Home / Browse projects / Raigarh, Maharashtra / Indiabulls Park 3
Indiabulls Park 3
By Lucina Land Development Limited
RG-MH-10538 · RERA P52000000488 · Last updated on MahaRERA portal: 12 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 9 cases
- 33 complaints at MahaRERA
- Completion date moved by 64 months
- 2 extensions taken
- Rs 950.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD
Clear
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indiabulls Park 3 is a Residential / Group Housing project by Lucina Land Development Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000000488 on 18 Jul 2017. Possession is promised by 30 Apr 2030. The completion date has moved by 64 months from the original filing. 768 of the 937 units on this registration are recorded sold or booked, and 12 of 44 construction stages are filed complete. 33 complaints are on record with the regulator.
At a glance
Project
- NameIndiabulls Park 3
- TypeResidential / Group Housing
- Location
- Sawala Apta Road
- Panvel
- Kon
- Raigarh
- 410207
- Pincode410207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000000488
- ReraGenie IDRG-MH-10538
Builder
- NameLucina Land Development Limited
- Entity typeCompany
- Whole-Time DirectorMEYYAPPAN RAMANATHAN
- DirectorsSSATYAJIT PARRIHAAR, MANISH RIYAL
- Other registrations8 more →
- Completed4 of 9
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jul 2017
- Promised completion30 Apr 2030
- Revised completionRevised to 30 Apr 2030 (originally 30 Dec 2024)
- Buildings4 building records
- Documents filed198 files
Current status
Figures as on 12 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 3 C | NA | 44 | 37 | 268 | 0 | 268 |
| 4 A | NA | 44 | 37 | 268 | 0 | 268 |
| 4 B | NA | 44 | 37 | 268 | 0 | 268 |
| 1 | NA | 44 | 36 | 133 | 0 | 133 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 12 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 90%.
3 C47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 80% |
| Plinth | 100% |
| Stilt Floor | 55% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 12% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
4 A48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 90% |
| Plinth | 100% |
| Stilt Floor | 55% |
| Slabs of Super Structure | 65% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 13% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 9% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
4 B43%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 20% |
| Plinth | 100% |
| Stilt Floor | 55% |
| Slabs of Super Structure | 71% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 15% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 7% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
138%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 12% |
| Plinth | 100% |
| Stilt Floor | 55% |
| Slabs of Super Structure | 37% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 8% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 7% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1166
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| 3 C | 363 | 363 |
| 4 A | 255 | 255 |
| 4 B | 255 | 255 |
| 1 | 293 | 293 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 3 C | NA | Rs 161.47 cr | Rs 80.13 cr |
| 1 | NA | Rs 149.97 cr | Rs 74.09 cr |
| 4 A | NA | Rs 123.08 cr | Rs 61.06 cr |
| 4 B | NA | Rs 122.82 cr | Rs 60.92 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rakhi Ubhare |
| Engineer | Ramesh Rampure |
| Engineer | Vitthal Shinde |
| Engineer | Krishna Kumar Bhatnagar |
| Chartered Accountant | R G V A & Associates |
| Chartered Accountant | A K O R D & CO |
| Partner | Role in project |
|---|---|
| Lucina Land Development Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Self Declaration of Reason for Delay is uploaded below in "OTHER" Tab.
Reason as filed by the promoterReasons in detail are mentioned in Form E
Litigation declared9
| Case | Court | Status |
|---|---|---|
| 214/2015/2015 | Civil Judge Senior Division Panvel | Ongoing |
| Consumer Complaint No. 944 /2016 | SCDRC, Maharashtra, Mumbai. | Ongoing |
| Consumer Complaint No. 948 /2016 | SCDRC, Maharashtra, Mumbai. | Ongoing |
| 2016/2016 | SCDRC, Maharashtra, Mumbai. | Ongoing |
| Complaint No. 1155 /2016 | SCDRC, Maharashtra, Mumbai. | Ongoing |
| Complaint No. 122 /2017 | DCDRC, Maharashtra, Mumbai. | Ongoing |
| CC No. 583 /2019 | SCDRC, Mumbai | Ongoing |
| CC No. 202 /2022 | District Consumer Dispute Redressal Forum, Central Mumbai | Ongoing |
| Consumer Complaint No. 508 of 2023/2023 | District Consumer Disputes Redressal commission, Central Mumbai. | Ongoing |
Complaints filed with MahaRERA33
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001291 | PRADIP SHRIPAT PATANKAR | LUCINA LAND DEVELOPMENT LIMITED | 20/10/2017 |
| CC006000000044300 | Vijay Shetty | M/s Lucina Land Development Limited | 19/12/2018 |
| CC006000000044313 | Dinesh Kumar Nahar | M./s Lucina Land Development Limited | 30/04/2018 |
| CC006000000057332 | Mrs SUSHILA GAUTAM | Indiabulls ( Lucina Land Development Limited ) | 16/12/2018 |
| CC006000000197246 | EDWARD JOHN | MS LUCINA LAND DEVELOPMENT LIMITED | 21/06/2021 |
| CC006000000197687 | Dr. Mrs. Milan Parag Telang | Lucina Land Development Limited | 22/07/2021 |
| CC006000000195953 | Ashwini A. Shinde | Lucia Land Development Ltd. | 09/02/2021 |
| CC006000000196144 | SAHEB RAMASHREY YADAV | M/s. LUCINA LAND DEVELOPMENT LIMITED | 26/02/2021 |
| CC006000000197399 | Rajib Kumar Bachhawat | Lucina Land Development Limited | 24/06/2021 |
| CC006000000354425 | Pratibha Patil | Lucina Land Development Limited | 27/02/2023 |
| CC006000000374768 | Chandramohan Manohar Potdar | Lucina Land Development Limited | 28/03/2023 |
| CC006000000375004 | Subrat Kaushik | Lucina Land Development Limited | 21/04/2023 |
| CC006000000395564 | RATNAKAR SURYAWANSHI Gopalrao Suryawanshi | Lucina Land Development Limited | 07/05/2023 |
| CC006000000397763 | MRS MANISHA SHANKAR CHILAP | LUCINA LAND DEVELOPMENTLTD | 12/10/2023 |
| CC006000000591308 | Venkataramani Ramamurthy | Lucina Land Development Limited | 31/07/2024 |
| CC006000000591331 | Chitra Hari | Lucina Land Developmentt | 26/07/2024 |
| CC006000000591494 | ankushpure | Lucina Land Development Ltd | 10/08/2024 |
| CC12400219 | Joyson Savio Dsilva | Lucina Land Development Limited | 24/09/2024 |
| CC12502068 | Dinesh Ashok More | Lucina Land Development Limited | 24/06/2025 |
| CC12501496 | Cyriac Mathew Mankunnathu | Lucina Land Development Limited | 04/05/2025 |
| CC12502055 | UNNATHAN SHEKHAR | Lucina Land Development Limited | 24/06/2025 |
| CC12503199 | SMITA CHALLU | Lucina Land Development Limited | 10/09/2025 |
| CC12503763 | Tarun NB Singh | Lucina Land Development Limited | 28/10/2025 |
| CC12504297 | Nikita Shrenik Jain | Lucina Land Development Limited | 05/12/2025 |
| SM12600111 | Bhakti Achrekar | Lucina Land Development Limited | 06/02/2026 |
| CC12601276 | Namrata Dayanand Jambhale | Lucina Land Development Limited | 09/03/2026 |
| CC12604809 | Rajendra Pralhad Jagdale | Lucina Land Development Limited | 31/07/2026 |
| CC12605140 | Shubhy Pandey | Lucina Land Development Limited | 12/08/2026 |
| CC12605279 | Rahul Tukaram Mali | Lucina Land Development Limited | 19/08/2026 |
| CC12605276 | Namrata Dayanand Jambhale | Lucina Land Development Limited | 19/08/2026 |
| CC12606012 | Saket Keshav Agarwal | Lucina Land Development Limited | 15/09/2026 |
| CC12605856 | Babu Balakrishnan Parapurath | Lucina Land Development Limited | 08/09/2026 |
| CC12606313 | Lucina Land Development Limited | Amruta Dhanbhadur Chand | 29/09/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Sep 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Sep 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2030
Documents filed198
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 198 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: FORM 5_Indiabulls Park 3_FY 25-26.pdf | 12 Sep 2026 |
| Withdrawal Update Form 1File: LLDL Park 3.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form_2 Park 3.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: LLDL_Indiabulls_Park 3.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form_2 A Park-3 (1).PDF | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Park 3.PDF | 16 Jun 2026 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Park_3.PDF | 16 Jun 2026 |
| Withdrawal Update Form 3File: Indiabulls Park 3_compressed.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Park-3.PDF | 26 Feb 2026 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Park-3.PDF | 26 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 Indiabulls Park 3.pdf | 26 Feb 2026 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Park-3.PDF | 12 Dec 2025 |
| Withdrawal Update Form 2File: Form_2 Indiabuills Park-3.PDF | 12 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Lucina Indiabulls Park 3_compressed.pdf | 12 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 Indiabulls Park 3.pdf | 1 Oct 2025 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Park-3.PDF | 17 Sep 2025 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Park-3_ V1.pdf | 17 Sep 2025 |
| Withdrawal Update Form 3File: Form_3 IP-3.pdf | 17 Sep 2025 |
| Form 2A (FY 2024-2025)File: Quality 2A Certificate Panvel Park 3.pdf | 30 Jun 2025 |
| Form 1File: From_1 Indiabulls Park-3.PDF | 24 Jun 2025 |
| Form 2File: From_2 Indiabulls Park-3.PDF | 24 Jun 2025 |
| Form 3File: From-3 Indiabulls Park-3_Compressed.pdf | 24 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Annexure B- Disclosure of sold Unsold Inventory_Compressed.pdf | 24 Jun 2025 |
| OthersFile: Encumbrance, Asset, Debtor Decl_Merge.pdf | 24 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: Annexure K-Encumbrance Concerned to Finance.PDF | 10 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Panvel Park Phase -3.PDF | 10 Mar 2025 |
| Certificates of CA (Form 3)File: Park 3_Final Form 3-min.pdf | 10 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From_2 Indiabulls Park-3.PDF | 10 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of Sold Unsold.PDF | 10 Mar 2025 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.PDF | 10 Mar 2025 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.PDF | 10 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Annexure K-Encumbrance Concerned to Finance.PDF | 10 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From_5 Indiabulls Park-3.PDF | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ IB Park-3.PDF | 12 Nov 2024 |
