Home / Browse projects / Pune, Maharashtra / Indrayani Sankalp-MPMC
Indrayani Sankalp-MPMC
RG-MH-24150 · RERA P52100007861 · Last updated on MahaRERA portal: 25 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 20 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indrayani Sankalp-MPMC is a Residential / Group Housing project by BEBANCO DEVELOPERS LTD in Pune, Maharashtra, registered with MahaRERA as P52100007861 on 18 Aug 2017. Possession was promised by 5 Feb 2025 and is now 20 months past that date. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameIndrayani Sankalp-MPMC
- TypeResidential / Group Housing
- Location
- WADGAON SHINDE ROAD
- SHINDE VASTI
- LOHGAON
- Haveli
- Pune
- 411047
- Pincode411047
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100007861
- ReraGenie IDRG-MH-24150
Builder
- NameBEBANCO DEVELOPERS LTD
- Entity typeCompany
- Managing DirectorDIGANT LAXMIDAS KAPADIA
- ChairpersonDIGANT LAXMIDAS KAPADIA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion5 Feb 2025
- Revised completionRevised to 5 Feb 2025 (originally 6 Feb 2024)
- Buildings60 building records
- Documents filed119 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1-A | NA | 16 | 0 | 0 | 0 | 0 |
| A1-B | NA | 16 | 0 | 0 | 0 | 0 |
| A1-C | NA | 16 | 0 | 0 | 0 | 0 |
| A1-D | NA | 16 | 0 | 0 | 0 | 0 |
| A1-E | NA | 16 | 0 | 0 | 0 | 0 |
| A1-F | NA | 16 | 0 | 0 | 0 | 0 |
| A1-G | NA | 16 | 0 | 0 | 0 | 0 |
| A1-H | NA | 16 | 0 | 0 | 0 | 0 |
| A1-I | NA | 16 | 0 | 0 | 0 | 0 |
| A1-J | NA | 16 | 0 | 0 | 0 | 0 |
| A1-K | NA | 16 | 0 | 0 | 0 | 0 |
| A1-L | NA | 16 | 0 | 0 | 0 | 0 |
| A1-M | NA | 16 | 0 | 0 | 0 | 0 |
| A1-N | NA | 16 | 0 | 0 | 0 | 0 |
| A1-O | NA | 16 | 0 | 0 | 0 | 0 |
| A1-P | NA | 16 | 0 | 0 | 0 | 0 |
| S1 | NA | 16 | 0 | 0 | 0 | 0 |
| S2 | NA | 16 | 0 | 0 | 0 | 0 |
| B1 | NA | 16 | 0 | 0 | 0 | 0 |
| B2 | NA | 16 | 0 | 0 | 0 | 0 |
| B3 | NA | 16 | 0 | 0 | 0 | 0 |
| B4 | NA | 16 | 0 | 0 | 0 | 0 |
| B5 | NA | 16 | 0 | 0 | 0 | 0 |
| B6 | NA | 16 | 0 | 0 | 0 | 0 |
| B7 | NA | 16 | 0 | 0 | 0 | 0 |
| B8 | NA | 16 | 0 | 0 | 0 | 0 |
| B9 | NA | 16 | 0 | 0 | 0 | 0 |
| B10 | NA | 16 | 0 | 0 | 0 | 0 |
| CD-1 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-3 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-4 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-5 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-6 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-7 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-8 | NA | 15 | 0 | 0 | 0 | 0 |
| A1-Q SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| A1-R SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| A1-S SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| A1-T SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| A1-U SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| A1-V SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B11 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B12 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B13 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B14 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B15 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B16 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B17 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| B18 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| CD-11 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-12 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-13 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-14 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-15 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-16 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| A1 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| A2 SECTOR 2 | NA | 16 | 0 | 0 | 0 | 0 |
| CD-9 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
| CD-10 SECTOR 2 | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 25 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 60 buildings; the table lists the first 20.
115 of 660 construction stages are filed complete across 60 buildings. The stage furthest along is Slabs of Super Structure, at 94%.
A1-A27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-B52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 87% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-C52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 87% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-D43%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 34% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 34% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-E45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 94% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-F45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-G27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-H38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 7% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 7% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-I37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 7% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-J27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-K27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-L38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 7% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 7% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-M36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-N36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-O27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-P27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S127%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S227%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B127%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B249%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 73% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 67% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 5% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2673
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A1-A | 1 | 38 | 39 |
| A1-B | 1 | 38 | 39 |
| A1-C | 1 | 38 | 39 |
| A1-D | 1 | 38 | 39 |
| A1-E | 1 | 38 | 39 |
| A1-F | 1 | 38 | 39 |
| A1-G | 1 | 38 | 39 |
| A1-H | 1 | 38 | 39 |
| A1-I | 1 | 38 | 39 |
| A1-J | 1 | 38 | 39 |
| A1-K | 1 | 38 | 39 |
| A1-L | 1 | 38 | 39 |
| A1-M | 1 | 38 | 39 |
| A1-N | 1 | 38 | 39 |
| A1-O | 1 | 38 | 39 |
| A1-P | 1 | 38 | 39 |
| S1 | 24 | 30 | 54 |
| S2 | 24 | 30 | 54 |
| B1 | 1 | 86 | 87 |
| B2 | 1 | 86 | 87 |
| B3 | 1 | 86 | 87 |
| B4 | 1 | 86 | 87 |
| B5 | 1 | 86 | 87 |
| B6 | 1 | 86 | 87 |
| B7 | 1 | 86 | 87 |
| B8 | 1 | 86 | 87 |
| B9 | 1 | 86 | 87 |
| B10 | 1 | 86 | 87 |
| A1-Q SECTOR 2 | 0 | 38 | 38 |
| A1-R SECTOR 2 | 1 | 38 | 39 |
| A1-S SECTOR 2 | 1 | 38 | 39 |
| A1-T SECTOR 2 | 1 | 38 | 39 |
| A1-U SECTOR 2 | 1 | 38 | 39 |
| A1-V SECTOR 2 | 1 | 38 | 39 |
| B11 SECTOR 2 | 1 | 84 | 85 |
| B12 SECTOR 2 | 1 | 84 | 85 |
| B13 SECTOR 2 | 1 | 84 | 85 |
| B14 SECTOR 2 | 1 | 84 | 85 |
| B15 SECTOR 2 | 1 | 84 | 85 |
| B16 SECTOR 2 | 1 | 84 | 85 |
| B17 SECTOR 2 | 1 | 84 | 85 |
| B18 SECTOR 2 | 1 | 84 | 85 |
| A1 SECTOR 2 | 1 | 78 | 79 |
| A2 SECTOR 2 | 1 | 78 | 79 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V KA |
| Engineer | ELEMATIC INDIA PVT LTD |
| Engineer | Amol Tambe |
| Chartered Accountant | R S A R and Associates |
| Partner | Role in project |
|---|---|
| BEBANCO DEVELOPERS LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, The current real estate project consists of 60 (36 + 24) nos. of buildings in 2 phases. The development work of buildings is at various stages as seen from the site photographs attached herewith. The completion of project will take some more time and therefore we request this Hon'ble Authority to permit extension of the project registration as per rules. Thanking you, Yours truly for Bebanco Developers Limited Director
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 115/2014 | hON dISTRICT COURT PUNE | FOR CROSS EXAMINATION OF WITNESS |
| 8181/2017 | HON BOMBAY HIGH COURT | FILED |
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400661 | PRAVEEN SATPAL JAIN | BEBANCO DEVELOPERS LTD | 05/11/2024 |
| CC12502082 | CHANDRAKANT GOPAL KHAIRMODE | BEBANCO DEVELOPERS LTD | 25/06/2025 |
| CC12502209 | Fawziya Mujeeb Karjatkar | BEBANCO DEVELOPERS LTD | 03/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf | 25 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate- Form 1 (1).pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202409_Form-3_Part1.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202409_Form-3_Part2.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: CA Certificate - Form 3.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202503_Form-3_Part1.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202503_Form-3_Part2.pdf | 25 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr 300924.pdf | 25 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf | 25 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf | 25 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate- Form 1 (1).pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202409_Form-3_Part1.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202409_Form-3_Part2.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: CA Certificate - Form 3.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202503_Form-3_Part1.pdf | 25 Jun 2025 |
| Certificates of CA (Form 3)File: 202503_Form-3_Part2.pdf | 25 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr 300924.pdf | 25 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf | 25 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- Form 2.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 202406_Sold.pdf | 20 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: I_MPMC_Form-1.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: I_MPMC_Form-2.pdf | 18 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202406_Ar.pdf | 23 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202406_Er.pdf | 23 Jul 2024 |
| Certificates of CA (Form 3)File: 202406_CA.pdf | 23 Jul 2024 |
| Declaration in FORM BFile: scanned copy of Affidavit.pdf | 30 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_2023-24.pdf | 30 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23_Form-5.pdf | 30 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202403_Ar.pdf | 19 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202403_Er.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 202403_Sold.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: 202403_CA.pdf | 19 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DLK Declaration.pdf | 19 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: JDK Declaration.pdf | 19 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: NDK Declaration.pdf | 19 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BDL Declaration.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: 201709_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201712_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201803_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201806_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201809_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201812_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201903_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201906_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201909_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 201912_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202003_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202006_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202009_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202012_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202103_CA.pdf | 14 Mar 2024 |
| Certificates of CA (Form 3)File: 202106_CA.pdf | 14 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202312_Ar.pdf | 20 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202309_Er.pdf | 20 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202312_Er.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: 202309_CA.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: 202312_CA.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf | 4 Oct 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 4 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 4 Certificates of CA (Form 5).pdf | 4 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf | 14 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf | 14 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A_2022-23.pdf | 14 Jul 2023 |
| CERSAI detailsFile: 202212_CERSAI.pdf | 20 Apr 2023 |
| CERSAI detailsFile: 202303_CERSAI.pdf | 20 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architecture Certificate.pdf | 17 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202203_Er.pdf | 17 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202206_Er.pdf | 17 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A_2021-22.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: 202206_CA.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: 202209_CA.pdf | 17 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_2021-22.pdf | 17 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202212_Ar.pdf | 20 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202212_Er.pdf | 20 Jan 2023 |
| CERSAI detailsFile: 202112_CERSAI.pdf | 20 Jan 2023 |
| CERSAI detailsFile: 202203_CERSAI.pdf | 20 Jan 2023 |
| CERSAI detailsFile: 202212_CERSAI.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: 202212_CA.pdf | 20 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Indrayani Sankalp-MPMC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHINDE VASTI13,700+ in Pune
NESTERRA - PHASE 1
Triaa Skyscrapers LLP
Divine Garden Phase II
SHRIRAM ASSOCIATES
Divine Garden Phase 1
SHRIRAM ASSOCIATES
Solitaire Business Hub Viman Nagar Phase 1
Classic Promoters and Builders Private Lim
Krishna Lake Town
Krishna Housing
NIVASA ENCHANTE - PHASE I
NIVASA ASSOCIATES
Builder: BEBANCO DEVELOPERS LTD
BEBANCO DEVELOPERS LTD has 1 registration on MahaRERA, including Indrayani Sankalp-MPMC. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Indrayani Sankalp-MPMC shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Indrayani Sankalp-MPMC is delayed beyond 5 Feb 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indrayani Sankalp-MPMC?
The registered promoter entity is BEBANCO DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indrayani Sankalp-MPMC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Indrayani Sankalp-MPMC?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Indrayani Sankalp-MPMC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indrayani Sankalp-MPMC?
The professionals named in the filing: Architect: V KA; Engineer: ELEMATIC INDIA PVT LTD; Engineer: Amol Tambe; Chartered Accountant: R S A R and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indrayani Sankalp-MPMC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback