KARRM INFRASTRUCTURE PRIVATE LIMITED

KARRM INFRASTRUCTURE PRIVATE LIMITED has 5 registrations on MahaRERA, including KARRM PANCHTATVA -1 and KARRM PANCHTATVA-3. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that KARRM RESIDENCY -4 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KARRM RESIDENCY -4 is delayed beyond 30 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KARRM RESIDENCY -4?

The registered promoter entity is KARRM INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KARRM RESIDENCY -4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KARRM RESIDENCY -4?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KARRM RESIDENCY -4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KARRM RESIDENCY -4?

The professionals named in the filing: Architect: FOUZI AND ASSOCIATES (MR AAMIR); Engineer: FOUZI AND ASSOCIATES (MR ALIM FOUZI). Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KARRM RESIDENCY -4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KARRM RESIDENCY -4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KARRM RESIDENCY -4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.