ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / K M RESIDENCY

Registered No litigation declared Residential / Group Housing project

K M RESIDENCY

By KM REALITY

RG-MH-20584 · RERA P99000007750 · Last updated on MahaRERA portal: 10 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 78 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 78 months from the original
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 50%
10 of 90Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

K M RESIDENCY is a Residential / Group Housing project by KM REALITY in Palghar, Maharashtra, registered with MahaRERA as P99000007750 on 17 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 78 months from the original filing. 80 of the 90 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameK M RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • pam
    • pam tembhi
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000007750
  • ReraGenie IDRG-MH-20584

Builder

  • NameKM REALITY
  • Entity typePartnership
  • PartnersBHUMIKA NITIN MHATRE, MANISH VINOD MHATRE, DILIP LAXMAN MHATRE, ASTIK MURLIDHAR MHATRE, LILADHAR LAXMAN MHATRE, NITIN BHAGWAN MHATRE, SANTOSH CHATURBHUJ SAMAL

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed81 files

Current status

89%80 of 90 units booked

Figures as on 10 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BILDING NO 13NA6590090

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.

BILDING NO 13: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes75%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,554 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityZilla Parishad thane
Permissible FSI3414.5
Proposed, not sanctioned3,414 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA BHAYANDAR

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHANT PATIL VASTU SHILP ASSOCIATES
ArchitectNishant Patil
EngineerYogesh Damaji Vaja
Chartered AccountantBharat Dhonde &Co
PartnerRole in project
KM REALITY-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000010786Jun 2021 → Jun 2022

Reason as filed by the promoterDate : 23.08.2021 To The Secretary Maharashtra Real Estate Authority Bandra, Mumbai Dear Sir, Reg. Application for Extension of Project K M RESIDENCY Reg. No. P99000007750-One Year Ours is a Residential Construction project located at Boisar . We registered our project as an Ongoing Project. 1. The date of completion of project is 30.06.2021, The project is in advanced stage of completion and will at least one more year to complete. 2. Due to Corona Pandemic, general recession in Real Estate Sector, lack of liquidity in NBFC and slow growth in economy, dried the resources with the customers, s

EXT99000013930Jun 2021 → Dec 2024

Reason as filed by the promoterTo, Maharashtra Real Estate Regulatory Authority (MahaRERA) 6th & 7th Floor, Housefin Bhavan, Plot No. C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Project name: K M RESIDENCY MahaRERA no.: P99000007750. Status: 90 % Complete Reg. Application for Extension of Project K M RESIDENCY u/s 7(3) having registration no. P99000007750. Dear Sir, Ours is a residential cum commercial project located at Village: Pam Tembhi, Taluka and District: Palghar, Pin code: 401501. Previously we have been granted extension u/s 6 for one year and the said period is expired on 30.12.2022. Our pro

EXT99000027780Jun 2021 → Dec 2027

Reason as filed by the promoterPlease refer to the covering letter attached

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf10 May 2025
Certificates of CA (Form 3)File: Form 3- Mar 25.pdf10 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf10 May 2025
Other - TechnicalFile: PERT-CMA Chart.pdf20 Mar 2025
Declaration in FORM BFile: FROM B.pdf19 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: APPENDIX F.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on 31-12-2024.pdf19 Feb 2025
Certificates of CA (Form 3)File: Form 3 as on 31-12-24.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-2024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosuer of Sold Unsold.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on 30-09-2024.pdf25 Oct 2024
Certificates of CA (Form 3)File: Form 3 as on 30-09-2024.pdf25 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-09-2024.pdf25 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold.pdf25 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on 30-06-2024-Signed.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-06-2024.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY 30-06-2024.pdf24 Jul 2024
Certificates of CA (Form 3)File: Form 3 as on 30-06-2024.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on 31-12-23.pdf7 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on 31-03-2024.pdf7 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-23.pdf7 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-03-2024.pdf7 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ENGINEER CERTIFICATE 25-04-24.pdf7 Jun 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf7 Jun 2024
Certificates of CA (Form 3)File: 1 Form 3 as on 31-12-2023.pdf7 Jun 2024
Certificates of CA (Form 3)File: 2 Form 3 as on 31-03-2024.pdf7 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf9 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf9 Oct 2023
CERSAI detailsFile: CERSAI Report.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory(Signed).pdf9 Oct 2023
Certificates of CA (Form 3)File: Form 3 31-03-2023.pdf9 Oct 2023
Certificates of CA (Form 3)File: Form 3 30-06-2023.pdf9 Oct 2023
Certificates of CA (Form 3)File: Form 3 30-09-2023.pdf9 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022 23.pdf9 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.pdf10 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture certificates.pdf7 Jun 2023
Other - TechnicalFile: Architecture certifica.pdf7 Jun 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf1 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FROM 5.pdf23 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf21 Feb 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD FLAT.pdf21 Feb 2023
CERSAI detailsFile: organized (2) (1).pdf21 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf21 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DETAILS FORMAT A.pdf13 Feb 2023
Deviation Report with respect to model copy of AgreementFile: DIVATION REPORT AGREEMENT.pdf13 Feb 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE DECLARATION.pdf10 Feb 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE DECLARATION.pdf10 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEEREST IN OTHER REAL ESTATE.pdf10 Feb 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE (1).pdf8 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: KM Residency Form-2A FY 2021-22.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE (1).pdf3 Feb 2023
Proforma of Agreement for saleFile: 2 Proforma of Allotment letter (3).pdf1 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form No 5 2017-18.pdf28 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form No 5 2018-19.pdf28 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form No 5 2019-20.pdf28 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form No 5 2020-21.pdf28 Aug 2021
Declaration about Commencement CertificateFile: CC Declaration.pdf23 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Not Applicable.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Not Applicable.pdf23 Aug 2021
Disclosure of sold/ booked inventoryFile: Declaration Sold Unsold.pdf23 Aug 2021
PAN CardFile: PAN.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT CERTIFICATE.pdf29 Jul 2017
Proforma of Allotment letterFile: AGREEMENT OF SALE.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech certificate.pdf27 Jul 2017
Building plan approvalFile: BUILDING LAYOUT PDF.pdf24 Jul 2017
Layout approvalFile: LAYOUT PDF.pdf24 Jul 2017
Copy of the legal title reportFile: title final.pdf24 Jul 2017
Details of encumbrancesFile: no encumbrnce.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PDF.pdf24 Jul 2017
Building Plan Approval (IOD)File: BUILDING LAYOUT PDF.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC1 (1).pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC1 (2).pdf24 Jul 2017

How this compares with Palghar

89%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 78 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep K M RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pam tembhi3,200+ in Palghar

2 kmK M RESIDENCYCompleted 2Lapsed / revoked 5Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: KM REALITY

KM REALITY has 1 registration on MahaRERA, including K M RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if K M RESIDENCY is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of K M RESIDENCY?

The registered promoter entity is KM REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in K M RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for K M RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at K M RESIDENCY?

The professionals named in the filing: Architect: NISHANT PATIL VASTU SHILP ASSOCIATES; Architect: Nishant Patil; Engineer: Yogesh Damaji Vaja; Chartered Accountant: Bharat Dhonde &Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in K M RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About K M RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save K M RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.