Inamdar Plaza
RG-MH-47545 · RERA P52900048009 · Last updated on MahaRERA portal: 20 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Inamdar Plaza is a Others project by Vijay Shridhar Tawde in Sindhudurg, Maharashtra, registered with MahaRERA as P52900048009 on 7 Dec 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 46 of the 150 units on this registration are recorded sold or booked, and 2 of 33 construction stages are filed complete.
At a glance
Project
- NameInamdar Plaza
- TypeOthers
- Location
- Tarele - Gaganbawada Road
- Vabhave
- Vaibhavvadi
- Sindhudurg
- 416810
- Pincode416810
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52900048009
- ReraGenie IDRG-MH-47545
Builder
- NameVijay Shridhar Tawde
- Entity typeIndividual
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Dec 2022
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2024)
- Buildings3 building records
- Documents filed24 files
Current status
Figures as on 20 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 8 | 8 | 48 | 32 | 80 |
| Building B | NA | 8 | 7 | 42 | 0 | 42 |
| Building C | NA | 8 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 50%.
Building A38%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed91
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 0 | 45 | 45 |
| Building B | 7 | 21 | 28 |
| Building C | 4 | 14 | 18 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Rajendra Vishram Raorane | Kankavali | Sindhudurg |
| Rajashree Rajendra Raorane | Kankavali | Sindhudurg |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A | NA | Rs 8.52 cr | Rs 8.52 cr |
| Building C | NA | Rs 4.96 cr | - |
| Building B | NA | Rs 3.72 cr | - |
| - | NA | Rs 93.75 lakh | - |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vishal Vasant Walke |
| Engineer | Vishal Vasant Walke |
| Chartered Accountant | Sagar Gajanan Teli |
| Partner | Role in project |
|---|---|
| Vijay Shridhar Tawde | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterI am writing with reference to our project “Inamdar Plaza- P52900048009” bearing registration number P52900048009. The project comprises the following buildings: Building A - 80 Units Flats and Shops Building B - 42 Flats Building C - 28 Flats The current status of the project buildings is as follows: Building A OC received 25-Oct-2024 and Submitted on MahaRERA Portal Building B No Bookings in Building - B and Application for De-registration of Project as per Order 42/2023 Submitted Building C No Bookings in Building - C and Application for De-registration of Project as per Order 42/2023 Submi
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Sep 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed24
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Architect Certificate Inamdar.pdf | 20 Nov 2025 |
| Form 2File: Form 2 - Engineer Certificate Inamdar.pdf | 20 Nov 2025 |
| Form 3File: Form 3 - CA Certificate Indamdar.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 20 Nov 2025 |
| Proforma of Agreement for saleFile: Final_Agreement_to_Sale_Mahakali Nov 29.pdf | 29 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement 29112022.pdf | 29 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 18 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment Letter.pdf | 18 Nov 2022 |
| CERSAI detailsFile: CERSAI Declaration New.pdf | 10 Oct 2022 |
| Layout approvalFile: Sanction Plan.pdf | 3 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf | 3 Oct 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 3 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf | 3 Oct 2022 |
| Building plan approvalFile: NA Order.pdf | 12 Sep 2022 |
| PAN CardFile: PAN Card.pdf | 12 Sep 2022 |
| Copy of the legal title reportFile: Search Report.pdf | 12 Sep 2022 |
| Details of encumbrances concerned to FinanceFile: No Encumbrances Declaration.pdf | 12 Sep 2022 |
| Details of encumbrances concerned to LegalFile: No Encumbrances Declaration.pdf | 12 Sep 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf | 12 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 12 Sep 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 12 Sep 2022 |
| Declaration in FORM BFile: Form B Vijay Tawade.pdf | 12 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 12 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 12 Sep 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 24 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Inamdar Plaza on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vabhave530+ in Sindhudurg
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
Shridhar Apartment
Vijay Shridhar Tawde
SAMARTHA HILL
SITARAM KRISHNA ADIVAREKAR
ADITYASAGAR COMPLEX PHASE II
Siddhesh Mahadeo Kanade
Adityasagar Complex
Siddhesh Mahadeo Kanade
MAHAKALI COMPLEX
VIJAY SHRIDHAR TAWADE
MANORAMA TOWNSHIP
Bhawani Heights Development Private Limite
See every Sindhudurg project, with the district possession charts
Builder: Vijay Shridhar Tawde
Vijay Shridhar Tawde has 2 registrations on MahaRERA, including Shridhar Apartment and Inamdar Plaza. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What does it mean that Inamdar Plaza shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Inamdar Plaza is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Inamdar Plaza?
The registered promoter entity is Vijay Shridhar Tawde, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Inamdar Plaza?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Inamdar Plaza?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Inamdar Plaza?
The professionals named in the filing: Architect: Vishal Vasant Walke; Engineer: Vishal Vasant Walke; Chartered Accountant: Sagar Gajanan Teli. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Inamdar Plaza?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.