| Certificates of CA (Form 3)File: Final_Form 3_Park-3.PDF | 12 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2 Indiabulls Park-3.PDF | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold Unsold.pdf | 12 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Concerned to Finance.pdf | 4 Nov 2024 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf | 4 Nov 2024 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf | 4 Nov 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Concerned to Finance.pdf | 4 Nov 2024 |
| Certificates of CA (Form 3)File: Signed_Form 3_Indiabulls Park 3.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Panvel Park-3.PDF | 23 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Panvel Park-3.PDF | 23 Jul 2024 |
| Certificates of CA (Form 3)File: Indiabulls Panvel Park Phase-3.PDF | 23 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Concerned to Finance.PDF | 20 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Concerned to Finance.PDF | 20 Jul 2024 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.PDF | 20 Jul 2024 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.PDF | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold unsold compressed.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Indiabulls Park-3.PDF | 7 May 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf | 19 Apr 2024 |
| Details of encumbrances concerned to LegalFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Panvel Park Phase-3.PDF | 19 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Indiabulls Panvel Park Phase-3.PDF | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure-B-Disclosure of sold unsold inventory_11zon.pdf | 19 Apr 2024 |
| CERSAI detailsFile: Annexure-G-Asset Based Declaration.pdf | 19 Apr 2024 |
| CERSAI detailsFile: Annexure-L-Debtor Based Declaration.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: Indiabulls Panvel Park Phase-3.PDF | 19 Apr 2024 |
| Declaration in FORM BFile: Form -B Indiabulls park -3.pdf | 10 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Panvel Park Phase-3.pdf | 1 Feb 2024 |
| Certificates of CA (Form 3)File: Indiabulls P-3 form 3_compressed.pdf | 1 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Panvel Park-3.pdf | 30 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 - Panvel Park-3.PDF | 30 Jan 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure-K- Non Encumbrance Concerned of finance.PDF | 21 Jan 2024 |
| Details of encumbrances concerned to LegalFile: Annexure-K- Non Encumbrance Concerned of finance.PDF | 21 Jan 2024 |
| CERSAI detailsFile: Annexure G- Asset Based Declarations.PDF | 21 Jan 2024 |
| CERSAI detailsFile: Annexure- L- Debtor Based Declaration.PDF | 21 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure-B- Disclosure of Sold _ Booked Inventory_11zon.pdf | 21 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revalidation of Amended CC.pdf | 28 Dec 2023 |
| Form 2AFile: Quality Assurance Certificate -Indiabulls Park 3.PDF | 21 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park -3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Park-3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: INDIABULLS PARK 3.PDF | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Panvel Park - 3.PDF | 20 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 198 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Indiabulls Park 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Panvel5,900+ in Raigarh
Filed coordinates, straight-line distance. 37 registered projects within 2 km.
Indiabulls Park 4
Lucina Land Development Limited
Indiabulls Park 1
Lucina Land Development Limited
Indiabulls Park 2
Lucina Land Development Limited
Shikhar Greens
Shikhar Realty
BELANTARA PHASE III
Today Royal Infra
CJ GREENS
C J ESTATES
See every Raigarh project, with the district possession charts
Builder: Lucina Land Development Limited
Lucina Land Development Limited has 9 registrations on MahaRERA, including Indiabulls Park 1 and Indiabulls Park 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Indiabulls Park 3 is delayed beyond 30 Apr 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indiabulls Park 3?
The registered promoter entity is Lucina Land Development Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indiabulls Park 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Indiabulls Park 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Indiabulls Park 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indiabulls Park 3?
The professionals named in the filing: Architect: Rakhi Ubhare; Engineer: Ramesh Rampure; Engineer: Vitthal Shinde; Engineer: Krishna Kumar Bhatnagar; Chartered Accountant: R G V A & Associates; Chartered Accountant: A K O R D & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indiabulls Park 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback