Home / Browse projects / Mumbai Suburban, Maharashtra / JP Eminence
JP Eminence
By JP Infra (Mumbai) Pvt. Ltd.
RG-MH-28619 · RERA P51800026524 · Last updated on MahaRERA portal: 17 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JP Eminence is a Others project by JP Infra (Mumbai) Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800026524 on 30 Sep 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameJP Eminence
- TypeOthers
- Location
- JP Road
- Andheri West
- Andheri
- Mumbai Suburban
- 400058
- Pincode400058
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800026524
- ReraGenie IDRG-MH-28619
Builder
- NameJP Infra (Mumbai) Pvt. Ltd.
- Entity typeCompany
- CINU45200MH2006PTC160428
- GSTIN27AACCV2529A1ZP
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- DirectorsVIJAYKUMAR OMPRAKASH JAIN, CHHAGANLAL KHAITAN
- Other registrations3 more →
- Completed3 of 4
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on30 Sep 2020
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed105 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JP Eminence | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
JP Eminence: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities17
As on 17 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Parking Tower | Yes | 100% |
| Compound paving and lighting | Yes | 100% |
Parking filed85
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V.S.Vaidya and Associates |
| Engineer | Rohit Krishna Gorule |
| Chartered Accountant | CAS & CO Chartered Accountants |
| Chartered Accountant | SGCO&Co.LLP |
| Partner | Role in project |
|---|---|
| J. P. INFRA (MUMBAI) PRIVATE LIMITED | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12401184 | Krishnan Nadesan Arunthuthiyar | JP Infra (Mumbai) Pvt. Ltd. | 20/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Apr 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Apr 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Apr 2025
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: JP Eminence - Full OC.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - JP Eminence - Dec 2024.pdf | 15 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - JP Eminence.pdf | 15 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - JP Eminence.pdf | 15 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - JP Eminence.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold inventory details-JP Eminence-Sep 2024.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence Sept 2024.pdf | 18 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 - JP Road March 24.pdf | 7 Dec 2024 |
| Details of encumbrancesFile: Financial Encumbrance_JP Eminence.pdf | 6 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence - June 2024.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_JP Eminence_30-09-24.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_JP Eminence.pdf | 29 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 24 Jp Eminence.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Booked June 24 JP Eminence.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - JP Eminence - June 2024.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence -March 2024.pdf | 5 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-JP Eminence-March 2024.pdf | 4 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold inventory details-JP Eminence-March 2024.pdf | 4 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - JP Eminence - Dec 2023.pdf | 10 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sold-unsold - JP Eminence - Dec 2023.pdf | 10 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold - JP Eminence - Sep 2023.pdf | 10 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold - JP Eminence - Dec 2023.pdf | 10 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence - Dec 2023.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - JP Eminence - March 2024.pdf | 11 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 -JP Eminence March 23.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-JP Eminence-Dec 2023.pdf | 11 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: JP Eminence Part OC - dt 06 Nov 2023.pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-JP Eminence-2023.pdf | 13 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - JP Eminence - Sep 2023.pdf | 8 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-JP Eminence-Sep 2023.pdf | 16 Oct 2023 |
| CERSAI detailsFile: CERSAI Report.pdf | 6 Sep 2023 |
| Details of encumbrancesFile: Encumbrance of JP Eminence dt August 2023.pdf | 28 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory - JP Eminence - June 2023.pdf | 31 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence June 2023.pdf | 27 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - JP Eminence - June 2023.pdf | 21 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - JP Eminence - June 2023.pdf | 21 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold - JP Eminence - March 2023.pdf | 15 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-JP Eminence-2022.pdf | 24 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - JP Eminence - March 2023.pdf | 8 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-JP Eminence-2023.pdf | 6 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence - March 2023.pdf | 6 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Interim Form 1 - Nov 2022.pdf | 3 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Interim Form 1 - 22 March 2023.pdf | 3 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence - 22 March 2023.pdf | 29 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JP Road Eminence Project RERA Form 2- 30-6-2022.pdf | 21 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence - March 2022.pdf | 21 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JP Eminence Form 3 Nov 2022.pdf | 21 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence Dec 2022.pdf | 3 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2022.pdf | 2 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Oct-Dec 22.pdf | 7 Feb 2023 |
| Proforma of Agreement for saleFile: JP Eminence - Agreement.pdf | 20 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory- JP Eminence.pdf | 19 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 22 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 21 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- JP Eminence (July-September 2022).pdf | 2 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 JP Eminence (April - June 2022).pdf | 2 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 5 JP Eminence 2022.pdf | 21 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JP Eminence.pdf | 22 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form 2 - JP Eminence.pdf | 19 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A -JP Eminence.pdf | 19 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: J5168 EMINENCE C04 Architect's Certificate.pdf | 10 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: J5168 EMINENCE C05 Architect's Certificate.pdf | 10 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - JP Eminence.pdf | 27 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC.pdf | 17 Feb 2022 |
| Declaration about Commencement CertificateFile: Declaration for CC dt 18012022.pdf | 17 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JP Road Project- Form 1 (April 21- June 21).pdf | 17 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 07102021.pdf | 17 Feb 2022 |
| CERSAI detailsFile: 1 Other.pdf | 17 Feb 2022 |
| CERSAI detailsFile: 2 Other.pdf | 17 Feb 2022 |
| CERSAI detailsFile: 3 Other.pdf | 17 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JP Eminence-Engineers Certificate.pdf | 10 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JP Road.pdf | 21 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 JP Eminence.pdf | 14 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory disclosure.pdf | 10 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JP Road Project.pdf | 28 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JP Road Project.pdf | 28 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JP Road Project.pdf | 28 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JP Road Project.pdf | 28 Oct 2021 |
| OtherFile: CERSAI_Acknowledgemnt_Report_200216242077_For_Registration_Of_Security_Interest_06_07_2021 | 1 Sep 2021 |
| OtherFile: CERSAI_Acknowledgemnt_Report_200216511546_For_Registration_Of_Security_Interest_06_07_2021 | 1 Sep 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| JP Decks | General Arun Kumar Vaidya Marg Next to Dindoshi Court Malad East Mumbai 400097 | 375 | Completed | Dec 2019 | Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 105 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep JP Eminence on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 382 registered projects within 2 km.
PEARL UNIVERSE
CHANDIWALA ENTERPRISES PRIVATE LIMITED
PRANAMI BLISS
Pranami Neev Realty Limited
Alpine Primo
ALPINE INFRAHEIGHTS LLP
NAMAN HABITAT
SHREE NAMAN DEVELOPERS PVT LTD
Vantage
Rolland Spaces Private Limited
Nasar Enclave Sale Building A and B Wing
M/s. Nasar Associates
See every Mumbai Suburban project, with the district possession charts
Builder: JP Infra (Mumbai) Pvt. Ltd.
JP Infra (Mumbai) Pvt. Ltd. has 4 registrations on MahaRERA, including JP Decks and JP North Celeste. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that JP Eminence shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if JP Eminence is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JP Eminence?
The registered promoter entity is JP Infra (Mumbai) Pvt. Ltd., a company as per the filing. Its CIN U45200MH2006PTC160428 and GSTIN 27AACCV2529A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JP Eminence?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against JP Eminence?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for JP Eminence?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JP Eminence?
The professionals named in the filing: Architect: V.S.Vaidya and Associates; Engineer: Rohit Krishna Gorule; Chartered Accountant: CAS & CO Chartered Accountants; Chartered Accountant: SGCO&Co.LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JP Eminence?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback