ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / KANCHANGANGA LEGACY

Registered No litigation declared Residential / Group Housing project

KANCHANGANGA LEGACY

By VISHAL INFRAVENTURE

RG-MH-92064 · RERA P50500052804 · Last updated on MahaRERA portal: 12 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
90 of 90Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 129 documents Report an error

KANCHANGANGA LEGACY is a Residential / Group Housing project by VISHAL INFRAVENTURE in Nagpur, Maharashtra, registered with MahaRERA as P50500052804 on 5 Oct 2023. Possession is promised by 31 Dec 2030. 0 of the 90 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameKANCHANGANGA LEGACY
  • TypeResidential / Group Housing
  • Location
    • BELTARODI
    • MOUJE BELTARODI
    • Nagpur (Rural)
    • Nagpur
    • 440037
  • Pincode440037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500052804
  • ReraGenie IDRG-MH-92064

Builder

  • NameVISHAL INFRAVENTURE
  • Entity typePartnership
  • PartnersASHISH MADHUKAR RAHATE, SOHAM SAMIR KUNAWAR, VIVEK TRIMBAK KUNAWAR, SUNIL GANPATRAO KASHIKAR

Key dates

this monthRegisteredOct 2023PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Oct 2023
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed129 files

Current status

0%0 of 90 units booked
6.0%Work done, per cost certificate

Figures as on 12 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANCHANGANGA LEGACYNA161590090

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

KANCHANGANGA LEGACY: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,138 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBESA-PIPLA NAGARPANCHAYAT
Permissible FSI6877.27
Proposed, not sanctioned6,877 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWARDHA ROAD NAGPUR-440015
Estimated costRs 16.15 cr
Cost incurredRs 96.88 lakh
Work done6.0%
BuildingWingEstimatedIncurred
KANCHANGANGA LEGACYNARs 16.15 crRs 96.88 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVAISHALI GAIKWAD
EngineerKAMAL SHAHU
EngineerRAVINDRA KUMAR WARUDKAR
EngineerSANJAY DHOLE
Chartered AccountantANKIT TALREJA
Chartered AccountantG A D & ASSOCIATES
Chartered AccountantUTSAV SUMIT & ASSOCIATES
Chartered AccountantSUMIT SANTOSH AGRAWAL & ASSOCIATES
PartnerRole in project
VISHAL INFRAVENTURE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed129

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 129 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 KANCHANGANGA LEGACY MAR-2026.pdf12 Apr 2026
Withdrawal Update Form 2File: FORM-2 KANCHANGANGA LEGACY MAR-2026.pdf12 Apr 2026
Withdrawal Update Form 3File: FORM-3 KANCHANGANGA LEGACY MAR-2026.pdf12 Apr 2026
Withdrawal Update Form 1File: FORM-1 KANCHANGANGA LEGACY MAR-2026.pdf11 Apr 2026
Withdrawal Update Form 2File: FORM-2 KANCHANGANGA LEGACY MAR-2026.pdf11 Apr 2026
Withdrawal Update Form 3File: FORM-3 KANCHANGANGA LEGACY MAR-2026 SCAN SIZE.pdf11 Apr 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 DEC-2023.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 MAR-2024.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 JUN-2024.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 SEP-2024.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 DEC-2024.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 MAR-2025.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 SEP-2025.pdf11 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 DEC-2025.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 DEC-2023.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 MAR-2024.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 JUN-2024.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 SEP-2024.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 DEC-2024.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 MAR-2025.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 SEP-2025.pdf11 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 DEC-2025.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 DEC-2023.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 MAR-2024 COMM.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 JUN-2024 COMM.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 SEP-2024 COMM.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 DEC-2024.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 MAR-2025 COMM.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 SEP-2025 COMM.pdf11 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 DEC-2025 COMM.pdf11 Mar 2026
Withdrawal Update Form 1File: FORM-1.pdf10 Mar 2026
Withdrawal Update Form 1File: FORM-1.pdf10 Mar 2026
Withdrawal Update Form 1File: KANCHANGANGA LEGACY FORM-1 JUN-2025.pdf10 Mar 2026
Withdrawal Update Form 2File: FORM-2.pdf10 Mar 2026
Withdrawal Update Form 2File: FORM-2.pdf10 Mar 2026
Withdrawal Update Form 2File: KANCHANGANGA LEGACY FORM-2 JUN-2025.pdf10 Mar 2026
Withdrawal Update Form 3File: FORM-3.pdf10 Mar 2026
Withdrawal Update Form 3File: FORM-3.pdf10 Mar 2026
Withdrawal Update Form 3File: KANCHANGANGA LEGACY FORM-3 JUN-2025 COMM.pdf10 Mar 2026
Form 2A (FY 2023-2024)File: KANCHANGANGA LEGACY FORM-2A MAR-2024.pdf10 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A MAR-2025.pdf10 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 DEC-2023.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 DEC-2023.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-3 DEC-2023.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD DEC-2023.pdf9 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 MAR-2024.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 MAR-2024.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-3 MAR-2024.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD MAR-2024.pdf9 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 JUN-2024.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 JUN-2024.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-2 JUN-2024.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD JUN-2024.pdf9 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 SEP-2024.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 SEP-2024.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-3 SEP-2024.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD SEP-2024.pdf9 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 DEC-2024.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 DEC-2024.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-3 DEC-2024.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD DEC-2024.pdf9 Mar 2026
Form 1File: Kanchanganga Legacy FORM-1 DEC-2023.pdf9 Mar 2026
Form 2File: Kanchanganga Legacy FORM-2 DEC-2023.pdf9 Mar 2026
Form 3File: Kanchanganga Legacy FORM-3 DEC-2023.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD DEC-2023.pdf9 Mar 2026
Withdrawal Update Form 1File: FORM-1.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM-2.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM-3.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM-1 JUN-25.pdf24 Oct 2025
Withdrawal Update Form 1File: FORM-1 SEPT-25.pdf24 Oct 2025
Withdrawal Update Form 2File: FORM-2 JUN-25 KANCHANGANGA LEGACY.pdf24 Oct 2025
Withdrawal Update Form 2File: FORM-2 SEPT-25 KANCHANGANGA LEGACY.pdf24 Oct 2025
Withdrawal Update Form 3File: FORM-3 JUN-25 SCANNED COMPRESSED.pdf24 Oct 2025
Withdrawal Update Form 3File: FORM-3 SEPT-25 SCANNED COMPRESSED.pdf24 Oct 2025
Form 5 (FY 2023-2024)File: FORM-5 MAR-24.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: FORM-5 MAR- 25 SCANNED.pdf13 Oct 2025
Rera29 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf13 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kanchanganga Legacy_Dec-2024.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Kanchanganga Legacy_Dec-2024.pdf11 Feb 2025

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANCHANGANGA LEGACY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUJE BELTARODI2,800+ in Nagpur

2 kmKANCHANGANGA LEGACYCompleted 25Lapsed / revoked 10Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: VISHAL INFRAVENTURE

VISHAL INFRAVENTURE has 1 registration on MahaRERA, including KANCHANGANGA LEGACY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if KANCHANGANGA LEGACY is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANCHANGANGA LEGACY?

The registered promoter entity is VISHAL INFRAVENTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANCHANGANGA LEGACY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KANCHANGANGA LEGACY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANCHANGANGA LEGACY?

The professionals named in the filing: Architect: VAISHALI GAIKWAD; Engineer: KAMAL SHAHU; Engineer: RAVINDRA KUMAR WARUDKAR; Engineer: SANJAY DHOLE; Chartered Accountant: ANKIT TALREJA; Chartered Accountant: G A D & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANCHANGANGA LEGACY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANCHANGANGA LEGACY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANCHANGANGA LEGACY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.