Home / Browse projects / Sangli, Maharashtra / INDOSHIVA ASSET
INDOSHIVA ASSET
RG-MH-22548 · RERA P53100032541 · Last updated on MahaRERA portal: 12 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
INDOSHIVA ASSET is a Others project by INDOSHIVA CONSTRUCTION in Sangli, Maharashtra, registered with MahaRERA as P53100032541 on 10 Jan 2022. Possession was promised by 31 Mar 2024 and is now 31 months past that date.
At a glance
Project
- NameINDOSHIVA ASSET
- TypeOthers
- Location
- VISHRAMBHAG GANPATI TEMPLE ROAD
- VISHRAMBHAG
- SANGLI
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100032541
- ReraGenie IDRG-MH-22548
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Jan 2022
- Promised completion31 Mar 2024
- Revised completionNone
- Buildings1 building record
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INDOSHIVA ASSET | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
INDOSHIVA ASSET: 93% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 12 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership10
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| CHANDRASHEKHAR ALIS HARI NARHAR KULKARNI | Sangli Miraj Kupwad (M Corp.) | Sangli |
| VAISHALI CHANDRASHEKHAR ALIS HARI KULKARNI | Sangli Miraj Kupwad (M Corp.) | Sangli |
| NIRMALA MARUTI HARANE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| DINESH GAJANAN KAMAT | Sangli Miraj Kupwad (M Corp.) | Sangli |
| KIRAN BAPU SHINDE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| ABHAYKUMARL BHASKARRAO PATIL | Sangli Miraj Kupwad (M Corp.) | Sangli |
| KSHAMA SHANKAR BHORE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| ANJALI DINESH KAMAT | Sangli Miraj Kupwad (M Corp.) | Sangli |
| SHUBHANGI KIRAN SHINDE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| PRAKASH NARHAR KULKARNI | Sangli Miraj Kupwad (M Corp.) | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR VIVEK DESHPANDE |
| Engineer | DR N K PATIL |
| Chartered Accountant | GOVIND SONI |
| Partner | Role in project |
|---|---|
| INDOSHIVA CONSTRUCTION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Feb 2025
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ASSET COMMENCEMENT CERTIFICATE COMPLITION SMKC.pdf | 12 Feb 2025 |
| Declaration in FORM BFile: FORM B UPDATED ASSET 1 mb.pdf | 21 Dec 2024 |
| Declaration in FORM BFile: Declaration As per Scrutiny Desk 2.pdf | 5 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 New Asset.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 5 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Final Sanctioned Letter Asset.pdf | 5 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Recent Sold Booked Alloted Inventory Asset - Copy.pdf | 5 Dec 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200330362608_For_Asset_Based_Search_05_12_2024_22_21_14_498.pdf | 5 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5 Asset 23-24.pdf | 5 Dec 2024 |
| Declaration in FORM BFile: affidavit for extension application asset.pdf | 31 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Recent Sold Booked Alloted Inventory Asset.pdf | 31 Oct 2024 |
| Proforma of Agreement for saleFile: Agreement Format.pdf | 31 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CA 22-23.pdf | 31 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Indoshiva Asset Architect Form 1 1mb.pdf | 6 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Indoshiva Asset form-5.pdf | 6 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Indoshiva Asset form-5.pdf | 6 Mar 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200226428605_For_Asset_Based_Search_22_12_2021_19_27_56_966.pdf | 22 Dec 2021 |
| Building plan approvalFile: ASSET Sanctioned Plan 1 mb.pdf | 2 Nov 2021 |
| Details of encumbrancesFile: Details of encumbrances Asset.pdf | 2 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: ASSET Sanctioned Plan 1 mb.pdf | 2 Nov 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: SMKC permission Asset1mb.pdf | 2 Nov 2021 |
| Copy of the legal title reportFile: Asset legal report New.pdf | 23 Oct 2021 |
| Details of encumbrancesFile: Details of Encumbrances MahaRera Asset.pdf | 23 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf | 23 Oct 2021 |
| Building plan approvalFile: indoshiva asset plan pdf.pdf | 19 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: indoshiva asset plan pdf.pdf | 19 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate letter.pdf | 19 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration of commencement certificate(1).pdf | 19 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate request(1).pdf | 19 Oct 2021 |
| Layout approvalFile: Cts 9756 Layout plan.pdf | 18 Oct 2021 |
| PAN CardFile: panpdf.pdf | 18 Oct 2021 |
| Copy of the legal title reportFile: Asset legal report 1 mb.pdf | 18 Oct 2021 |
| Details of encumbrancesFile: Details of Encumbrances MahaRera Asset.pdf | 18 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: Cts 9756 Layout plan.pdf | 18 Oct 2021 |
| Declaration in FORM BFile: ASSET Form B affadavit 1 MB.pdf | 18 Oct 2021 |
| Proforma of Allotment letterFile: Agreement Format.pdf | 18 Oct 2021 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 18 Oct 2021 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| INDOSHIVA TOWERP53100030141 | VAKHARBHAG, Sangli | 22 | Jul 2021 | Completed | Dec 2022 | Late, Apr 2024 |
| INDOSHIVA PRIDE | CTS 12950 REVENUE COLONY BAPAT MALA SANGLI 416416 | 18 | - | Completed | Jun 2021 | Mar 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep INDOSHIVA ASSET on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VISHRAMBHAG, SANGLI790+ in Sangli
Filed coordinates, straight-line distance. 195 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: INDOSHIVA CONSTRUCTION
INDOSHIVA CONSTRUCTION has 4 registrations on MahaRERA, including INDOSHIVA PRIDE and INDOSHIVA TOWER. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that INDOSHIVA ASSET shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if INDOSHIVA ASSET is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of INDOSHIVA ASSET?
The registered promoter entity is INDOSHIVA CONSTRUCTION, a partnership as per the filing. Its GSTIN 27AAHFI3627E1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in INDOSHIVA ASSET?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for INDOSHIVA ASSET?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at INDOSHIVA ASSET?
The professionals named in the filing: Architect: AR VIVEK DESHPANDE; Engineer: DR N K PATIL; Chartered Accountant: GOVIND SONI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INDOSHIVA ASSET?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.