Home / Browse projects / Mumbai City, Maharashtra / KALIKUND HEIGHTS
KALIKUND HEIGHTS
RG-MH-90927 · RERA P51900017733 · Last updated on MahaRERA portal: 30 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 70 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KALIKUND HEIGHTS is a Others project by KALIKUND DEVELOPERS in Mumbai City, Maharashtra, registered with MahaRERA as P51900017733 on 11 Sep 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 70 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameKALIKUND HEIGHTS
- TypeOthers
- Location
- NOSHIR BHARUCHA MARG
- GRANT ROAD WEST
- Mumbai City
- 400007
- Pincode400007
- RERA no.P51900017733
- ReraGenie IDRG-MH-90927
Builder
- NameKALIKUND DEVELOPERS
- Entity typePartnership
- PartnersPOPATLAL VARDHAN, DILIP CHANDAN, NARESH MEHTA, CHUNILAL CHANDAN, VIJAY CHANDAN, SOHINI VARDHAN, HASTIMAL BOTHRA, RAMESH BOTHRA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Sep 2018
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 28 Feb 2021)
- Buildings1 building record
- Documents filed109 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KALIKUND HEIGHTS WING A | NA | 39 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.
KALIKUND HEIGHTS WING A: 88% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 65% |
Progress on shared amenities15
As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIL PATIL |
| Architect | SKYLINE ARCHITECTS |
| Engineer | STRUCT BOMBAY CONSULTANT |
| Partner | Role in project |
|---|---|
| KALIKUND DEVELOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTwo Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A).
Reason as filed by the promoterTwo Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A).
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.85% allottees for purpose of extension of RERA registration period of the said project.
Litigation declared5
| Case | Court | Status |
|---|---|---|
| CONPW/47/2016/2016 | HIGH COURT | PENDING |
| APPW/62/2014/2014 | HIGH COURT | PENDING |
| RAE/201460/2008/2008 | SMALL CAUSES COURT | PENDING |
| RAD/200162/2012/2012 | SMALL CAUSES COURT | DISMISSED |
| RAE/200535/2008/2008 | SMALL CAUSES COURT | PENDING |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000397171 | suresh Mohanlal Mehta | Kalikund developers | 21/08/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Sep 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jun 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed109
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Kalikund Heights as on March 2026.pdf | 30 Apr 2026 |
| Form 2File: Form 2 - Kalikund Heights as on March 2026.pdf | 30 Apr 2026 |
| Form 3File: Form 3 - Kalikund Heights as on March 2026.pdf | 30 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Kalikund Heights as on March 2026.pdf | 30 Apr 2026 |
| Form 1File: Form 1 - Kalikund Heights as on June 2025.pdf | 16 Jan 2026 |
| Form 2File: Form 2 - Kalikund Heights as on June 2025.pdf | 16 Jan 2026 |
| Form 3File: Form 3 - Kalikund Heights as on June 2025.pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Kalikund Heights as on June 2025.pdf | 16 Jan 2026 |
| Form 1File: Form 1 - Kalikund Heights as on Sept 2025.pdf | 16 Jan 2026 |
| Form 2File: Form 2 - Kalikund Heights as on Sept 2025.pdf | 16 Jan 2026 |
| Form 3File: Form 3 - Kalikund Heights as on Sep 2025.pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Kalikund Heights as on Sep 2025.pdf | 16 Jan 2026 |
| Form 1File: Form 1 - Kalikund Heights as on Dec 2025.pdf | 16 Jan 2026 |
| Form 2File: Form 2 - Kalikund Heights as on Dec 2025.pdf | 16 Jan 2026 |
| Form 3File: Form 3 - Kalikund Heights as on Dec 2025.pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Kalikund Heights as on Dec 2025.pdf | 16 Jan 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 March 2019.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form 1 March 2020.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form 1 March 2021.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form 1 March 2022.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Form 1 March 2023.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Form 1 June 2024.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Form 1 Sept 2024.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Form 1 Dec 2024.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Form 1 March 2025.pdf | 23 Jun 2025 |
| Certificates of CA (Form 3)File: 13 Form 3 Kalikund Heights 30-09-2024 - Signed_compressed.pdf | 23 Jun 2025 |
| Certificates of CA (Form 3)File: 14 Form 3 Kalikund Heights 31-12-2024 - Signed.pdf | 23 Jun 2025 |
| Certificates of CA (Form 3)File: 15 Form 3 Kalikund Heights 31-03-2025 - Signed.pdf | 23 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form 2 - Sep 2024 - Signed.pdf | 23 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Form 2 - Dec 2024 - Signed.pdf | 23 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Form 2 - March 2025 - Signed.pdf | 23 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Kalikund Heights for FY 2019-20 - Signed.pdf | 23 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: F5 kalikund.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 31032019.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 31032020.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 31032021.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 31032022.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 31032023.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 31032024.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 30062024.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 30092024.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 30122024.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 31032025.pdf | 4 May 2025 |
| Certificates of CA (Form 3)File: Form 3 Kalikund Heights 30-09-2024.pdf | 4 May 2025 |
| Certificates of CA (Form 3)File: Certified Form 3 Kalikund Heights 31-12-2024.pdf | 4 May 2025 |
| Certificates of CA (Form 3)File: Form 3 Kalikund Heights 31-03-2025.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sep 2024.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2024.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 2025.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jun 24.pdf | 19 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 24.pdf | 19 Jul 2024 |
| Certificates of CA (Form 5)File: Form 5 17-18 (2).pdf | 19 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19 (2).pdf | 19 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 11 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 11 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 11 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 19.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 20.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 21.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 22.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 23.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 24.pdf | 8 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 19.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 20.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 21.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 22.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 23.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Mar 24.pdf | 8 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 8 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kalikund Heights.pdf | 5 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf | 19 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 19 Jun 2024 |
| Declaration in FORM BFile: Form B Kalikund Heights .pdf | 10 Jun 2024 |
| CERSAI detailsFile: Declaration of CERSAI.pdf | 10 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A .pdf | 10 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 10 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 109 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KALIKUND HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GRANT ROAD WEST780+ in Mumbai City
AARADHYA AVAAN
SHREEPATI SKIES (R R CHATURVEDI)
The Empire Tower
Samak Constructions Pvt. Ltd
Golden Navkar
GOLDEN REALTY (BALARAM STREET)
BELFORT BAY - MUMBADEVI
SHAILENDRA REALTORS PVT. LTD.
SHUKRIYA ELITE TOWER
ELITE CASTLES PRIVATE LIMITED
NIRVAANA PEARL
Nirvaana Lifespace LLP
See every Mumbai City project, with the district possession charts
Builder: KALIKUND DEVELOPERS
KALIKUND DEVELOPERS has 1 registration on MahaRERA, including KALIKUND HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if KALIKUND HEIGHTS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KALIKUND HEIGHTS?
The registered promoter entity is KALIKUND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KALIKUND HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KALIKUND HEIGHTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KALIKUND HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KALIKUND HEIGHTS?
The professionals named in the filing: Architect: ANIL PATIL; Architect: SKYLINE ARCHITECTS; Engineer: STRUCT BOMBAY CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KALIKUND HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback