Home / Browse projects / Raigarh, Maharashtra / INDRAPRASTHA PHASE 2 Includes Building no. 5,9

Completed No litigation declared Residential / Group Housing project

INDRAPRASTHA PHASE 2 Includes Building no. 5,9

By M/s Indraprastha Associates

RG-MH-46227 · RERA P52000018038 · Last updated on MahaRERA portal: 19 May 2022

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
May 2021Possession promisedregistration recorded completed
14 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

INDRAPRASTHA PHASE 2 Includes Building no. 5,9 is a Residential / Group Housing project by M/s Indraprastha Associates in Raigarh, Maharashtra, registered with MahaRERA as P52000018038 on 10 Oct 2018. The registration is recorded completed; possession was promised by 31 May 2021.

At a glance

Project

  • NameINDRAPRASTHA PHASE 2 Includes Building no. 5,9
  • TypeResidential / Group Housing
  • Location
    • Near Gaondevi Mandir Gondhlpada
    • Gondhalpada
    • Alibag
    • Raigarh
    • 402201
  • Pincode402201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000018038
  • ReraGenie IDRG-MH-46227

Builder

  • NameM/s Indraprastha Associates
  • Entity typeOthers
  • PartnersJayant Madhukar Wakharkar, Kamlesh Jairamdas Talreja, Reshma Kamlesh Talreja, Shalaka Chandrashekhar Wagle
  • Named personsJAYANT MADHUKAR WAKHARKAR, KAMLESH JAIRAMDAS TALREJA, CHANDRASHEKHAR WAGLE, SHALAKA CHANDRASHEKHAR WAGLE, RESHMA KAMLESH TALREJA
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2018PromisedMay 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Oct 2018
  • Promised completion31 May 2021
  • Revised completionNone
  • Buildings2 building records
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 5NA60000
BUILDING NO 9NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

BUILDING NO 579%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 979%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered2
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 5123
BUILDING NO 9123

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,746 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2746.0
Proposed, not sanctioned2,746 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchALIBAG

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHINAY JOGI
EngineerMAHESH CHAVAN
PartnerRole in project
M/s Indraprastha Associates-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000001333May 2021 → May 2022

Reason as filed by the promoter1. Delay from Authority, to issue the plinth completion certificate. (Date of Application 06/09/2018 Received Plinth Completion certificate on 07/12/2018) 2. Ban on sand supply by Dist. Collector Raigad due to CRZ etc.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 May 2022

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf19 May 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy certificate.pdf13 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bldg 05 Arch Certificate Form 1.pdf1 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bldg 09 Arch Certificate Form 1.pdf1 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf1 Mar 2022
Certificates of CA (Form 3)File: CA Cetificate Form 3.pdf1 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate BLDG 05.pdf29 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate BLDG 09.pdf29 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RCC engineer certificate.pdf29 Oct 2021
Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf29 Oct 2021
Certificates of CA (Form 5)File: Form 5 CA Certificate.pdf29 Oct 2021
Declaration about Commencement CertificateFile: Declaration.pdf6 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 05.pdf6 Jul 2021
Certificates of CA (Form 5)File: CA Certificate.pdf6 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Bldg 05.pdf5 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Bldg 09.pdf5 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC consultant certificate.pdf5 Jul 2021
Certificates of CA (Form 5)File: CA Certificate.pdf5 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA -BLDG-05-80 _compressed.pdf29 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA -BLDG-09-80_compressed.pdf29 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC Consultant Certificate.pdf29 Oct 2020
Certificates of CA (Form 3)File: FORM 3.pdf29 Oct 2020
Certificates of CA (Form 5)File: FORM 5.pdf29 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 09.pdf26 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE OF ENGINEER.pdf26 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect Certificate.pdf26 Feb 2020
Certificates of CA (Form 3)File: CA Certificate.pdf26 Feb 2020
Certificates of CA (Form 5)File: CA Certificate.pdf26 Feb 2020
Certificates of CA (Form 5)File: CA Certificate.pdf26 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Associated Consulting Engineers Form 2_compressed.pdf22 Oct 2019
Certificates of CA (Form 3)File: CA Certificate Form 3.pdf22 Oct 2019
Certificates of CA (Form 5)File: CA Certificate Form 5.pdf22 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf3 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC CONSULTANT CERTIFICATE_compressed.pdf3 Jun 2019
Certificates of CA (Form 3)File: CA Certificate.pdf3 Jun 2019
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf3 Jun 2019
Certificates of CA (Form 5)File: CA CERTIFIED Form 5.pdf14 Feb 2019
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf15 Jan 2019
OtherFile: Plinth Completion letter.pdf8 Jan 2019
Proforma of Allotment letterFile: Agreement to Sale.pdf26 Oct 2018
Proforma of Allotment letterFile: Rera Final Agreement.pdf26 Sep 2018
Building plan approvalFile: SANCTION LAYOUT.pdf24 Sep 2018
Layout approvalFile: SANCTION LAYOUT.pdf24 Sep 2018
PAN CardFile: IPA PANCARD.pdf24 Sep 2018
Copy of the legal title reportFile: Title Report.pdf24 Sep 2018
Details of encumbrancesFile: Encumbrances Cetificate.pdf24 Sep 2018
Copy of Layout Approval (in case of layout)File: SANCTION LAYOUT.pdf24 Sep 2018
Building Plan Approval (IOD)File: SANCTION LAYOUT.pdf24 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf24 Sep 2018
Declaration in FORM BFile: Affidavit.pdf24 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf24 Sep 2018
Certificates of CA (Form 3)File: CA Certificate.pdf24 Sep 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
INDRAPRASTHA-PHASE 1GONDHALPADA ALIBAG120CompletedDec 2017Apr 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INDRAPRASTHA PHASE 2 Includes Building no. 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gondhalpada5,900+ in Raigarh

2 kmINDRAPRASTHA PHASE 2 IncCompleted 12Lapsed / revoked 10Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: M/s Indraprastha Associates

M/s Indraprastha Associates has 2 registrations on MahaRERA, including INDRAPRASTHA PHASE 2 Includes Building no. 5,9 and Indraprastha Building 6. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if INDRAPRASTHA PHASE 2 Includes Building no. 5,9 is delayed beyond 31 May 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDRAPRASTHA PHASE 2 Includes Building no. 5,9?

The registered promoter entity is M/s Indraprastha Associates, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDRAPRASTHA PHASE 2 Includes Building no. 5,9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INDRAPRASTHA PHASE 2 Includes Building no. 5,9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDRAPRASTHA PHASE 2 Includes Building no. 5,9?

The professionals named in the filing: Architect: ABHINAY JOGI; Engineer: MAHESH CHAVAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDRAPRASTHA PHASE 2 Includes Building no. 5,9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDRAPRASTHA PHASE 2 Includes Building no. 5,9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDRAPRASTHA PHASE 2 Includes Building no. 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.