Home / Browse projects / Nashik, Maharashtra / INDO ASIAN SIGNATURE

Registered No litigation declared Residential / Group Housing project

INDO ASIAN SIGNATURE

By INDO ASIAN BUILDCON PRIVATE LIMITED

RG-MH-32736 · RERA P51600080423 · Last updated on MahaRERA portal: 30 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2030Possession promisedno revision filed
4 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 3%
101 of 101Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

INDO ASIAN SIGNATURE is a Residential / Group Housing project by INDO ASIAN BUILDCON PRIVATE LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600080423 on 3 Jun 2025. Possession is promised by 31 Mar 2030. 0 of the 101 units on this registration are recorded sold or booked, and 4 of 33 construction stages are filed complete.

At a glance

Project

  • NameINDO ASIAN SIGNATURE
  • TypeResidential / Group Housing
  • Location
    • NA
    • MAUJE
    • TALEGOAN
    • Igatpuri (M Cl)
    • Igatpuri
    • Nashik
    • 422403
  • Pincode422403
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600080423
  • ReraGenie IDRG-MH-32736

Builder

  • NameINDO ASIAN BUILDCON PRIVATE LIMITED
  • Entity typeCompany

Key dates

this monthRegisteredJun 2025PromisedMar 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jun 2025
  • Promised completion31 Mar 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed45 files

Current status

0%0 of 101 units booked
4.8%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1 A WINGNA9831031
BUILDING NO 1 B WINGNA9831031
BUILDING NO 2NA9839039

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 3%.

BUILDING NO 1 A WING18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 1 B WING18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed294

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots294
Closed/Covered294
BuildingClosed/CoveredTotal
BUILDING NO 1 A WING9898
BUILDING NO 1 B WING9898
BUILDING NO 29898

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Oct 2025
LandownerVillageDistrict
SANJAY GOPAL YADAVIgatpuri (M Cl)Nashik
RAJENDRA GOPAL YADAVIgatpuri (M Cl)Nashik
NANDAN GOPAL YADAVIgatpuri (M Cl)Nashik
SUSHMA GOPAL YADAVIgatpuri (M Cl)Nashik

Approvals and building plan

Sanctioning authorityIgatpuri Municipal Council
Permissible FSI15808.34
Proposed, not sanctioned5,808 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 CENTRUM BUILDING WAGLE ESTATE THANE WEST 400604
Estimated costRs 16.72 cr
Cost incurredRs 79.78 lakh
Work done4.77%
BuildingWingEstimatedIncurred
BUILDING NO 2NARs 6.33 cr-
BUILDING NO 1 A WINGNARs 3.80 crRs 39.89 lakh
BUILDING NO 1 B WINGNARs 3.80 crRs 39.89 lakh
-NARs 2.79 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP D ARCHITECT
EngineerDILIP G VEKHANDE
Chartered AccountantLILANI AND CO
Chartered AccountantVINOD KUMAR JAIN
PartnerRole in project
INDO ASIAN BUILDCON PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2030

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_ MARCH 26_ INDFO ASAIN SIGNATURES.pdf30 Apr 2026
Withdrawal Update Form 2File: FORM 2_ MARCH 26_ INDO ASAIN SIGNATURES.pdf30 Apr 2026
Withdrawal Update Form 3File: FORM 3_ MARCH 26_ INDO ASAIN SIGNATURES.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1_DEC25_INDOASIAN SIGNATURES.pdf21 Jan 2026
Withdrawal Update Form 2File: FORM 2_DEC25_INDOASIAN SIGNATURES.pdf21 Jan 2026
Withdrawal Update Form 3File: FORM 3_DEC25_INDOASIAN SIGNATURES.pdf21 Jan 2026
Withdrawal Update Form 1File: FORM 1_SEP 25_INDOASIAN SIGNATURES.pdf17 Nov 2025
Withdrawal Update Form 2File: FORM 2_SEP 25_INDOASIAN SIGNATURES.pdf17 Nov 2025
Withdrawal Update Form 3File: FORM 3_SEP 25_INDOASIAN SIGNATURES.pdf17 Nov 2025
Withdrawal Update Form 1File: FORM 1_ JUNE 25_ INDO ASAIN SIGNATURES.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM 2_ JUNE 25_ INDO ASAIN SIGNATURES.pdf17 Oct 2025
Withdrawal Update Form 3File: FORM 3_ JUNE 25_ INDO ASAIN SIGNATURES.pdf17 Oct 2025
Commencement Certificates / NA Order for plotted developmentFile: WA.pdf21 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A).pdf22 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: LETTER .pdf22 Mar 2025
Copy of the legal title reportFile: 1 Copy of the legal title report (1) (1).pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf9 Mar 2025
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal .pdf4 Mar 2025
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance .pdf4 Mar 2025
Proforma of Allotment letterFile: 18 Proforma of Allotment letter .pdf4 Mar 2025
Declaration in FORM BFile: 9 Declaration in FORM B .pdf4 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 CA Certificate on Project Cost Fund withdrawal (Form 3) - Land Cost Declaration.pdf4 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: 7 Commencement Certificates NA Order for plotted development.pdf4 Mar 2025
Declaration about Commencement CertificateFile: 8 Declaration about Commencement Certificate .pdf4 Mar 2025
CERSAI detailsFile: 12 CERSAI details .pdf4 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 20 Declaration about all RERA Designated Bank Accounts (Format A) - Declaration for Landow4 Mar 2025
Deviation Report with respect to Allotment letterFile: 23 Deviation Report with respect to Allotment letter .pdf4 Mar 2025
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal .pdf4 Mar 2025
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance .pdf4 Mar 2025
Other - TechnicalFile: 26 Other - Technical Annexure A.pdf4 Mar 2025
Deviation Report with respect to model copy of AgreementFile: 24 Deviation Report with respect to model copy of Agreement .pdf4 Mar 2025
Proforma of Agreement for saleFile: 17 Proforma of Agreement for sale .pdf4 Mar 2025
Proforma of Agreement for saleFile: 17 a Proforma of Agreement for sale .pdf4 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 16 a Disclosure of Interest in Other Real Estate Organizations .pdf4 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 16 b Disclosure of Interest in Other Real Estate Organizations .pdf4 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 22 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)-4 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: 13 Disclosure for securedunsecured finance availed for the project.pdf4 Mar 2025
Layout approvalFile: 5 Copy of Layout Approval (in case of layout).pdf28 Feb 2025
Building plan approvalFile: 6-1 Building Plan Approval.pdf28 Feb 2025
Building plan approvalFile: 6-2 Building Plan Approval.pdf28 Feb 2025
PAN CardFile: 1 PAN CARD.pdf28 Feb 2025
Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval (in case of layout).pdf28 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 6-1 Building Plan Approval.pdf28 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 6-2 Building Plan Approval.pdf28 Feb 2025
Other - LegalFile: 25 Legal Other- 7-12.pdf28 Feb 2025

How this compares with Nashik

0%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INDO ASIAN SIGNATURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAUJE, TALEGOAN4,100+ in Nashik

2 kmINDO ASIAN SIGNATURECompleted 1Lapsed / revoked 3Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: INDO ASIAN BUILDCON PRIVATE LIMITED

INDO ASIAN BUILDCON PRIVATE LIMITED has 1 registration on MahaRERA, including INDO ASIAN SIGNATURE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if INDO ASIAN SIGNATURE is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDO ASIAN SIGNATURE?

The registered promoter entity is INDO ASIAN BUILDCON PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDO ASIAN SIGNATURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INDO ASIAN SIGNATURE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDO ASIAN SIGNATURE?

The professionals named in the filing: Architect: P D ARCHITECT; Engineer: DILIP G VEKHANDE; Chartered Accountant: LILANI AND CO; Chartered Accountant: VINOD KUMAR JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDO ASIAN SIGNATURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDO ASIAN SIGNATURE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDO ASIAN SIGNATURE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.