Jessika Chs.Ltd.
RG-MH-08288 · RERA P51800011498 · Last updated on MahaRERA portal: 7 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Litigation declared, 1 case
- 2 complaints at MahaRERA
- Completion date moved by 54 months
- 4 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Jessika Chs.Ltd. is a Residential / Group Housing project by Vinayak Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011498 on 31 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 54 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameJessika Chs.Ltd.
- TypeResidential / Group Housing
- Location
- natakwala lane
- Borivali(W)
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800011498
- ReraGenie IDRG-MH-08288
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2020)
- Buildings1 building record
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A and B | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.
Wing A and B: 66% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 7 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Vinayak Developers A/C Jessika | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Umesh Bhatt |
| Engineer | VIDYUT Y RAJA |
| Chartered Accountant | HIRAL SHAH |
| Chartered Accountant | RAJESH R SHAH |
| Partner | Role in project |
|---|---|
| Vinayak Developers | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to change MCGM policies, new DCR 2034 and covid pandemic
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30 JUNE 2023
Reason as filed by the promoterWORK COMPLETION ON PROCESS
Reason as filed by the promoterInitially, Jessika CHS Ltd. engaged a contractor for the construction of the project. However, due to severe delays and unsatisfactory performance, compounded by a significant fund crunch, the said contractor was unable to complete the construction work as agreed. This resulted in contractual disputes between Jessika CHS Ltd. and the said contractor, leading to prolonged litigation. The legal proceedings and subsequent termination of the contract delayed progress considerably, creating a substantial impact on the project timeline. To resume and accelerate construction, Jessika CHS Ltd. and Vin
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 636/2015 | Bombay High Court | Disposed |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000220966 | Mrs. Sarika Suresh Rokade | VINAYAK DEVELOPERS | 26/04/2022 |
| CC12600436 | ARPANA SUBHASHCHANDRA MAHAJAN | Vinayak Developers | 23/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jun 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD vd.pdf | 7 Nov 2024 |
| Certificates of CA (Form 3)File: vinayak form 3-output (1).pdf | 6 Nov 2024 |
| Layout approvalFile: Sanctioned Plan-compressed.pdf | 25 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: Sanctioned Plan-compressed.pdf | 25 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: final form 1 (1).pdf | 25 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Final.pdf | 25 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: final form 2 (1).pdf | 25 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2a Final.pdf | 25 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 vi.pdf | 25 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about RERA Designated Bank Accounts for Real Estate Projects-output.pdf | 23 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Mohod Dis of Intresr-output.pdf | 23 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations copy-output.pdf | 23 Oct 2024 |
| Declaration in FORM BFile: LIMAY P51800011498_FileName_1.pdf | 16 Oct 2024 |
| Declaration in FORM BFile: affidavit jessika rera.pdf | 16 Oct 2024 |
| Certificates of CA (Form 3)File: new FORM 3 .pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: RERA Jessika List (2).pdf | 16 Oct 2024 |
| OtherFile: TERMINATION COPRAMOTER_.pdf | 29 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD AND ALLOTMENT INVENTORY.pdf | 13 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: engineer form 2A 19-20.pdf | 22 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer form 2A 20-21.pdf | 22 Jun 2022 |
| PAN CardFile: PAN VIN.pdf | 21 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf | 21 Jun 2022 |
| Declaration about Commencement CertificateFile: cc declaration.pdf | 20 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect form 1.pdf | 20 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2.pdf | 20 Jun 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200239213942_For_Asset_Based_Search_08_06_2022_11_02_26_969.pdf | 20 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: JESSIKA-FORM-5-FY-2017-18.pdf | 20 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: JESSIKA-FORM-5-FY-2018-19.pdf | 20 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: JESSIKA-FORM-5-FY-2019-20.pdf | 20 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: JESSIKA-FORM-5-FY-2020-21.pdf | 20 Jun 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Jessika Share Certi.pdf | 11 Apr 2018 |
| OtherFile: Jessika Share Certi.pdf | 11 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jessika arc certificate.pdf | 31 Jan 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng certificate jessika.pdf | 31 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form 1.pdf | 31 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer cerificate.pdf | 31 Oct 2017 |
| Certificates of CA (Form 3)File: JESSIKA CAC Form-3.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: affidavit cum declaration.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf | 26 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: certificate of engineer-.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Encrumbrance.pdf | 12 Jul 2017 |
| Building plan approvalFile: IOD.pdf | 21 Jun 2017 |
| Layout approvalFile: IOD Issued Approved Plan.pdf | 21 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: IOD Issued Approved Plan.pdf | 21 Jun 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 21 Jun 2017 |
| Copy of the legal title reportFile: 317-343` Tilte Certificate.pdf | 20 Jun 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 2068360_furthercc_signed.pdf | 20 Jun 2017 |
| Proforma of Allotment letterFile: Draft.pdf | 20 Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 16 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Jessika Chs.Ltd. on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borivali(W)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 457 registered projects within 2 km.
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: Vinayak Developers
Vinayak Developers has 17 registrations on MahaRERA, including Durvankur Apartment and Jessika Chs.Ltd.. Its filings disclose 10 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Jessika Chs.Ltd. shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Jessika Chs.Ltd. is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Jessika Chs.Ltd.?
The registered promoter entity is Vinayak Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Jessika Chs.Ltd.?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Jessika Chs.Ltd.?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Jessika Chs.Ltd.?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Jessika Chs.Ltd.?
The professionals named in the filing: Architect: Umesh Bhatt; Engineer: VIDYUT Y RAJA; Chartered Accountant: HIRAL SHAH; Chartered Accountant: RAJESH R SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Jessika Chs.Ltd.?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.