Home / Browse projects / Mumbai Suburban, Maharashtra / ICON BELLE VUE
ICON BELLE VUE
RG-MH-20194 · RERA P51800009393 · Last updated on MahaRERA portal: 28 Sep 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 38 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ICON BELLE VUE is a Others project by ICON DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009393 on 22 Aug 2017. Possession was promised by 30 Aug 2023 and is now 38 months past that date. The completion date has moved by 30 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameICON BELLE VUE
- TypeOthers
- Location
- Ramdas Sutrale Marg
- Chandawarkar Cr Rd 01
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800009393
- ReraGenie IDRG-MH-20194
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion30 Aug 2023
- Revised completionRevised to 30 Aug 2023 (originally 28 Feb 2021)
- Buildings1 building record
- Documents filed35 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| REBAN CHS LTD | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 22%.
REBAN CHS LTD: 52% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 22% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 9% |
| Sanitary Fittings within the flats / premises | 9% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 22% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 9% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities17
As on 28 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Society office | Yes | 0% |
| Amenity Space | Yes | 0% |
Parking filed71
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP SHEKHAR (SAI PROJECT CONSULTANT) |
| Engineer | HIREN TANNA |
| Partner | Role in project |
|---|---|
| ICON DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, I/We the Promoters of the Project Sai Shanti Park Anand registered under project registration number P52000005784 do hereby declare that we had mentioned the revised proposed date of completion of project is 31st December 2019. We would like to inform you that the project is 80% completed. We have total 95 apartments/Shops, out of that 67 apartment/Shops is sold and 28 apartments/Shops are unsold which needs to be sell but without the Extension Number we are unable to sell those inventories. Hence we are making this application for Project Extension we request you give extension for
Reason as filed by the promoterDear Sir, I/We the Promoters of the Project Sai Shanti Park Anand registered under project registration number P52000005784 do hereby declare that we had mentioned the revised proposed date of completion of project is 31st December 2019. We would like to inform you that the project is 80% completed. We have total 95 apartments/Shops, out of that 67 apartment/Shops is sold and 28 apartments/Shops are unsold which needs to be sell but without the Extension Number we are unable to sell those inventories. Hence we are making this application for Project Extension we request you give extension for
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502645 | NILESH V SHAH | ICON DEVELOPERS | 30/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Dec 2021
Documents filed35
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CERSAI detailsFile: CERSAI ICON BELLE VUE.pdf | 28 Sep 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE ICON BELLE VUE.pdf | 8 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Compress Engineer Certificate site supervisor Form 2Afor.pdf | 8 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ICON BELLE VUE.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 or ICON BELLE VUE Rera extension compressed.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 for ICON BELLE VUE Rera extension April 2018 March 2019compressed.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 for ICON BELLE VUE Rera extension April 2019 March 2020 compressed.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 for ICON BELLE VUE Rera extension April 2020 March 2021 compressed.pdf | 8 Apr 2022 |
| Building plan approvalFile: SWATI AMENDED 05 page 02 001.pdf | 29 Dec 2021 |
| Building Plan Approval (IOD)File: SWATI AMENDED 05 page 02 001.pdf | 29 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 04 UP TO 20TH FLOOR.pdf | 29 Dec 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf | 29 Dec 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC GR and First.pdf | 28 Dec 2021 |
| Declaration in FORM BFile: ICON BELLE VUE FORM B Section 3 6.pdf | 10 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ICON BELLE VUE ARCHITECT CERTIFICATE_.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ICON BELLE VUE ENGINEER CERTIFICATE_.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: ICON BELLE VUE CA CERTIFICATE_20170729.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Swati title.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: ICON BELLE VUE AFFIDEVIT FOR RERA B AND W_20170728_142540.pdf | 28 Jul 2017 |
| Building plan approvalFile: Swati IOD 10 08 2016 001.pdf | 27 Jul 2017 |
| Layout approvalFile: NO LAYOUT.pdf | 27 Jul 2017 |
| Building plan approvalFile: ICON BELLE VUE IOD 001.pdf | 27 Jul 2017 |
| Building plan approvalFile: ICON BELLE VUE IOD 002.pdf | 27 Jul 2017 |
| Building plan approvalFile: ICON BELLE VUE IOD 003.pdf | 27 Jul 2017 |
| PAN CardFile: ICON DEVELOPERS PAN CARD.pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: Swati title.pdf | 27 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: NO LAYOUT.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: Swati IOD 10 08 2016 001.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: ICON BELLE VUE IOD 001.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: ICON BELLE VUE IOD 002.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: ICON BELLE VUE IOD 003.pdf | 27 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: ICON BELLE VUE FURTHER CC 06 07 2017 001.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: ICON BELLE VUE SALE DEED sgs.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: ICON BELLE VUE allotment letter.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Draft_Agreement_for_Sale_Real_Estate_Act_2016.pdf | 27 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VIJAY LAKSHMI | Malad - West. | 1 | Completed | Dec 2015 | Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 35 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ICON BELLE VUE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chandawarkar Cr Rd 016,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 57 registered projects within 2 km.
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: ICON DEVELOPERS
ICON DEVELOPERS has 8 registrations on MahaRERA, including J-25 ICON HEIGHTS and ICON BELLE VUE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ICON BELLE VUE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ICON BELLE VUE is delayed beyond 30 Aug 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ICON BELLE VUE?
The registered promoter entity is ICON DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ICON BELLE VUE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ICON BELLE VUE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ICON BELLE VUE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ICON BELLE VUE?
The professionals named in the filing: Architect: SANDEEP SHEKHAR (SAI PROJECT CONSULTANT); Engineer: HIREN TANNA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ICON BELLE VUE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback