KARRM RESIDENCY -4
By KARRM INFRASTRUCTURE PRIVATE LIMITED
RG-MH-21276 · RERA P51700003215 · Last updated on MahaRERA portal: 6 Apr 2018
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 71 months past the filed date
- 46 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KARRM RESIDENCY -4 is a Residential / Group Housing project by KARRM INFRASTRUCTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700003215 on 5 Aug 2017. Possession was promised by 30 Nov 2020 and is now 71 months past that date. The completion date has moved by 18 months from the original filing. 46 complaints are on record with the regulator.
At a glance
Project
- NameKARRM RESIDENCY -4
- TypeResidential / Group Housing
- Location
- Dhasai
- Shahapur
- Thane
- 421601
- Pincode421601
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700003215
- ReraGenie IDRG-MH-21276
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2017
- Promised completion30 Nov 2020
- Revised completionRevised to 30 Nov 2020 (originally 31 May 2019)
- Buildings14 building records
- Documents filed13 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DARPAN | NA | 5 | 0 | 0 | 0 | 0 |
| SATHI | NA | 5 | 0 | 0 | 0 | 0 |
| AAZAD | NA | 5 | 0 | 0 | 0 | 0 |
| ANURODH | NA | 5 | 0 | 0 | 0 | 0 |
| ANCHAL | NA | 5 | 0 | 0 | 0 | 0 |
| ANDAAZ | NA | 5 | 0 | 0 | 0 | 0 |
| AMRIT | NA | 5 | 0 | 0 | 0 | 0 |
| SANGAM | NA | 5 | 0 | 0 | 0 | 0 |
| PAWAN | NA | 5 | 0 | 0 | 0 | 0 |
| NASEEB | NA | 5 | 0 | 0 | 0 | 0 |
| ZINDAGI | NA | 5 | 0 | 0 | 0 | 0 |
| KRANTI | NA | 5 | 0 | 0 | 0 | 0 |
| ARPAN | NA | 5 | 0 | 0 | 0 | 0 |
| JYOTI | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building14
As on 6 Apr 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
86 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
DARPAN73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SATHI69%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
AAZAD71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ANURODH71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ANCHAL65%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ANDAAZ67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
AMRIT67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SANGAM74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PAWAN73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
NASEEB72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ZINDAGI73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
KRANTI77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 35% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
ARPAN72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
JYOTI72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities20
As on 6 Apr 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 18% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 45% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 15% |
| Solid Waste Management And Disposal | Yes | 55% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Club House | Yes | 0% |
| Nana Nani Park | Yes | 0% |
| Organic Waste Composite | Yes | 0% |
| Garden | Yes | 0% |
| Swimming pool | Yes | 0% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S. KARRM BUILDCON | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | FOUZI AND ASSOCIATES (MR AAMIR) |
| Engineer | FOUZI AND ASSOCIATES (MR ALIM FOUZI) |
| Partner | Role in project |
|---|---|
| KARRM INFRASTRUCTURE PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe state that due to unavoidable circumstances and that to beyond the control of the promoter we shall be unable to deliver the above mentioned project or on before 31/05/2019 as per registration granted under section 5 of the Real Estate (regulation and Development) Act,2016.further ,adding to that due to lack of liquidity and defaulter allottees we are lagging behind to complete the project or on before 31/05/2019. We expect to deliver the project on or before 31/05/2020
Litigation declared1
| Case | Court | Status |
|---|---|---|
| Special Civil Suit no 125/2009/2009 | Civil Judge S D Kalyan Court | AMENDED PLAINT |
Complaints filed with MahaRERA46
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000057253 | PRASAD PRABHAKAR JAYWANT | KARRM INFRASTRUCTURE PVT. LTD. | 22/12/2018 |
| CC006000000012159 | Mr Namdev Ramchandra Ghadge | Karrm Infrastructure Pvt.Ltd. | 26/11/2017 |
| CC006000000044226 | Amol Rohidas Mirajkar | Karrm Infrastructure Private Limited | 03/07/2018 |
| CC006000000056354 | AMOL MIRAJKAR | KARRM INFRASTRUCTURE PVT LTD | 29/09/2018 |
| CC006000000023226 | NAMDEO ABA ULMEK | KARRM INFRASTRUCTURE PVT. LTD. | 07/02/2018 |
| CC006000000044106 | Shamala Dilip Patil | Karrm Infrastructure Private Limited | 08/05/2018 |
| CC006000000056787 | Ms. Shamala Dilip Patil | Karrm Infrastructure Private Limited | 02/11/2018 |
| CC006000000055430 | Ratan Ramesh Salunkhe | KARRM INFRASTRUCTURE PRIVATE LIMITED | 18/07/2018 |
| CC006000000068155 | Rashmi Nikhil Ashar | Karrm Infrastructure Pvt. Limited | 20/02/2019 |
| CC006000000056594 | VINOD NAIR | KARRM INFRASTRUCTURE PRIVATE LIMITED | 19/12/2018 |
| CC006000000210246 | Mr. Dilip Alve | Karrm Infrastructure Pvt. Ltd. | 07/03/2022 |
| CC006000000057372 | SUDHEENDRA N PANDURANGI | KARRM INFRASTRUCTURE PRIVATE LIMITED | 19/12/2018 |
| CC006000000057498 | Satish Bhirud | Karrm Infrastructure Pvt. Ltd. | 04/01/2019 |
| CC006000000057697 | SHRADDHA SHARAD NARVEKAR | KARRM INFRASTRUCTURE PRIVATE LIMITED | 17/01/2019 |
| CC006000000078613 | Pradnya S Samant | Karrm Infrastructure Pvt Ltd | 24/03/2019 |
| CC006000000110743 | Abhijit Borawake | Karrm Infrastructure Pvt Ltd | 28/08/2019 |
| CC006000000194727 | Umasankar Nistala | Karrm Infrastructure Pvt. Ltd. | 30/10/2020 |
| CC006000000194728 | Umasankar Nistala | Karrm Infrastructure Pvt. Ltd. | 30/10/2020 |
| CC006000000110667 | Shailendra Kumar Jain | Karrm Infrastructures Private Limited | 23/08/2019 |
| CC006000000209764 | Anand Kondalkar | Ramakant Jadhav | 30/01/2022 |
| CC006000000181974 | Mahendra J Gupta | Karrm Infrastructure Pvt. Ltd Shahapur | 25/12/2019 |
| CC006000000193185 | Hardeep Singh Saini | Karrm Infrastructure Pvt Ltd | 08/05/2020 |
| CC006000000193309 | UMESH H RANE | karma infrastructure pvt ltd | 13/01/2021 |
| CC006000000193389 | Archana Shelke | Ketan Babulal Patel | 09/07/2020 |
| CC006000000193550 | Vinod kumar Premjibhai Patel | KETAN B PATEL | 22/07/2020 |
| CC006000000193588 | Ketayun Nalladaru | Karrm infrastructure | 26/07/2020 |
| CC006000000193834 | Vaibhav B Bonde | Ketan Patel | 24/02/2021 |
| CC006000000194729 | RAVI NARENDRA SURTANI | Karrm Infrastructure Private Limited | 13/11/2020 |
| CC006000000195384 | Mr. Nisar Ahmad Ishaq | Karrm Infrastructure Pvt ltd | 28/12/2020 |
| CC006000000195427 | Mr. Prem Prakash Narsing | Karrm Infrastructure Pvt ltd | 01/07/2021 |
| CC006000000195942 | RAMESHRAMCHANDRA KADAM | KARRM INFRASTRUCTURE PVT LTD | 12/02/2021 |
| CC006000000196428 | Sridharan Narayanan | KARRM INFRASTRUCTURE PVT LTD | 21/03/2021 |
| CC006000000196538 | Kailashben Jiteshkumar Rathod | Karrm Infrastructure Pvt Ltd | 29/03/2021 |
| CC006000000197733 | SONALI MANOHAR GHOLAP | KARRM RESIDENCY | 28/08/2021 |
| CC006000000198296 | SHARMAINE DSOUZA | KARRM INFRASTRUCTURE PVT. LTD. | 09/09/2021 |
| CC006000000198507 | SANGEETA SAHADEV GADEKAR | KARRM INFRASTRUCTURE PVT. LTD. | 02/10/2021 |
| CC006000000210061 | Yash Pravin Solanki | SATISH GANGADHARRAO PILLANGWAD | 19/02/2022 |
| CC006000000241291 | Mr Neelmanikant Kamlakant Mishra and Mrs Neelam Neelmani Mishra | M/s Karrm Infrastructure Pvt Ltd | 31/05/2022 |
| CC006000000375098 | Vipin Kumar Singh | Karrm Infrastructure Pvt. Ltd. | 17/04/2023 |
