Home / Browse projects / Mumbai Suburban, Maharashtra / IZARRA

Completed No litigation declared Residential / Group Housing project

IZARRA

By ORNO INFRAPROJECTS PVT LTD

RG-MH-37127 · RERA P51800018888 · Last updated on MahaRERA portal: 17 Oct 2024

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 21 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 0%
2Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

IZARRA is a Residential / Group Housing project by ORNO INFRAPROJECTS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018888 on 10 Dec 2018. The registration is recorded completed; possession was promised by 30 Sep 2024. The completion date has moved by 21 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameIZARRA
  • TypeResidential / Group Housing
  • Location
    • 14th Road
    • Khar west
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800018888
  • ReraGenie IDRG-MH-37127

Builder

  • NameORNO INFRAPROJECTS PVT LTD
  • Entity typeCompany
  • DirectorKRISHNAKUMAR BHOPAYA KARMAYA

Key dates

this monthRegisteredDec 2018First promiseDec 2022Revised toSep 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Dec 2018
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
IZARRANA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.

IZARRA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered28

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area832 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3941.47
Proposed, not sanctioned2,234 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJ P ROAD ANDHERI WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSKYLINE INFRABUILT CONSULTANTSPVT LTD
EngineerRANGANATHAN
PartnerRole in project
ORNO INFRAPROJECTS PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013458Dec 2022 → Dec 2023

Reason as filed by the promoterTHE PROJECT IS DELAYED DUE TO PERMISSION DELAY. ATTACHED HEREWITH LOI DATED 15/12/2022

EXT51800019159Dec 2022 → Apr 2024

Reason as filed by the promoterOC application is in progress. may required another month for approval.

EXT51800024316Dec 2022 → Sep 2024

Reason as filed by the promoterDear Sir/Madam, We are in the process of applying OC. the contruction work is complete as can be verified from the architect and engineer certificate.

EXT51800018605Dec 2022 → Feb 2024

Reason as filed by the promoterDear Sir/Madam, We are in process of application of occupancy certificate and expected to receive it by the end of February 2024 hence need extention of two months. required consent are attached herewith for your quick review.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12501026Reshma Ashok BhagiaORNO INFRAPROJECTS PVT LTD26/03/2025
CC12502425ORNO INFRAPROJECTS PVT LTDReshma Bhagia16/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Oct 2024

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Izzara1_merged.pdf17 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: Izzara1.pdf14 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: Izzara Form 4.pdf9 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_compressed.pdf8 Oct 2024
Declaration in FORM BFile: Orno Affidavit.pdf11 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate signed_compressed.pdf11 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold disclosure.pdf11 Jul 2024
Certificates of CA (Form 3)File: Form 3 signed.pdf11 Jul 2024
Declaration in FORM BFile: Affidavit.pdf6 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate signed 2.pdf6 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate signed.pdf6 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold.pdf6 Mar 2024
Certificates of CA (Form 3)File: Form 3 signed.pdf6 Mar 2024
Declaration in FORM BFile: Affidavit.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Annexure C 2A Signed.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: NEW DISCLOSURE OF SOLD.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Orno Form 5 Sign.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf12 Jan 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: orno 2020.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: orno 2021.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: orno 2022.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORNO FORM 5 2022.pdf10 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf23 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf23 May 2022
Certificates of CA (Form 3)File: Form 3_compressed.pdf19 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5).pdf19 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Izzara C-C- up-to 15th floor 24-Apr-2021 12-37-50_compressed (1).pdf5 May 2021
Commencement Certificates / NA Order for plotted developmentFile: PDF.pdf26 Dec 2019
Annual Audit Report of Statutory CA (Form 5)File: orno certificate.pdf24 Oct 2019
Building plan approvalFile: IOA COPY1.pdf5 Dec 2018
Layout approvalFile: IOA PLAN1.pdf5 Dec 2018
Copy of the legal title reportFile: title certificate_Part1.pdf5 Dec 2018
Copy of the legal title reportFile: title certificate_Part2.pdf5 Dec 2018
Copy of the legal title reportFile: title certificate_Part3.pdf5 Dec 2018
Copy of the legal title reportFile: title certificate_Part4.pdf5 Dec 2018
Copy of the legal title reportFile: title certificate_Part5.pdf5 Dec 2018
Copy of Layout Approval (in case of layout)File: IOA PLAN1.pdf5 Dec 2018
Building Plan Approval (IOD)File: IOA COPY1.pdf5 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf5 Dec 2018
Certificates of CA (Form 3)File: CA certificate.pdf5 Dec 2018
Proforma of Allotment letterFile: Draft Rera Agreement - Orno Infraprojects -Izarra .pdf5 Dec 2018
PAN CardFile: pan card orno.pdf3 Dec 2018
Details of encumbrancesFile: Encumberance.pdf3 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Izara new CC upto 10th floor 27-09-2018 27-Sep-2018 17-01-14(1).pdf3 Dec 2018
Declaration in FORM BFile: Form B1.pdf3 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 1.pdf3 Dec 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 21 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IZARRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khar west6,700+ in Mumbai Suburban

2 kmIZARRACompleted 119Lapsed / revoked 53Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 323 registered projects within 2 km.

Builder: ORNO INFRAPROJECTS PVT LTD

ORNO INFRAPROJECTS PVT LTD has 1 registration on MahaRERA, including IZARRA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if IZARRA is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IZARRA?

The registered promoter entity is ORNO INFRAPROJECTS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IZARRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against IZARRA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for IZARRA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IZARRA?

The professionals named in the filing: Architect: SKYLINE INFRABUILT CONSULTANTSPVT LTD; Engineer: RANGANATHAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IZARRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IZARRA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IZARRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.