ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Impulse Residency C Wing

Registered No litigation declared Residential / Group Housing project

Impulse Residency C Wing

By Impulse Buildcon

RG-MH-61035 · RERA PR1260002500581 · Last updated on MahaRERA portal: 27 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Staircases, 95%
8 of 8Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 12 documents Report an error

Impulse Residency C Wing is a Residential / Group Housing project by Impulse Buildcon in Pune, Maharashtra, registered with MahaRERA as PR1260002500581 on 14 Aug 2025. Possession is promised by 6 Jun 2027. 0 of the 8 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameImpulse Residency C Wing
  • TypeResidential / Group Housing
  • Location
    • -
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1260002500581
  • ReraGenie IDRG-MH-61035

Builder

  • NameImpulse Buildcon
  • Entity typePartnership
  • PartnersRajkumar Kashmirilal Agarwal, AMRENDRA MEHTA, AJAY KASHMIRILAL AGARWAL, PANKAJ KUMAR, Vijay Kashmirilal Agarwal
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2025PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2025
  • Promised completion6 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed12 files

Current status

0%0 of 8 units booked
13.0%Work done, per cost certificate

Figures as on 27 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing C NA54808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

Wing C: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNo0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Stilt / Ground26

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,590 sq m
Land owned byNot the promoter
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jul 2025
LandownerVillageDistrict
Rajkumar Kashmirilal Agarwal-Pune
Ajay Kashmirilal Agarwal-Pune
Narayandevi Kashmirilal Agarwal-Pune
Vijay Kashmirilal Agarwal-Pune
Anita Rajesh Agarwal-Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI515.68
Proposed, not sanctioned516 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.1A, GR.FLR, VASCON WEIKFIELD, WEIKFIELD IT CITI INFO PARK, SHRI SATPAL MALHOTRA ROAD, PUNE, MAHARASTRA - 411014
Estimated costRs 1.87 cr
Cost incurredRs 24.28 lakh
Work done12.96%
BuildingWingEstimatedIncurred
Wing CNARs 1.78 crRs 24.28 lakh
-NARs 9.37 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSomnath Kerur and Asoociates
ArchitectPB Associates
EngineerDesign Concept
EngineerSK Consultants & Engineers
Chartered AccountantN B Sayed & Associates
PartnerRole in project
Impulse Buildcon-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 6 Jun 2027

Documents filed12

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 of Impulse Residency C Wing-as on 31-03-26.pdf27 May 2026
Withdrawal Update Form 2File: Form 2 of Impulse Residency C Wing-as on 31-03-26.pdf27 May 2026
Withdrawal Update Form 3File: Form 3 of Impulse Residency C Wing-as on 31-03-26.pdf27 May 2026
Withdrawal Update Form 1File: Form 1 - Impulse Residency as on Dec 2025.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 - Impulse Residency as on Dec 2025.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 - Impulse Residency as on Dec 2025.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 - Impulse Residency C Wing as on Sep 2025.pdf22 Oct 2025
Withdrawal Update Form 2File: Form 2 - Impulse Residency C Wing as on Sep 2025.pdf22 Oct 2025
Withdrawal Update Form 3File: Form 3 - Impulse Residency C Wing as on Sep 2025.pdf22 Oct 2025
Layout approvalFile: Layout plan.pdf21 Jul 2025
Building plan approvalFile: Building Plan Approval.pdf21 Jul 2025
Declaration and undertaking (Annexure A)File: Order No 50 (4).pdf21 Jul 2025

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Impulse Residency C Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmImpulse Residency C WingCompleted 62Lapsed / revoked 24Other 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: Impulse Buildcon

IMPULSE BUILDCON has 2 registrations on MahaRERA, including IMPULSE RESIDENCY and Impulse Residency C Wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Impulse Residency C Wing is delayed beyond 6 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Impulse Residency C Wing?

The registered promoter entity is Impulse Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Impulse Residency C Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Impulse Residency C Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Impulse Residency C Wing?

The professionals named in the filing: Architect: Somnath Kerur and Asoociates; Architect: PB Associates; Engineer: Design Concept; Engineer: SK Consultants & Engineers; Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Impulse Residency C Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Impulse Residency C Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Impulse Residency C Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.