Home / Browse projects / Pune, Maharashtra / KALPAK HOMES KIRKATWADI PHASE II

Completed No litigation declared Residential / Group Housing project

KALPAK HOMES KIRKATWADI PHASE II

By SHUBHANKAR DEVELOPERS

RG-MH-02474 · RERA P52100000741 · Last updated on MahaRERA portal: 5 Jun 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 51 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
6Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

KALPAK HOMES KIRKATWADI PHASE II is a Residential / Group Housing project by SHUBHANKAR DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100000741 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Mar 2024. The completion date has moved by 51 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameKALPAK HOMES KIRKATWADI PHASE II
  • TypeResidential / Group Housing
  • Location
    • KIRKATWADI
    • Haveli
    • Pune
    • 411024
  • Pincode411024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000741
  • ReraGenie IDRG-MH-02474

Builder

  • NameSHUBHANKAR DEVELOPERS
  • Entity typePartnership
  • PartnerAJIT BELVALKAR
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Mar 2024
  • Revised completionRevised to 30 Mar 2024 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PHASE IINA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

PHASE II: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes44%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes25%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed183

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots183
Closed/Covered77
Open Space106

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,980 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RAJEEV PURUSHOTTAM BODASPune (M Corp.)Pune

Approvals and building plan

Permissible FSI9590.64
Proposed, not sanctioned7,693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APARTMENT GROUND FLOOR, PLOT NO 3 CTS NO 870, BHANDARKAR ROAD PUNE 411004

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTADPL
EngineerJW CONSULTANT
PartnerRole in project
SHUBHANKAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009027Dec 2019 → Sep 2023

Reason as filed by the promoterThe project got delayed and stalled due to financial issues as the financial institutions had own problems / stopped credit supply . Now we have been approved credit facility for entire balance work under Government scheme ‘ SWAMIH “ and with it we can complete the project as stipulated here .

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000033482Mr. Kalidas Vasant YenpureM/s. Shubhankar Developers01/10/2019
CC005000000053992Bhagwan Ramchanra GawaliM/s Shubhankar Developers06/02/2020
CC005000000064614Rajendra Shankar Phalke and Mrs. Archana Rajendra PhalkeM/s. Shubhankar Developers through its Partner Sameer Sharatchandra Belvalkar01/10/2020
CC005000000064690Babita Bhagchand JadhavSameer Sharatchandra Belvalkar02/10/2020
CC005000000064873Rohit Vinayak JoshiShubhankar Developers29/11/2020
CC005000000471497Pramod Baburao HinganeShubhankar Kalpak Builders Pvt Ltd08/08/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Apr 2025

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 2024.pdf5 Jun 2025
Certificates of CA (Form 3)File: FORM 3 MARCH 2025.pdf4 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH 2024.pdf4 Jun 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD MARCH 2024.pdf3 Jun 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD MARCH 2025.pdf3 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A MARCH 2024.pdf3 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf3 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: FORM 5.pdf3 Jun 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Kalpak Homes Kirkatwadi Phase II Soceity Reg Certificate.pdf17 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kalpak Homes PH-II FINAL OC.pdf17 Apr 2025
Certificates of CA (Form 3)File: FORM 3 KALPAK KIRKATWDI PH II.pdf20 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC F.pdf30 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC F.pdf30 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SKBPL FROM 5.pdf30 Dec 2023
Certificates of CA (Form 3)File: FORM 3.pdf28 Nov 2023
Certificates of CA (Form 3)File: KALPAK KIRKATWADI PH II.pdf4 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kirkatwadi Form 5.pdf21 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf3 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.pdf3 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf26 Aug 2022
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.PDF19 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf8 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf8 Aug 2022
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf6 Aug 2022
Certificates of CA (Form 3)File: CA Certificate March 2021.pdf23 May 2022
Certificates of CA (Form 3)File: CA Certificate June 2021.pdf23 May 2022
Certificates of CA (Form 3)File: CA Certificate Sept 2021.pdf23 May 2022
Certificates of CA (Form 3)File: CA Certificate Dec 2021.pdf23 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kalpak homes kirkatwadi phase II.pdf31 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Declaration about Commencement Certificate.pdf17 Dec 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf17 Dec 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_book inventory.pdf17 Dec 2021
Certificates of CA (Form 3)File: Form 3_CA Certificate_.pdf26 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_Annual Report.pdf26 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer's Certificate-K wadi Ph 2 site- 2019-2020.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer's Certificate-K wadi Ph 2 site- 2020-2021.pdf23 Jun 2021
Declaration about Commencement CertificateFile: C C Pink zone.pdf22 Jun 2021
Disclosure of sold/ booked inventoryFile: Kalpak Homes Kirkatwadi Phase II-Sold and Unsold Inventory.pdf22 Jun 2021
Building plan approvalFile: revised layout 1.pdf4 Jun 2021
Building plan approvalFile: revised layout 1.pdf4 Jun 2021
Building plan approvalFile: 01-05_compressed.pdf4 Jun 2021
Building plan approvalFile: 05-05_compressed.pdf4 Jun 2021
Building Plan Approval (IOD)File: revised layout 1.pdf4 Jun 2021
Building Plan Approval (IOD)File: revised layout 1.pdf4 Jun 2021
Building Plan Approval (IOD)File: 01-05_compressed.pdf4 Jun 2021
Building Plan Approval (IOD)File: 05-05_compressed.pdf4 Jun 2021
Certificates of CA (Form 3)File: CA Certificate dated 30-6-2020.pdf2 Nov 2020
Certificates of CA (Form 3)File: CA Certificate dated 30-9-2020.pdf2 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf2 Nov 2020
OtherFile: Vakalatnama.pdf24 Sep 2020
OtherFile: Written statement in RERA complaint.pdf24 Sep 2020
OtherFile: Authority Letter - Siddhi Kulkarni.pdf21 Sep 2020
Certificates of CA (Form 3)File: KALPAK KIRKATWADI.pdf11 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - KKW Ph II.pdf6 Jan 2020
Details of encumbrancesFile: Anand Rathi - details of encumbrances.pdf27 Apr 2019
Certificates of CA (Form 3)File: KALPAK KIRKATWADI PH II CA CERTIFICATE.pdf3 Jan 2019
Certificates of CA (Form 3)File: CA FORM 3.pdf27 Nov 2018
Certificates of CA (Form 3)File: Form 3.pdf27 Nov 2018
Certificates of CA (Form 5)File: FORM 5.pdf27 Nov 2018
Proforma of Allotment letterFile: KW_II_RERA_AGREEMENT and ALLOTTMENT-rev 1.pdf4 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf20 Jul 2017
Certificates of CA (Form 3)File: Shubhankar CA Certificate Maha RERA.pdf20 Jul 2017
Declaration in FORM BFile: Kalpak Kirkatwadi Ph II Form B.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate.pdf19 Jul 2017
Proforma of Allotment letterFile: KW_II_RERA_AGREEMENT_ALLOTMENT.pdf19 Jul 2017
Copy of the legal title reportFile: TSR.pdf14 Jul 2017
Details of encumbrancesFile: KH-Kirkatwadi Phase II Encumbrances Certificate.pdf14 Jul 2017
PAN CardFile: SHUBHANKAR DEV PAN.pdf13 Jul 2017
Layout approvalFile: scan029.pdf23 Jun 2017
Building plan approvalFile: scan030.pdf23 Jun 2017
Building plan approvalFile: scan031.pdf23 Jun 2017
Building plan approvalFile: scan032.pdf23 Jun 2017
Copy of Layout Approval (in case of layout)File: scan029.pdf23 Jun 2017
Building Plan Approval (IOD)File: scan030.pdf23 Jun 2017
Building Plan Approval (IOD)File: scan031.pdf23 Jun 2017
Building Plan Approval (IOD)File: scan032.pdf23 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: SCAN.pdf23 Jun 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 51 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALPAK HOMES KIRKATWADI PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIRKATWADI13,700+ in Pune

2 kmKALPAK HOMES KIRKATWADI Completed 12Lapsed / revoked 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: SHUBHANKAR DEVELOPERS

SHUBHANKAR DEVELOPERS has 5 registrations on MahaRERA, including KALPAK HOMES KIRKATWADI PHASE II and Ayush Park. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KALPAK HOMES KIRKATWADI PHASE II is delayed beyond 30 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALPAK HOMES KIRKATWADI PHASE II?

The registered promoter entity is SHUBHANKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALPAK HOMES KIRKATWADI PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KALPAK HOMES KIRKATWADI PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KALPAK HOMES KIRKATWADI PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALPAK HOMES KIRKATWADI PHASE II?

The professionals named in the filing: Architect: TADPL; Engineer: JW CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALPAK HOMES KIRKATWADI PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALPAK HOMES KIRKATWADI PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALPAK HOMES KIRKATWADI PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.