| CC006000000395948 | Smita Raj Orke | Karrm Infrastructure Pvt Ltd | 11/06/2023 |
| CC006000000439663 | vaishali ujjwal dekate | ramakanth subhash jadhav | 16/03/2024 |
| CC006000000591242 | Sunny Narendra Surtani | Karrm Infrastructure Private Limited | 25/07/2024 |
| CC12400968 | Rupali Dinesh Sharma | KARRM INFRASTRUCTURE PRIVATE LIMITED | 01/12/2024 |
| CC12501009 | Rajani Shettigar | KARRM INFRASTRUCTURE PRIVATE LIMITED | 23/03/2025 |
| CC12501537 | Sunanda Rajesh Agawane and Rajesh Jaysing Agawane | KARRM INFRASTRUCTURE PRIVATE LIMITED | 09/05/2025 |
| CC12601191 | Anand Sitaram Kamble | KARRM INFRASTRUCTURE PRIVATE LIMITED | 05/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed13
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement Certificates / NA Order for plotted developmentFile: KR-4cc21-03-2012.pdf | 6 Apr 2018 |
| Layout approvalFile: KR layout.PDF | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Layout (IOD) KR.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: KR layout.PDF | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Layout (IOD) KR.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE KR SECTOR 4.pdf | 29 Jul 2017 |
| PAN CardFile: PAN CARD KIPL.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: Legal titleReport KR 4.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE KR.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Declaration in Form B - Promoter KR.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate KR 4.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of ENGINEER (FORM 2) KR.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: AFS and ALLOTMENT KR.pdf | 28 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| KARRM RESIDENCY SECTOR 3 | VILLAGE DHASAI TALUKA SHAHPUR | 840 | Completed | Dec 2014 | Late, Jul 2017 |
| KARRM RESIDENCY SECTOR 2 | Village Dhasai Taluka Shahpur District Thane | 1,020 | Completed | Dec 2014 | Late, Feb 2016 |
| KARRM RESIDENCY SECTOR 1 | VILLAGE DHASAI TALUKA SHAHPUR | 540 | Completed | Dec 2014 | Late, Feb 2016 |
| KARRM GARDENS PROJECT 2 | VILLAGE AMBARNATH MC I TALUKA AMBARNATH DISTRICT THANE | 119 | Completed | Dec 2014 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 13 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep KARRM RESIDENCY -4 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dhasai7,600+ in Thane
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
BELLA VISTA PHASE 8
INDO ASIAN BUILDCON PVT LTD
RUSTOMJEE BELLE VUE
KEYSTONE REALTORS LIMITED
THE VENISCAPE
MIVAAN BUILDCON PRIVATE LIMITED
VISION SKY WORLD
M/S VISION SKY WORLD
Sunteck FORESTWorld 1
SUNTECK REALTY HOLDINGS PVT LTD
Sunteck FORESTWorld 2
SUNTECK REALTY HOLDINGS PVT LTD
See every Thane project, with the district possession charts
Builder: KARRM INFRASTRUCTURE PRIVATE LIMITED
KARRM INFRASTRUCTURE PRIVATE LIMITED has 5 registrations on MahaRERA, including KARRM PANCHTATVA -1 and KARRM PANCHTATVA-3. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that KARRM RESIDENCY -4 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KARRM RESIDENCY -4 is delayed beyond 30 Nov 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KARRM RESIDENCY -4?
The registered promoter entity is KARRM INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KARRM RESIDENCY -4?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KARRM RESIDENCY -4?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KARRM RESIDENCY -4?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KARRM RESIDENCY -4?
The professionals named in the filing: Architect: FOUZI AND ASSOCIATES (MR AAMIR); Engineer: FOUZI AND ASSOCIATES (MR ALIM FOUZI). Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KARRM RESIDENCY -4?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback