RG-MH-18481 · RERA P51800076878 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 10.00 crore secured on the land, in favour of Aditya Birla Housing Finance Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Stilt Floor, 25%
25 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

JAY KRUPA SADAN BY SHREE HARI REALTY is a Others project by SHREE HARI REALTY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800076878 on 3 Jul 2024. Possession is promised by 31 Dec 2026. 4 of the 29 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameJAY KRUPA SADAN BY SHREE HARI REALTY
  • TypeOthers
  • Location
    • TPS SANTACRUZ NO.6
    • SANTACRUZ WEST
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400054
  • Pincode400054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800076878
  • ReraGenie IDRG-MH-18481

Builder

  • NameSHREE HARI REALTY
  • Entity typePartnership
  • PartnersRAMESH JETHABHAI RAVARIYA, RAMESH BHAGA RAVARIYA, MUKESH GANGJI PATEL
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jul 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed50 files

Current status

14%4 of 29 units booked
26.7%Work done, per cost certificate

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JAY KRUPA SADAN BY SHREE HARI REALTYNA55121729

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 25%.

JAY KRUPA SADAN BY SHREE HARI REALTY: 30% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor25%
Slabs of Super Structure1%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area650 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Housing Finance Limited
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on9 Jul 2025
LandownerVillageDistrict
JAY KRUPA SADAN CHSLVileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1680.78
Proposed, not sanctioned1,681 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR REGAL APARTMENT OPP HP PETROL PUMP SV ROAD SANTACRUZ W MUMBAI 400054
Estimated costRs 11.25 cr
Cost incurredRs 3.00 cr
Work done26.67%
BuildingWingEstimatedIncurred
JAY KRUPA SADAN BY SHREE HARI REALTYNARs 10.12 crRs 3.00 cr
-NARs 1.12 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHardik Hingoo
ArchitectRasik P Hingoo Associates
EngineerMahesh Mahagundappa Shirol
EngineerHuzefa Sathalia
Chartered AccountantShah and Vejani
Chartered AccountantDarshan Kishor Shah
PartnerRole in project
SHREE HARI REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 5_Signed.pdf26 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1_Signed.pdf16 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2_Signed.pdf16 Apr 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 25-26 Q4.pdf16 Apr 2026
Withdrawal Update Form 1File: ARCHITECT FORM 1_Q3.pdf20 Jan 2026
Withdrawal Update Form 2File: ENGINEERS FORM 2_Q3.pdf20 Jan 2026
Withdrawal Update Form 3File: Withdrawal Application Form3_Signed 25-26 Q3.pdf20 Jan 2026
Form 2A (FY 2024-2025)File: FORM-2A FY 24-25 06-12-2025.pdf8 Dec 2025
Withdrawal Update Form 1File: Form 1 Architectu0027s Certificate.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2 Engineeru0027s Certificate.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate - Both signed.pdf31 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Annual FY 2024-2025 Digital Signature File.pdf26 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1 Q4.pdf9 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jay Krupa Sadan by Shree Hari Realty Q4.pdf9 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS FORM 2 Q4.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1 Q3.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jay Krupa Sadan by Shree Hari Realty Q3.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS FORM 2 Q3.pdf9 Jan 2025
Proforma of Agreement for saleFile: AFS November 14.pdf18 Nov 2024
Proforma of Agreement for saleFile: AFS November 14.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1 Q2.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jay Krupa Sadan Final Q2.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS FORM 2 Q2.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Rera Form 2.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed Final.pdf12 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf7 Aug 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed Final.pdf22 Jun 2024
Copy of the legal title reportFile: Title Report.pdf18 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrance_merged.pdf18 Jun 2024
Details of encumbrances concerned to LegalFile: Encumbrance_merged.pdf18 Jun 2024
Proforma of Agreement for saleFile: Revised AFS Residential.pdf18 Jun 2024
Other - LegalFile: SHREE HARI REALTY DEED OF PARTNERSHIP NEW_11zon.pdf18 Jun 2024
CERSAI detailsFile: Cersai Report Revised.pdf7 Jun 2024
CERSAI detailsFile: CERSAI.pdf7 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Formate A.pdf7 Jun 2024
Other - TechnicalFile: ANNEXURE A (1).pdf7 Jun 2024
Layout approvalFile: IOD DRAWING AP 1.pdf5 Jun 2024
Building plan approvalFile: IOD DRAWING AP 1.pdf5 Jun 2024
PAN CardFile: SHR Pan.pdf5 Jun 2024
Copy of Layout Approval (in case of layout)File: IOD DRAWING AP 1.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD DRAWING AP 1.pdf5 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: C C COPY.pdf5 Jun 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf5 Jun 2024
Declaration in FORM BFile: Form B - SHR.pdf5 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf5 Jun 2024
Proforma of Allotment letterFile: AL.pdf5 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation Report (Allotment letter).pdf5 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report (Agreement for sale).pdf5 Jun 2024

How this compares with Mumbai Suburban

14%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JAY KRUPA SADAN BY SHREE HARI REALTY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SANTACRUZ WEST6,700+ in Mumbai Suburban

2 kmJAY KRUPA SADAN BY SHREECompleted 164Lapsed / revoked 74Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 391 registered projects within 2 km.

Builder: SHREE HARI REALTY

SHREE HARI REALTY has 2 registrations on MahaRERA, including KRISHNA ICON and JAY KRUPA SADAN BY SHREE HARI REALTY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if JAY KRUPA SADAN BY SHREE HARI REALTY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JAY KRUPA SADAN BY SHREE HARI REALTY?

The registered promoter entity is SHREE HARI REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JAY KRUPA SADAN BY SHREE HARI REALTY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JAY KRUPA SADAN BY SHREE HARI REALTY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JAY KRUPA SADAN BY SHREE HARI REALTY?

The professionals named in the filing: Architect: Hardik Hingoo; Architect: Rasik P Hingoo Associates; Engineer: Mahesh Mahagundappa Shirol; Engineer: Huzefa Sathalia; Chartered Accountant: Shah and Vejani; Chartered Accountant: Darshan Kishor Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAY KRUPA SADAN BY SHREE HARI REALTY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAY KRUPA SADAN BY SHREE HARI REALTY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAY KRUPA SADAN BY SHREE HARI REALTY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.