Home / Browse projects / Raigarh, Maharashtra / Innovative Plaza II

Registered No litigation declared Residential / Group Housing project

Innovative Plaza II

By PINNACLE CONSTRUCTION

RG-MH-28896 · RERA P52000027283 · Last updated on MahaRERA portal: 5 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 30 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
45 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

Innovative Plaza II is a Residential / Group Housing project by PINNACLE CONSTRUCTION in Raigarh, Maharashtra, registered with MahaRERA as P52000027283 on 1 Dec 2020. Possession is promised by 31 Dec 2028. The completion date has moved by 30 months from the original filing. 4 of the 49 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameInnovative Plaza II
  • TypeResidential / Group Housing
  • Location
    • plot no 11 sec 12
    • taloja phase II
    • Taloje Panchnad
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000027283
  • ReraGenie IDRG-MH-28896

Builder

  • NamePINNACLE CONSTRUCTION
  • Entity typePartnership
  • PartnersMOHD RAIS MOHD TAKSEEN KHAN, ASHFAQ AHMED RAIS KHAN, MAHENDRAKUMAR MOTILAL MOURYA, ABDUL LATIF ALI PARKAR
  • Other registrations6 more →
  • Completed5 of 7

Key dates

this monthRegisteredDec 2020First promiseJun 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2020
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed83 files

Current status

8%4 of 49 units booked
35.7%Work done, per cost certificate

Figures as on 5 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Innovative Plaza IINA7749049

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

Innovative Plaza II: 37% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area600 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 May 2025

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI2590.73
Proposed, not sanctioned2,591 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchseawoods west
Estimated costRs 5.86 cr
Cost incurredRs 2.09 cr
Work done35.66%
BuildingWingEstimatedIncurred
Innovative Plaza IINARs 5.44 crRs 2.09 cr
-NARs 41.83 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIARCH DESIGN STUDIO
EngineerSamarth Agarwal
EngineerTanveer Abdul Majid Choughule
Chartered AccountantS M Shaikh and Co
Chartered AccountantBharat A Choudhary and Co
Chartered AccountantRakesh Choudhary & Co
PartnerRole in project
PINNACLE CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07102518052Jun 2026 → Dec 2028

Reason as filed by the promoterSince our project was falling in CRZ-II, and with CZMP in force we were required to keep further development work in abeyance until change in the CRZ rulings. Due to the same reason our development work was halted for a period of more than 4 years. After the revision in CRZ rulings in general, we have recently received Amended CC dated 14/02/2025, according to which development will be now carried out.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_20260630 Plot No 11 Sector 12 Taloja.pdf5 Aug 2026
Withdrawal Update Form 2File: Form 2_Innovative Plaza II -- EC 30-06-26 with DSC.pdf5 Aug 2026
Withdrawal Update Form 3File: Form 3 _ Q1 FY 26-27 _Innovative Plaza 2 CA and Partner Signed.pdf5 Aug 2026
Withdrawal Update Form 1File: Form 1_ 20260331 Plot No 11 Sector 12 Taloja.pdf19 May 2026
Withdrawal Update Form 2File: Form 2_ Innovative Plaza II EC 31-03-26 with DSC.pdf19 May 2026
Withdrawal Update Form 3File: Form 3 _ Q4 FY 25-26 _Innovative Plaza 2_ CA and Client Signed.pdf19 May 2026
Withdrawal Update Form 1File: Form 1_20251231_Plot no_11_Sector-12_Taloja.pdf11 Mar 2026
Withdrawal Update Form 2File: Form 2_ Innovative Plaza II -- EC 31-12-25.pdf11 Mar 2026
Withdrawal Update Form 3File: Form 3 _SG_ Q3 FY 25-26 _Innovative Plaza 2_ ca and client signed_.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1 _ 20250930plot no 11, sector 12, Taloja.pdf12 Nov 2025
Withdrawal Update Form 2File: Form 2 _ Innovative Plaza II -- EC 30-09-25 with DSC.pdf12 Nov 2025
Withdrawal Update Form 3File: Form 3 SG_signed_ Q2 FY 25-26 _Innovative Plaza 2.pdf12 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf11 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 signed_Innovative Plaza Il FY 2024-25.pdf11 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf29 Aug 2025
Withdrawal Update Form 2File: Form 2 - Innovative Plaza II -- EC 30-06-25.pdf29 Aug 2025
Withdrawal Update Form 3File: Form 3 _ Q1 FY 25-26 _Innovative Plaza 2_Signed.pdf29 Aug 2025
Withdrawal Update Form 1File: Form 1.pdf17 Aug 2025
Withdrawal Update Form 2File: Form 2 - Innovative Plaza II -- EC 30-06-25.pdf17 Aug 2025
Withdrawal Update Form 3File: Form 3_Q4 (FY 24-25)_Innovative Plaza 2_Signed.pdf17 Aug 2025
Declaration and undertaking (Annexure A)File: Annexure A.pdf26 Jun 2025
Form 1File: Form 1 MAR-2023.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 31-03-23.pdf26 Jun 2025
Form 3File: Form 3 _ Q4 FY 22-23_Innovative Plaza 2_signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q4 22 23.pdf26 Jun 2025
Form 1File: Form 1JUN-2023.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 30-06-23.pdf26 Jun 2025
Form 3File: Form 3 _ Q1 FY 23-24_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q1 23 24.pdf26 Jun 2025
Form 1File: Form 1 SEP-2023.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 30-09-23.pdf26 Jun 2025
Form 3File: Form 3 _ Q2 FY 23-24_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q2 23- 24.pdf26 Jun 2025
Form 1File: Form 1 30-12-23.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 30-12-23.pdf26 Jun 2025
Form 3File: Form 3 _ Q3 FY 23-24_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q3 23 24.pdf26 Jun 2025
Form 1File: Form 1 30-03-24.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 30-03-24.pdf26 Jun 2025
Form 3File: Form 3 _ Q4 FY 23-24_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q4 23 24.pdf26 Jun 2025
Form 1File: Form 1 JUN-2024.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 29-06-24.pdf26 Jun 2025
Form 3File: Form 3 _ Q1 FY 24-25_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q1 24 25.pdf26 Jun 2025
Form 1File: Form 1 30-09-24.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 30-09-24.pdf26 Jun 2025
Form 3File: Form 3 _ Q2 FY 24-25_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q2 24-25.pdf26 Jun 2025
Form 1File: Form 1 31-12-24.pdf26 Jun 2025
Form 2File: Innovative Plaza II -- EC 31-12-24.pdf26 Jun 2025
Form 3File: Form 3 _ Q3 FY 24-25_Innovative Plaza 2_Signed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Q3 24 25.pdf26 Jun 2025
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf26 Jun 2025
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf26 Jun 2025
Form 5 (FY 2022-2023)File: Form 5_Innovative Plaza Il FY 2022-23_signed.pdf26 Jun 2025
Form 5 (FY 2023-2024)File: Form 5_Innovative Plaza Il FY 2023-24_signed.pdf26 Jun 2025
Building plan approvalFile: 11 12 CC DRG.pdf23 May 2025
Form 1File: Form 1.pdf23 May 2025
Form 2File: Form 2.pdf23 May 2025
Form 3File: Form 3_Q4 (FY 24-25)_Innovative Plaza 2_Signed.pdf23 May 2025
Disclosure of Sold and Booked InventoryFile: Disclsoure of Sold and Booked Inventory_Innovative Plaza 2.pdf23 May 2025
Withdrawal Update Form 1File: Form 1.pdf23 May 2025
Withdrawal Update Form 1File: Form 1.pdf23 May 2025
Withdrawal Update Form 2File: Form 2.pdf23 May 2025
Withdrawal Update Form 2File: Form 2.pdf23 May 2025
Withdrawal Update Form 3File: Form 3_Q4 (FY 24-25)_Innovative Plaza 2_Signed.pdf23 May 2025
Withdrawal Update Form 3File: Form 3_Q4 (FY 24-25)_Innovative Plaza 2_Signed.pdf23 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf1 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Innovative Plaza II -- EC 10-03-25.pdf1 Apr 2025
Building plan approvalFile: Building Plan.pdf26 Nov 2020
Layout approvalFile: Layout.pdf26 Nov 2020
Copy of the legal title reportFile: title and search-c.pdf26 Nov 2020
Details of encumbrancesFile: declaration.pdf26 Nov 2020
Copy of Layout Approval (in case of layout)File: Layout.pdf26 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf26 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf26 Nov 2020
Declaration in FORM BFile: Form B-compressed.pdf26 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-compressed.pdf26 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-compressed.pdf26 Nov 2020

How this compares with Raigarh

8%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 30 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Innovative Plaza II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near taloja phase II5,900+ in Raigarh

2 kmInnovative Plaza IICompleted 67Lapsed / revoked 16Other 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: PINNACLE CONSTRUCTION

PINNACLE CONSTRUCTION has 7 registrations on MahaRERA, including INNOVATIVE PLAZA-I and INNOVATIVE RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Innovative Plaza II is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Innovative Plaza II?

The registered promoter entity is PINNACLE CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Innovative Plaza II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Innovative Plaza II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Innovative Plaza II?

The professionals named in the filing: Architect: TRIARCH DESIGN STUDIO; Engineer: Samarth Agarwal; Engineer: Tanveer Abdul Majid Choughule; Chartered Accountant: S M Shaikh and Co; Chartered Accountant: Bharat A Choudhary and Co; Chartered Accountant: Rakesh Choudhary & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Innovative Plaza II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Innovative Plaza II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Innovative Plaza II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.