Home / Browse projects / Ahmednagar, Maharashtra / INDU PAVILION

Registration lapsed No litigation declared Commercial project

INDU PAVILION

By SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED

RG-MH-05047 · RERA P52200023392 · Last updated on MahaRERA portal: 30 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 32 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 75%
95 of 108Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

INDU PAVILION is a Commercial project by SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED in Ahmednagar, Maharashtra, registered with MahaRERA as P52200023392 on 12 Dec 2019. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 32 months from the original filing. 13 of the 108 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameINDU PAVILION
  • TypeCommercial
  • Location
    • NAGAR MANMAD ROAD
    • SAVEDI
    • Ahmadnagar (M Corp.)
    • Nagar
    • Ahmednagar
    • 414003
  • Pincode414003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200023392
  • ReraGenie IDRG-MH-05047

Builder

  • NameSOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorPUNEET BALKRISHNAN CHETTIAR
  • Declared earlier projects2 →

Key dates

7 months past promisethis monthRegisteredDec 2019First promiseJul 2023Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Dec 2019
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Jul 2023)
  • Buildings1 building record
  • Documents filed73 files

Current status

12%13 of 108 units booked
89.7%Work done, per cost certificate

Figures as on 30 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INDU PAVILIONNA900108108

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.

INDU PAVILION: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,091 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Jul 2025

Approvals and building plan

Sanctioning authorityAHILYANAGAR MUNICIPAL CORPORATION
Permissible FSI11455.0
Proposed, not sanctioned8,041 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGHOLE ROAD, NEAR BALGANDHARVA, PUNE
Estimated costRs 18.92 cr
Cost incurredRs 16.98 cr
Work done89.73%
BuildingWingEstimatedIncurred
INDU PAVILIONNARs 17.38 crRs 16.98 cr
-NARs 1.54 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATISH N JOSHI
EngineerABHAY SURESHCHAND PATWA
EngineerHEMANT BALASAHEB SHINDE
Chartered AccountantPRITESH ACHALIYA
Chartered AccountantJ P N R & ASSOCIATES
PartnerRole in project
SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52200019607Jul 2023 → Mar 2026

Reason as filed by the promoterApplication for extension of project under Section 7(3) Reasons 1. Covid Period 2. Very bad real estate market post covid. 3. Shift in customer preference to ready to move in projects. 4. All these reasons compelled us to stop our project construction in the covid period. 5. We have not received any amount from any customer till date. There is No booking / No allotment to any customer. 6. All the amount used for the project till date are from owned funds. 7. Construction work is ongoing.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Nov 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT_CERTIFICATE_2_QTR.PDF30 Mar 2026
Withdrawal Update Form 1File: ARCHITECT_CERTIFICATE_3_QTR.PDF30 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf30 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf30 Mar 2026
Withdrawal Update Form 3File: FORM 3 - SIGNED_0001.pdf30 Mar 2026
Withdrawal Update Form 3File: FORM 3- SIGNED_0001.pdf30 Mar 2026
Withdrawal Update Form 1File: ARCHITECT_CERTIFICATE_1_QTR.PDF24 Mar 2026
Withdrawal Update Form 1File: ARCHITECT_CERTIFICATE_1_QTR.PDF24 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf24 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf24 Mar 2026
Withdrawal Update Form 3File: FORM 3 - SIGNED.pdf24 Mar 2026
Withdrawal Update Form 3File: FORM 3 - SIGNED.pdf24 Mar 2026
Withdrawal Update Form 1File: FORM 1.PDF22 Jul 2025
Withdrawal Update Form 2File: FORM 2_Signed.PDF22 Jul 2025
Withdrawal Update Form 3File: FORM 3_Signed_compressed.pdf22 Jul 2025
Form 1File: FORM 1.PDF15 Jul 2025
Form 2File: FORM 2.PDF15 Jul 2025
Form 3File: FORM 3_signed.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclouser of SoldUnsold - Final-SIGNED.PDF15 Jul 2025
Form 2A (FY 2019-2020)File: Form 2A FY 2019-20 -signed.pdf10 Jul 2025
Form 2A (FY 2020-2021)File: Form 2A FY 2020-21 -signed.pdf10 Jul 2025
Form 2A (FY 2021-2022)File: Form 2A FY 2021-22 -signed.pdf10 Jul 2025
Form 2A (FY 2022-2023)File: Form 2A FY 2022-23 -signed.pdf10 Jul 2025
Form 2A (FY 2023-2024)File: Form 2A FY 2023-24 -signed.pdf10 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25 -signed.pdf10 Jul 2025
Form 5 (FY 2019-2020)File: Form 5 FY 2019-20 signed.pdf5 Jul 2025
Form 5 (FY 2020-2021)File: Form 5 FY 2020-21 signed.pdf5 Jul 2025
Form 5 (FY 2021-2022)File: Form 5 FY 2021-22 signed.pdf5 Jul 2025
Form 5 (FY 2022-2023)File: Form 5 FY 2022-23 signed.pdf5 Jul 2025
Form 5 (FY 2023-2024)File: Form 5 FY 2023-24 signed.pdf5 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25 signed.pdf5 Jul 2025
Declaration in FORM BFile: FORM_B_NOT.PDF8 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE_FORM_1.PDF8 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM_2A.PDF8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM_2A.PDF8 Jul 2024
Disclosure of sold/ booked inventoryFile: BOOK_SOLD_INVENTORY.PDF8 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CA_compressed.pdf8 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5.PDF8 Jul 2024
Other - LegalFile: FORMAT_B.PDF8 Jul 2024
PAN CardFile: pan_soleyes.pdf7 Dec 2019
Declaration in FORM BFile: FORM B AFFIDAVIT-NOTARISED.pdf7 Dec 2019
Details of encumbrancesFile: Encumbrance certificate.pdf6 Dec 2019
Copy of the legal title reportFile: Search report Indu Pavilion.pdf5 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect_certificate_form1.pdf5 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate Form 2 07-11-2019.pdf5 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf5 Dec 2019
Proforma of Allotment letterFile: Agreement Indu_pavilio Update 09-11-2019.pdf4 Dec 2019
Layout approvalFile: 1-12.pdf20 Nov 2019
Building plan approvalFile: 2-12.pdf20 Nov 2019
Building plan approvalFile: 3-12.pdf20 Nov 2019
Building plan approvalFile: 4-12.pdf20 Nov 2019
Building plan approvalFile: 5-12.pdf20 Nov 2019
Building plan approvalFile: 6-12.pdf20 Nov 2019
Building plan approvalFile: 7-12.pdf20 Nov 2019
Building plan approvalFile: 8-12.pdf20 Nov 2019
Building plan approvalFile: 9-12.pdf20 Nov 2019
Building plan approvalFile: 10-12.pdf20 Nov 2019
Building plan approvalFile: 11-12.pdf20 Nov 2019
Building plan approvalFile: 12-12.pdf20 Nov 2019
Copy of Layout Approval (in case of layout)File: 1-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 2-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 3-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 4-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 5-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 6-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 7-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 8-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 9-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 10-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 11-12.pdf20 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 12-12.pdf20 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE PAGE 1 _INDU PAVILLION-converted.pdf20 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE PAGE 2 _INDU PAVILLION-converted.pdf20 Nov 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MEENAKSHI GREENS11TH CROSS ROAD MUNICIPAL WARD 57 J P NAGAR BANGALORE 5600786CompletedMar 2014Late, Apr 2014

How this compares with Ahmednagar

12%of this project is bookeddistrict median 10%
7%of Ahmednagar projects moved their completion datethis one moved by 32 months
28%of Ahmednagar registrations have lapsed or been cancelledthis one is among them

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep INDU PAVILION on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SAVEDI490+ in Ahmednagar

2 kmINDU PAVILIONCompleted 6Lapsed / revoked 1Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED

SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED has 1 registration on MahaRERA, including INDU PAVILION. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What does it mean that INDU PAVILION shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if INDU PAVILION is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDU PAVILION?

The registered promoter entity is SOLUTIIONEYES CONSULTANCY SERVICESS & CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDU PAVILION?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INDU PAVILION?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDU PAVILION?

The professionals named in the filing: Architect: SATISH N JOSHI; Engineer: ABHAY SURESHCHAND PATWA; Engineer: HEMANT BALASAHEB SHINDE; Chartered Accountant: PRITESH ACHALIYA; Chartered Accountant: J P N R & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDU PAVILION?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDU PAVILION. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDU PAVILION to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.