Home / Browse projects / Mumbai Suburban, Maharashtra / Integrated Arya
Integrated Arya
RG-MH-08339 · RERA P51800004521 · Last updated on MahaRERA portal: 11 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 117 months
- 6 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Integrated Arya is a Others project by Integrated Spaces Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004521 on 9 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 117 months from the original filing. 82 of the 167 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameIntegrated Arya
- TypeOthers
- Location
- Off. L. B. S. Marg
- Narayan Nagar
- Ghatkopar West
- Kurla
- Mumbai Suburban
- 400086
- Pincode400086
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004521
- ReraGenie IDRG-MH-08339
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Aug 2017
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 31 Mar 2019)
- Buildings1 building record
- Documents filed167 files
Current status
Figures as on 11 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INTEGRATED ARYA | NA | 11 | 9 | 159 | 8 | 167 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 92%.
INTEGRATED ARYA: 84% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 88% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 92% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 82% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Progress on shared amenities15
As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed109
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| INTEGRATED ARYA | NA | Rs 32.70 cr | Rs 33.60 cr |
| - | NA | Rs 1.02 cr | Rs 1.05 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YMS CONSULTANTS LIMITED |
| Architect | YOMESH RAO |
| Engineer | Dayanand Salunke |
| Engineer | PRADEEP ASHOK THORAT |
| Chartered Accountant | NEHALI DHAVAL DOSHI |
| Chartered Accountant | VINAY BHUSHAN&associates |
| Partner | Role in project |
|---|---|
| Integrated Spaces Limited | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterFlooring, Tiling work, Electrification work, Internal and external plumbing work has been completed of Wing A & B and initiate same work in wing C,D,E,F. Due to COVID 19 lockdown, there has been delay in completion of finishing work at site. Hence, we seek further extension of 3 months i.e. upto 31.03.2022.
Reason as filed by the promoterProject is ready for application for OC we have completed 12 compliance out of 13 compliance for application of OC and we will apply for OC on or before 31-03-2022. For completion of balance finishing work and to take water connection at site, we seek further extension of 4 months i.e. upto 31-07-2022 to complete ancillary work for delivery of project.
Reason as filed by the promoter1 Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis 2 Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum. 3 Unseasonal and heavy rain during odd months also impacted badly in our project construction phase 4 The sales in the market was absolutely bad and hence we could not get enough business and fresh income to run the construction flow as per the schedule 5 Most of our investors and directors faced issues in fund
Reason as filed by the promoterDue to adverse market condition and slowdown in Real Estate Industry in 2019, there has been a delay in completion of balance construction and finishing work at site. Hence we seek further extension of 9 months to complete work and obtain Occupation Certificate for the project.
Reason as filed by the promoter“In the present litigation we are at Consent term stage also awaiting DP 2034 for further approvals. ”
Reason as filed by the promoterWe "Integrated Spaces Limited", promoters of the project named "Integrated Arya" located at CTS No. 183C/1 and 183C/2 of Village Kirol, Taluka Kurla, District Mumbai Suburhan, 400086 The project consists of total 6 wings and cach wing consist of ground plus & floors. Plinth Approval was received for the project in the year 8 July 2015 and Full CC (G+7) for the project was received on 6th May 2019 We have completed ground plus 7 floors as per the approval received also we have obtained part occupation certificate for ground plus 7 floors dated May 2022. Out of 102 units (including 8ª floor unit
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 3969/2010 | City Civil Court | RECORDING EVIDENCE |
| 7545/2017 | High Court Mumbai | Pre Admission |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197800 | Manohar Shrinivas Chetty | Integrated Spaces Ltd. | 28/07/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Dec 2022
Documents filed167
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Arya.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: Form 2 Arya.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate Integrated Arya M26.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: Form 1 Arya Dec 25.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Arya Dec 25.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Arya Dec 25.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Arya - Sept 25.pdf | 2 Dec 2025 |
| Withdrawal Update Form 2File: Arya Form 2 - Sept 25.pdf | 2 Dec 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate Integrated Arya Sept 25.pdf | 2 Dec 2025 |
| Form 5 (FY 2024-2025)File: ISL Arya Form 5_FY 24-25.pdf | 2 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Arya June 25.pdf | 27 Nov 2025 |
| Withdrawal Update Form 2File: Arya Form 2 - June 25.pdf | 27 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Arya June 25.pdf | 27 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Arya.pdf | 3 Oct 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form1 (Arya).pdf | 2 May 2025 |
| Certificates of CA (Form 3)File: Signed_CA Certificate Integrated Arya Mar 25.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Arya Q 4 FY 24-25.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Arya - Inventory.pdf | 2 May 2025 |
| Declaration in FORM BFile: Arya - Forrm B.pdf | 27 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Arya Form-5 23-24.pdf | 18 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Arya.pdf | 12 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 30 Jan 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 27 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 27 Nov 2024 |
