ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KAILASH HEIGHTS

Completed No litigation declared Others project

KAILASH HEIGHTS

By KAILASH DEVELOPERS

RG-MH-25712 · RERA P99000008653 · Last updated on MahaRERA portal: 11 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 54 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2024Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

KAILASH HEIGHTS is a Others project by KAILASH DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000008653 on 19 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2024. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NameKAILASH HEIGHTS
  • TypeOthers
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000008653
  • ReraGenie IDRG-MH-25712

Builder

  • NameKAILASH DEVELOPERS
  • Entity typePartnership
  • Other registrations3 more →
  • Completed2 of 4

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toJun 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAILASH HEIGHTSNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

KAILASH HEIGHTS: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 11 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,274 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5728.36
Proposed, not sanctioned5,728 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 6 TO 9 NEAR NEW VIVA COLLAGE MANIBAI GOPAL RESIDENCY, DMART ROAD, VIRAR WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY WADE AND ASSOCIATES
EngineerSHAH AND GATANI ASSOCIATES
PartnerRole in project
KAILASH DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000005325Dec 2019 → Dec 2020

Reason as filed by the promoterRespected Sir, We have already applied for the Occupancy certificate towards the authority as on 13th August 2019. However still we are in process of the obtaining of Occupancy Certificate from the VVCMC Authority as on date. We have already uploaded Form 4 as obtained by architect in the respect of above project. We request you to kindly extend the Date of Completion so as to obtain certificate from the authority. Thanking You

EXT99000010197Dec 2019 → Jun 2022

Reason as filed by the promoterRespected Sir, We Promoter of above mentioned project wants to state as follows: - 1. Completion of Project: - We promoters of the above mentioned project have timely completed all the construction and finishing work of the project. We are enclosing form 4 of architect stating completion of Project, for your ready reference. 2. Application of Occupancy Certificate: - We had made application for grant of Occupancy Certificate to the project 13/08/2019, which is Still Pending with the Town Planning Department of Municipal Corporation i.e. VVCMC. We are enclosing copy of same for your reference.

EXT99000012079Dec 2019 → Jun 2024

Reason as filed by the promoterAs per letter attached

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: OC COPY.pdf11 Apr 2025
Details of encumbrancesFile: Financial Encumbrance.pdf29 Jun 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf29 Jun 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf29 Jun 2024
Declaration in FORM BFile: 3 FORM-B.pdf29 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM-1.pdf29 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1A-Form 2A site supervisor.pdf29 Jun 2024
CERSAI detailsFile: CERSAI.pdf29 Jun 2024
Certificates of CA (Form 3)File: FORM - 3.pdf29 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 5 Annexure A Discloser of interest partner - Ask Sir.pdf29 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1B-Form-5 Kailash Heights 22-23.pdf29 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 6 Declaration of seprate Bank Ac - Ask Sir.pdf29 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold and Unsold.pdf14 Jun 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: KAILASH HEIGHTS SOCEITY CERTIFICATE.pdf25 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KAILASH HEIGHTS SCAN.pdf12 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KAILASH HEIGHTS SCAN.pdf12 Aug 2021
Declaration about Commencement CertificateFile: FORMAT- D.pdf13 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A B C.pdf13 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A B C.pdf13 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD USOLD B C FINAL.pdf13 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018.pdf13 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019.pdf13 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2019.pdf13 Jul 2021
Architect’s Certificate on Completion of Project (Form 4)File: kailash heights 1.pdf2 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: KAILASH HEIGHTS.pdf2 Jun 2021
Certificates of CA (Form 5)File: Kailash Heights.pdf23 Oct 2019
Certificates of CA (Form 5)File: Kailash Devlopers - heights.pdf11 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech certificate.pdf10 Aug 2018
Certificates of CA (Form 3)File: CA certificate upload.pdf10 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf6 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE-ilovepdf-compressed.pdf6 Nov 2017
Certificates of CA (Form 3)File: CA CERTIFICATE FINAL.pdf6 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf30 Jul 2017
Certificates of CA (Form 3)File: KAILASH HEIGHTS ca.pdf30 Jul 2017
Building plan approvalFile: BUILDING PLAN.pdf29 Jul 2017
Layout approvalFile: Leout.pdf29 Jul 2017
PAN CardFile: Pan Card.pdf29 Jul 2017
Copy of the legal title reportFile: legal title report KAILASH-DEV-6BC.pdf29 Jul 2017
Details of encumbrancesFile: FORM B FINAL.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Leout.pdf29 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf29 Jul 2017
Proforma of Allotment letterFile: agreement for sale final.pdf29 Jul 2017
Declaration in FORM BFile: FORM B.pdf28 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 54 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAILASH HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmKAILASH HEIGHTSCompleted 36Lapsed / revoked 21Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: KAILASH DEVELOPERS

KAILASH DEVELOPERS has 4 registrations on MahaRERA, including KAILASH HEIGHTS and KAILASH TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if KAILASH HEIGHTS is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAILASH HEIGHTS?

The registered promoter entity is KAILASH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAILASH HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KAILASH HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAILASH HEIGHTS?

The professionals named in the filing: Architect: AJAY WADE AND ASSOCIATES; Engineer: SHAH AND GATANI ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAILASH HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAILASH HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAILASH HEIGHTS to a free account