ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Indiabulls Park 5

Registered No litigation declared Commercial project

Indiabulls Park 5

By Lucina Land Development Limited

RG-MH-15632 · RERA P52000025902 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 54 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedmoved 54 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 70%
0 of 7Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

Indiabulls Park 5 is a Commercial project by Lucina Land Development Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000025902 on 27 Jul 2020. Possession is promised by 30 Dec 2030. The completion date has moved by 54 months from the original filing. 7 of the 7 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameIndiabulls Park 5
  • TypeCommercial
  • Location
    • Sawale Apte Road
    • Panvel
    • Kon
    • Raigarh
    • 410207
  • Pincode410207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000025902
  • ReraGenie IDRG-MH-15632

Builder

  • NameLucina Land Development Limited
  • Entity typeCompany
  • Whole-Time DirectorMEYYAPPAN RAMANATHAN
  • DirectorsSSATYAJIT PARRIHAAR, MANISH RIYAL
  • Other registrations8 more →
  • Completed4 of 9

Key dates

this monthRegisteredJul 2020First promiseJun 2026Revised toDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2020
  • Promised completion30 Dec 2030
  • Revised completionRevised to 30 Dec 2030 (originally 30 Jun 2026)
  • Buildings2 building records
  • Documents filed123 files

Current status

100%7 of 7 units booked
50.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
6ANA121011
6BNA121066

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 70%.

6A34%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)70%
Plinth50%
Stilt Floor50%
Slabs of Super Structure30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
6B34%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)70%
Plinth50%
Stilt Floor50%
Slabs of Super Structure30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,466 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Sep 2025

Approvals and building plan

Sanctioning authorityCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
Permissible FSI2305.85
Proposed, not sanctioned2,306 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC Bank House, Senapati Bapat Marg, Lower Parel West
Estimated costRs 4.47 cr
Cost incurredRs 2.23 cr
Work done50.0%
BuildingWingEstimatedIncurred
6BNARs 3.13 crRs 1.56 cr
6ANARs 1.34 crRs 67.01 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRakhi Ubhare
EngineerRamesh Rampure
EngineerVitthal Shinde
EngineerKrishna Kumar Bhatnagar
Chartered AccountantA K O R D & CO
Chartered AccountantR G V A & Associates
PartnerRole in project
Lucina Land Development Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000019559Jun 2026 → Dec 2028

Reason as filed by the promoterThe Self Declaration of Reason for Delay is uploaded below in "OTHER" Tab.

EA31072621975Jun 2026 → Dec 2030

Reason as filed by the promoterReason in detail has been mentioned in Form E

Litigation declared1

CaseCourtStatus
214/2015/2015Civil Judge Senior Division PanvelPending for hearing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600106Bhakti AchrekarLucina Land Development Limited05/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2030

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: LLDL_Indiabulls Park 5.pdf20 Jul 2026
Withdrawal Update Form 2File: Form_2 Park 5.PDF20 Jul 2026
Withdrawal Update Form 3File: LLDL_Indiabullls Park 5.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form_2 A Park-5 (1).PDF1 Jul 2026
Withdrawal Update Form 1File: Form_1 Indiabulls Park 5.PDF16 Jun 2026
Withdrawal Update Form 2File: Form_2 Indiabulls Park_5.PDF16 Jun 2026
Withdrawal Update Form 3File: Indiabulls Park 5.pdf16 Jun 2026
Withdrawal Update Form 1File: Form_1 Indiabulls Park-5.PDF26 Feb 2026
Withdrawal Update Form 2File: Form_2 Indiabulls Park-5.PDF26 Feb 2026
Withdrawal Update Form 3File: Form 3 Q3 Indiabulls Park 5.pdf26 Feb 2026
Withdrawal Update Form 1File: Form_1 Indiabulls Park-5.PDF12 Dec 2025
Withdrawal Update Form 2File: Form_2 Indiabuills Park-5.PDF12 Dec 2025
Withdrawal Update Form 3File: Form 3_Lucina Indiabulls Park 5_compressed.pdf12 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 Indiabulls Park 5.pdf1 Oct 2025
Withdrawal Update Form 1File: Form_1 Indiabulls Park-5.PDF17 Sep 2025
Withdrawal Update Form 2File: Form_2 Indiabulls Park-5 _V1.pdf17 Sep 2025
Withdrawal Update Form 3File: Form_3 Indiabulls Park-5.PDF17 Sep 2025
Form 2A (FY 2024-2025)File: Quality 2A Certificate Panvel Park 5.pdf30 Jun 2025
Form 1File: From_1 Indiabulls Park-5.PDF25 Jun 2025
Form 2File: From_2 Indiabulls Park-5.PDF25 Jun 2025
Form 3File: From-3 Indiabulls Park-5.PDF25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Annexure B- Disclosure of sold Unsold Inventory.PDF25 Jun 2025
OthersFile: Encumbrance, Asset, Debtor Decl_Merge.pdf25 Jun 2025
Details of encumbrances concerned to FinanceFile: Annexure K-Encumbrance Concerned to Finance.PDF27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Panvel Park Phase -5.PDF27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park 5_Final Form 3-min.pdf27 Feb 2025
Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of Sold Unsold.PDF27 Feb 2025
CERSAI detailsFile: Annexure G-Asset Based Declaration.PDF27 Feb 2025
CERSAI detailsFile: Annexure L- Debtor Based Declaration.PDF27 Feb 2025
Details of encumbrances concerned to LegalFile: Annexure K-Encumbrance Concerned to Finance.PDF27 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From_5 Indiabulls Park-5.PDF3 Dec 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Concerned to Finance P5.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_ IB Park-5.PDF12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final_Form 3_Park-5.PDF12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2 Indiabulls Park-5.PDF12 Nov 2024
Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold unsold.pdf12 Nov 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf12 Nov 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf12 Nov 2024
Details of encumbrances concerned to LegalFile: Encumbrance Concerned to Finance P5.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_Form 3_Indiabulls Park 5.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Panvel Park-5.PDF23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Park-5.PDF23 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Indiabulls Panvel Park Phase-5.PDF23 Jul 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Concerned to Finance.PDF20 Jul 2024
Details of encumbrances concerned to LegalFile: Encumbrance Concerned to Finance.PDF20 Jul 2024
Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold unsold.PDF20 Jul 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.PDF20 Jul 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.PDF20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Indiabulls Park-5.PDF7 May 2024
Details of encumbrances concerned to FinanceFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf19 Apr 2024
Details of encumbrances concerned to LegalFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Indiabulls Panvel Park Phase-5.PDF19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Indiabulls Panvel Park Phase-5.PDF19 Apr 2024
Disclosure of sold/ booked inventoryFile: Annexure-B-Disclosure of sold unsold inventory.pdf19 Apr 2024
CERSAI detailsFile: Annexure-G-Asset Based Declaration.pdf19 Apr 2024
CERSAI detailsFile: Annexure-L-Debtor Based Declaration.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Indiabulls Panvel Park Phase-5.PDF19 Apr 2024
Declaration in FORM BFile: Form-B indiabulls park-5.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Park Phase-5.pdf1 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Indiabulls Panvel Park-5.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Panvel Park-5.PDF30 Jan 2024
Details of encumbrances concerned to FinanceFile: Annexure-K- Non Encumbrance Concerned of finance.PDF19 Jan 2024
Details of encumbrances concerned to LegalFile: Annexure-K- Non Encumbrance Concerned of finance.PDF19 Jan 2024
Disclosure of sold/ booked inventoryFile: Annexure-B- Disclosure of Sold _ Booked Inventory.PDF19 Jan 2024
CERSAI detailsFile: Annexure-G- Asset Based Declaration.PDF19 Jan 2024
CERSAI detailsFile: Annexure-L- Debtor Based Declartion.PDF19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Panvel Park Phase 5 Architect Certificate.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Panvel Park Phase 5 Architect Certificate.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Indiabulls Park 5.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Park Phase 5 Engineer Certificate.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Park Phase 5 Engineer Certificate.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: INDIABULLS PARK - 5.PDF21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Panvel Park 5.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Panvel Park - Phase 5.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park 5.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PARK 5.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Indiabulls Park Phase-5.PDF17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Park Phase 5 Engineer Certificate_.PDF17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Indiabull Park 5.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Park 5.pdf29 Sep 2023

How this compares with Raigarh

100%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 54 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Indiabulls Park 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Panvel5,900+ in Raigarh

2 kmIndiabulls Park 5Completed 11Lapsed / revoked 3Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Lucina Land Development Limited

Lucina Land Development Limited has 9 registrations on MahaRERA, including Indiabulls Park 1 and Indiabulls Park 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Indiabulls Park 5 is delayed beyond 30 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Indiabulls Park 5?

The registered promoter entity is Lucina Land Development Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Indiabulls Park 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Indiabulls Park 5?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Indiabulls Park 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Indiabulls Park 5?

The professionals named in the filing: Architect: Rakhi Ubhare; Engineer: Ramesh Rampure; Engineer: Vitthal Shinde; Engineer: Krishna Kumar Bhatnagar; Chartered Accountant: A K O R D & CO; Chartered Accountant: R G V A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Indiabulls Park 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Indiabulls Park 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Indiabulls Park 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.