| Declaration in FORM BFile: Arya Form B.pdf | 22 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arya.pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arya.pdf | 9 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 12 Aug 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 12 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate for RERA (Arya).pdf | 24 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Arya form 2A.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Arya.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 14 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Arya.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Arya Inventory Disclosure.pdf | 7 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 23.pdf | 5 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Dec 23.pdf | 5 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual Audit Report 2022 2023.pdf | 30 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 (arya)_signed.pdf | 13 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 -Arya Sept 23.pdf | 23 Dec 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate Integrated Arya sept'23_Signed Final.pdf | 23 Dec 2023 |
| Details of encumbrances concerned to FinanceFile: Integrated Arya Encumbrances.pdf | 1 Dec 2023 |
| Details of encumbrances concerned to LegalFile: Integrated Arya Encumbrances.pdf | 1 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Int Arya_Sep 2023.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Int Arya_Apr-June 2023.pdf | 26 Aug 2023 |
| Certificates of CA (Form 3)File: Int Arya Form 3 Apr-Jun 23.pdf | 26 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-FY22-23-Integrated Arya.pdf | 18 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Integrated Arya-Q1.pdf | 14 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineer's Certificate-Q4.pdf | 14 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3- C A Certificate- Form 3- Final Signed (1).pdf | 8 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate - Integrated Arya.pdf | 27 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert June 22.pdf | 18 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Sep 22.pdf | 18 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3_CA June 22.pdf | 18 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3_CA Sept 22.pdf | 18 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: I Arya - Self Declaration_No Encumbrance.pdf | 28 Feb 2023 |
| Details of encumbrances concerned to LegalFile: I Arya - Self Declaration_No Encumbrance.pdf | 28 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf | 28 Feb 2023 |
| Certificates of CA (Form 3)File: CA form 3.pdf | 28 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Arya FY 21-22.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Integrated Arya_FY 21-22_signed.pdf | 3 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate -Arya - Dec 22.pdf | 23 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Integrated Arya_Form 4 - Architect certificate.pdf | 19 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate-Arya_signed.pdf | 19 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_ARYA_EC_Mar 22_Signed.pdf | 18 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 13d_part oc letter with visible sign 190522.pdf | 3 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Certificate - Arya.pdf | 25 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_ARYA_EC_Mar 22_Signed.pdf | 25 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ARYA_EC_Mar'21.pdf | 25 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold_Booked Inventory.pdf | 12 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Integrated Arya_Q1_Form 1_08 08 2022.pdf | 17 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Signed 09042022.pdf | 9 Apr 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate_Arya_Signed Final.pdf | 4 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report.pdf | 1 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARYA_EC_Mar'21.pdf | 20 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 signed INTEGRATED ARYA.pdf | 20 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 10 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - 30062021.pdf | 10 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A March 2021.pdf | 10 Aug 2021 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Integrated IRS 1 | Ulve Node | 108 | Completed | Dec 2016 | Late, Jul 2017 |
| Integrated Bhoomi | Ghatkopar West | 96 | Completed | Dec 2016 | Dec 2016 |
| Shivnagar Karma Bhoomj | Ghatkopar West | 92 | Completed | Jul 2015 | Jul 2015 |
| Integrated Karma | Ghatkopar East | 40 | Completed | Dec 2012 | Nov 2012 |
| Pranay Kiran | Ghatkopar West | 76 | Completed | Mar 2012 | Feb 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 167 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Integrated Arya on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Narayan Nagar, Ghatkopar West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 304 registered projects within 2 km.
Atul Life Phase I
ATUL PROJECTS INDIA PVT LTD
SERENE CITY
SANGHVI BUILDTECH LLP
Neelyog Regent
Ratan Builders
Imperial Indrapuram B & C
Imperial Global Infra
HERITAGE AHURA RESIDENCY
KERSI JAMSHED RANDERIA
O AND S BUSINESS SUITES
SUCHITA ORANGE HDM PROJECT
See every Mumbai Suburban project, with the district possession charts
Builder: Integrated Spaces Limited
Integrated Spaces Limited has 6 registrations on MahaRERA, including Integrated Kamal and Integrated Ahana. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Integrated Arya is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Integrated Arya?
The registered promoter entity is Integrated Spaces Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Integrated Arya?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Integrated Arya?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Integrated Arya?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Integrated Arya?
The professionals named in the filing: Architect: YMS CONSULTANTS LIMITED; Architect: YOMESH RAO; Engineer: Dayanand Salunke; Engineer: PRADEEP ASHOK THORAT; Chartered Accountant: NEHALI DHAVAL DOSHI; Chartered Accountant: VINAY BHUSHAN&associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Integrated Arya?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.