Home / Browse projects / Raigarh, Maharashtra / JAYDEV HEIGHTS
JAYDEV HEIGHTS
RG-MH-87217 · RERA P52000046542 · Last updated on MahaRERA portal: 24 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 18 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JAYDEV HEIGHTS is a Others project by JAYDEV LIFESPACE LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000046542 on 10 Aug 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 18 months from the original filing. 15 of the 45 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameJAYDEV HEIGHTS
- TypeOthers
- Location
- PUSHPAK WAHAL NAVI MUMBAI
- ULWE
- Ulawe
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000046542
- ReraGenie IDRG-MH-87217
Builder
- NameJAYDEV LIFESPACE LLP
- Entity typePartnership
- PartnersKISHOR BECHARA PATEL, NIKHILESH MISHRA
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Aug 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed155 files
Current status
Figures as on 24 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JAYDEV HEIGHTS | NA | 7 | 7 | 40 | 5 | 45 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 86%.
JAYDEV HEIGHTS: 53% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 60% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 62% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 86% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 66% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 8% |
Progress on shared amenities15
As on 24 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 40% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed9
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHIVAJI KALURAM KOLI | Ulawe | Raigarh |
| HARSHAD SHIVAJI KOLI | Ulawe | Raigarh |
| VISHAL KOLI | Ulawe | Raigarh |
| DHIRAJ MAHADEO KOLI | Ulawe | Raigarh |
| MAHADEO KALARAM KOLI | Ulawe | Raigarh |
| RAMCHANDRA SAKHARAM KOLI | Ulawe | Raigarh |
| UMESH RAMCHANDRA KOLI | Ulawe | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| JAYDEV HEIGHTS | NA | Rs 3.30 cr | Rs 3.23 cr |
| - | NA | Rs 20.00 lakh | Rs 17.85 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Atul Patel Architects |
| Engineer | Descon Engineers |
| Engineer | SHAHJI TANPURE |
| Chartered Accountant | Manish K Ramawati And Company |
| Chartered Accountant | RSL & CO |
| Partner | Role in project |
|---|---|
| JAYDEV LIFESPACE LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Commencement Certificate (CC) for the 7th floor was delayed because additional Floor Space Index (FSI) approvals were required, and its revalidation was further held up by CIDCO’s internal administrative processes-both factors outside the developer’s control. Additionally, obtaining the Fire No Objection Certificate (NOC) for the construction between the 6th and 7th floors was delayed when the Fire Brigade’s policy changed: authority for fire‑safety approvals shifted from private contractors to Assistant Divisional Fire Officers (ADFOs). This transition caused procedural confusion and hold
Reason as filed by the promoterThe project construction is nearly complete, and an application for the Occupation Certificate (OC) has already been submitted to the concerned Planning Authority. However, the OC is still pending due to administrative procedures beyond the Promoter's control, despite all required submissions being completed and regular follow-ups being made. Since possession cannot be legally handed over without the OC, an extension is required to maintain regulatory compliance. The delay will not adversely affect the allottees, as the construction work has been completed and only the final approval remains p
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed155
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 24 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 2026.pdf | 24 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 Q1 2026.pdf | 24 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 22 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 22 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 22 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 22 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 2026.pdf | 22 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 2026.pdf | 22 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 2026.pdf | 22 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 2026.pdf | 22 Aug 2026 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 22 Aug 2026 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 22 Aug 2026 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 22 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 Q1 2026.pdf | 22 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A-Jydev Lifespace1 Signed.pdf | 22 Aug 2026 |
| Withdrawal Update Form 1File: JAYDEV HEIGHTS - Q4 - FORM 1- signed.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 Signed.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: JAYDEV HEIGHTS - Q4 - FORM 1- signed.pdf | 9 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 Signed.pdf | 9 Jun 2026 |
| Withdrawal Update Form 3File: JAYDEV HEIGHTS - FORM 3.pdf | 9 Jun 2026 |
| Form 2A (FY 2024-2025)File: JAYDEV HEIGHT - FORM 2A.pdf | 25 Mar 2026 |
| Withdrawal Update Form 1File: JAYDEV HEIGHTS DEC FORM 1.pdf | 16 Mar 2026 |
| Withdrawal Update Form 2File: JAYDEV HEIGHTS DEC FORM 2.pdf | 16 Mar 2026 |
| Withdrawal Update Form 3File: JAYDEV HEIGHTS - FORM 3.pdf | 16 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 2025.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: ENGINEERS CERTIFICATE SEP 25.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Jaydev Heights_Sept 25_Scanned.pdf | 13 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - jaydev Heights - FY 2024-25.pdf | 24 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 june 2025.pdf | 10 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 june 2025.pdf | 10 Sep 2025 |
| Withdrawal Update Form 3File: Form 3_Jaydev Height_30-06-2025.pdf | 10 Sep 2025 |
| Form 2A (FY 2023-2024)File: form 2 a 23-24.pdf | 22 Aug 2025 |
| Form 2A (FY 2022-2023)File: form 2 a 23-24.pdf | 22 Aug 2025 |
| Form 5 (FY 2022-2023)File: form 5 22-23 (1).pdf | 22 Aug 2025 |
| Form 5 (FY 2023-2024)File: form 5 23-24.pdf | 22 Aug 2025 |
| Form 1File: form 1 sign Dec 2022 signed.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 23.pdf | 21 Aug 2025 |
| Form 3File: form 3 june 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: form 1 sign Dec 2022 signed.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 23.pdf | 21 Aug 2025 |
| Form 3File: form 3 june 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: form 1 march 2023 final sign.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 23.pdf | 21 Aug 2025 |
| Form 3File: form 3 june 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: form 1 signed.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 23.pdf | 21 Aug 2025 |
| Form 3File: form 3 june 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: Form 1 march 24 signed.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 24.pdf | 21 Aug 2025 |
| Form 3File: form 3 march 24.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: form 1 june 24.pdf | 21 Aug 2025 |
| Form 2File: form 2 june 24.pdf | 21 Aug 2025 |
| Form 3File: form 3 june 24.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: Form 1 Spet 24 SIGN.pdf | 21 Aug 2025 |
| Form 2File: form 2 sept 24.pdf | 21 Aug 2025 |
| Form 3File: Form 3 Signed final.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure Signed.pdf | 21 Aug 2025 |
| Form 1File: form 1 dec 24 SIGNED.pdf | 21 Aug 2025 |
| Form 2File: form 2 dec 24.pdf | 21 Aug 2025 |
| Form 3File: form 3 dec 24.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Book FINAL March 25.pdf | 21 Aug 2025 |
| Form 1File: form 1 dec 23.pdf | 18 Aug 2025 |
| Form 2File: form 2 dec 23.pdf | 18 Aug 2025 |
| Form 3File: form 3 dec 23.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure Signed.pdf | 18 Aug 2025 |
| Form 1File: form 1 sept 23.pdf | 18 Aug 2025 |
| Form 2File: form 2 sept 23.pdf | 18 Aug 2025 |
| Form 3File: form 3 sept 23.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Signed.pdf | 18 Aug 2025 |
| Withdrawal Update Form 1File: form 1 jaydev height signed.pdf | 28 Jun 2025 |
| Withdrawal Update Form 2File: form 2 jaydev heights signed .pdf | 28 Jun 2025 |
| Withdrawal Update Form 3File: Form 3 final.pdf | 28 Jun 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 155 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JAYDEV HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ULWE5,900+ in Raigarh
Filed coordinates, straight-line distance. 214 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: JAYDEV LIFESPACE LLP
JAYDEV LIFESPACE LLP has 2 registrations on MahaRERA, including JAYDEV HEIGHTS and Jaydev Imperia. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if JAYDEV HEIGHTS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JAYDEV HEIGHTS?
The registered promoter entity is JAYDEV LIFESPACE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JAYDEV HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JAYDEV HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JAYDEV HEIGHTS?
The professionals named in the filing: Architect: Atul Patel Architects; Engineer: Descon Engineers; Engineer: SHAHJI TANPURE; Chartered Accountant: Manish K Ramawati And Company; Chartered Accountant: RSL & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAYDEV HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback