Home / Browse projects / Dakshina Kannada, Karnataka / INDIRA RESIDENCY
INDIRA RESIDENCY
By SHREE VIGNESHWARA DEVELOPERS
RG-KA-23002 · RERA PRM/KA/RERA/1257/334/PR/300525/007801 · Last updated on RERA Karnataka portal: 12 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
INDIRA RESIDENCY is a Residential/Group Housing project by SHREE VIGNESHWARA DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/300525/007801 on 30 May 2025. Possession is promised by 31 Mar 2029. 14 of the 28 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.
At a glance
Project
- NameINDIRA RESIDENCY
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- 575003
- Pincode575003
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/300525/007801
- ReraGenie IDRG-KA-23002
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 May 2025
- Promised completion31 Mar 2029
- Revised completionNone
- Buildings1 building record
- Documents filed80 files
Current status
Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INDIRA RESIDENCY | - | - | - | 28 | 0 | 28 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 50%.
Building: 34% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 50% |
| Masonry Construction | 40% |
| Plastering inside , outside & Ceiling | 30% |
| Joinery: Doors, Windows, Ventilators etc | 25% |
| Basic work of Water supply, Sanitary and Electrification | 20% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 10% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 20% |
| Painting | 10% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 15% |
| Sewage and Drainage System | Yes | 10% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 10% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 10% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 15% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | No | Not applicable |
| Gym | Yes | 0% |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 30% |
| Lifts | Yes | 15% |
| Corridor/Lobbies | Yes | 10% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 15% |
| Terrace | Yes | 15% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| OKAAS VENTURES | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 21.26 cr | Rs 11.45 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chaithanya K Shetty |
| Engineer | Krishna Shetty |
| Chartered Accountant | Harish Khetan |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed80
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/300525/007801 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: C A Certificat.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect's Certificate, I.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers Cert.pdf | 12 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 12 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 12 Oct 2026 |
| Q2 2026-27 Fire and Safety | 12 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form4-CA-Indira Residency.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5-Architect's Certificate, Indira Residency.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form6-Engineer Certificate, Indira Residency.pdf | 13 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 13 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 13 Jul 2026 |
| Q1 2026-27 Fire and Safety | 13 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA Q4 Indira 14042026.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Indira Residency Architect certificate.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Indira Residency Rera.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Indira Form 4 Q3 2526.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Indira Form 5 Q3 2526.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Indira Form 6 Q3 2526.pdf | 15 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 15 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 15 Jan 2026 |
| Q3 2025-26 Fire and Safety | 15 Jan 2026 |
| RTC, survey 666/47B 666/48 666/49 666/47B | - |
| Mutation, survey 666/47B 666/48 666/49 666/47B | - |
| Encumbrance Certificate, survey 666/47B 666/48 666/49 666/47B | - |
| Conversion/Alienation Order, survey 666/47B 666/48 666/49 666/47B | - |
| Sale/Title/Gift Deed, survey 666/47B 666/48 666/49 666/47B | - |
| JDA, survey 666/47B 666/48 666/49 666/47B | - |
| Khatha, survey 666/47B 666/48 666/49 666/47B | - |
| Registration CertificateFile: Annx 1 Firm Registration.pdf | - |
| Partnership DeedFile: Annx 24 Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Annx 59 Form 1 CA.pdf | - |
| Certificate issued by Architect Form 2File: Annx 61 Form 2 Arch.pdf | - |
| Certificate issued by Engineer Form 3File: Annx 60 Form 3 Eng.pdf | - |
| TDR Purchase Deed / Sale DeedFile: Annx 58 TDR Title Deed.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Annx 49 Non Litigation Affidavit.pdf | - |
| Balance Sheet 2023 - 2024File: Annx 70 Balance Sheet FY 2023-24.pdf | - |
| Balance Sheet 2022 - 2023File: Annx 70 Balance Sheet FY 2022-23.pdf | - |
| Balance Sheet 2021 - 2022File: Annx 70 Balance Sheet FY 2021-22.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Annx 71 Profit and Loss FY 2023-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Annx 71 Profit and Loss FY 2022-23.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Annx 71 Profit and Loss FY 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Annx 72 ITR Ack FY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: Annx 72 ITR Ack FY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: Annx 72 ITR Ack FY 2021-22.pdf | - |
| Annx 80 Commencement Certificate | - |
| Annx 81 Approved Plan | - |
| Annx 82 Sectional Drawing | - |
| Annx 83 Certificate for Structural Safety | - |
| Annx 84 Project Specifications | - |
| Annx 85 Brochure_compressed | - |
| Annx 86 Relinquishment Deed | - |
| Annx 87 Proforma Sale Agreement | - |
| Annx 88 Proforma Letter of Allotment | - |
| Annx 89 Declaration Form B Affidavit | - |
| Annx 90 Affidavit Sec 3 | - |
| Annx 91 JD Affidavit cum Declaration | - |
| Annx 92 Advocate Search Report | - |
| Annx 95 MESCOM NOC | - |
| Annx 96 Water NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Annx 99 Fire NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Prospectus/BrochureFile: Annx 85 Brochure_compressed.pdf | - |
| Advertisement Copy 1File: Annx 85 Brochure_compressed.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Pushyaraga | Pushyaraga Behind Hindi Prachar Samithi 2nd Cross Mannagudda Lalbaug Mangalore | Ongoing | Mar 2027 | Not due yet |
| BIMBIS | Bimbis Commercial and Residential Urwastores Ashok Nagar Mangalore | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep INDIRA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
MAHALAXMI
Land Trades Builders and Developers
ROHAN CROWN
PROPERTY REAL ESTATE & DEVELOPERS
NORTHERNSKY EXCELSA
Northern Sky Properties Private Limited
Oldfields by Northernsky
Northernsky Properties Private Limited
LOTUS PEARL
PRANAVA BUILDERS AND DEVELOPERS
See every Dakshina Kannada project, with the district possession charts
Builder: SHREE VIGNESHWARA DEVELOPERS
Shree Vigneshwara Developers has 5 registrations on RERA Karnataka, including Kadri Enclave and BIMBIS. Its filings declare 8 earlier projects, 5 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if INDIRA RESIDENCY is delayed beyond 31 Mar 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of INDIRA RESIDENCY?
The registered promoter entity is SHREE VIGNESHWARA DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ACBFS6815N1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in INDIRA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at INDIRA RESIDENCY?
The professionals named in the filing: Architect: Chaithanya K Shetty; Engineer: Krishna Shetty; Chartered Accountant: Harish Khetan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INDIRA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.