Home / Browse projects / Mumbai Suburban, Maharashtra / HUM SUB CHSL
HUM SUB CHSL
RG-MH-21033 · RERA P51800004487 · Last updated on MahaRERA portal: 8 Feb 2019
Source: official MahaRERA filing
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HUM SUB CHSL is a Residential / Group Housing project by SHRADDHARPAN DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004487 on 9 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2019. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameHUM SUB CHSL
- TypeResidential / Group Housing
- Location
- Parmanand Mehta Marg
- Shankar Lane
- Kandivali (West)
- Borivali
- Mumbai Suburban
- 400067
- Pincode400067
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004487
- ReraGenie IDRG-MH-21033
Builder
- NameSHRADDHARPAN DEVELOPERS
- Entity typePartnership
- PartnersSURENDRA D SHAH, Bharat S Rao
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Aug 2017
- Promised completion30 Jun 2019
- Revised completionRevised to 30 Jun 2019 (originally 30 Jun 2018)
- Buildings1 building record
- Documents filed41 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HUM SUB CHSL | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Feb 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
HUM SUB CHSL: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Feb 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed74
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S B Associates |
| Engineer | Nexus Project Solution Private Ltd |
| Partner | Role in project |
|---|---|
| SHRADDHARPAN DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe above project is completed, as it can be seen from the Architects report dated 31-12-2018 that 100 % of the work has been completed, we are also submitting the Architects report for your kind reference. All the compliances for Occupation Certificate are in order and we are in the process for filing the application for Occupation Certificate. We would like to request for extension of due date of our project on the following grounds. - 100% work is completed. - All the compliance for O.C from various authorities is done. - The O.C is currently being processed and will be obtained in due cour
Reason as filed by the promoterThe above project is on the verge of completion, as it can be seen from the Architects report that 90 -95 % of the work has been completed. The cabling and electric metres for each flat from the electricity provider viz. Reliance Energy Ltd. is also done and the power connection will be given soon. The pending work is like electrical fitting in flats, testing of lifts & firefighting devices, fitting, testing of water pumps, installation of car parking (currently under progress) and finishing of lobby work, paving of areas of recreational open space. We estimate that it would not take us more t
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000089776 | Rashmi H Tejani | Messers Shraddharpan Developers | 19/06/2019 |
| CC006000000198038 | Zarna Samin Gorasia | SHRADDHARPAN DEVELOPERS | 21/08/2021 |
| CC12602792 | Kirit Suba | SHRADDHARPAN DEVELOPERS | 13/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed41
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: BANK ACCOUNT CLOSUR INTIMATION.pdf | 8 Feb 2019 |
| Certificates of Architect (Form 4)File: Form 4 for RERA.pdf | 25 Jan 2019 |
| Certificates of Architect (Form 4)File: HUM SUB bldg OC CERTIFICATE.pdf | 24 Jan 2019 |
| Certificates of CA (Form 5)File: Untitled.pdf | 2 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf | 22 Feb 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 22 Feb 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 22 Feb 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 22 Feb 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 22 Feb 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 22 Feb 2018 |
| OtherFile: Encrumbances.pdf | 22 Feb 2018 |
| Layout approvalFile: Self declaration for layout.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Self declaration for layout.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Affidavit FINAL.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: RERA Allotement and AGREEMENT HUMSUB 28 7 17 (1).pdf | 28 Jul 2017 |
| OtherFile: Area clarification letter.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: Encumbrance letter.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate final.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 27 Jul 2017 |
| Building plan approvalFile: IOD 1.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 2.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 3.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 4.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD5.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 6.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 7.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD 8.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: title certificate.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 1.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 2.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 3.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 4.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD5.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 6.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 7.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 8.pdf | 26 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOD.pdf | 25 Jul 2017 |
| PAN CardFile: SD pan card.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 25 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 41 filed documents as one ZIP, foldered, with a manifest
Keep HUM SUB CHSL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shankar Lane, Kandivali (West)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 331 registered projects within 2 km.
Ruparel Optima Ph I
Ruparel Infra & Realty Pvt Ltd
"SALE BLDG NO. 6 (A & B) WING KNOWN AS NORTHER
N.ROSE DEVELOPERS PVT LTD
JP Commerz
Metallica Industries Limited
Ruparel Skygreens I
Shree Siddhivinayak Infrastructure & Realt
ShreejiAikyam
Rushabh Developers
Shiv Vardaan
NAVKARMIK HOMES LLP, URVI CONSTRUCTION
See every Mumbai Suburban project, with the district possession charts
Builder: SHRADDHARPAN DEVELOPERS
SHRADDHARPAN DEVELOPERS has 1 registration on MahaRERA, including HUM SUB CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if HUM SUB CHSL is delayed beyond 30 Jun 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HUM SUB CHSL?
The registered promoter entity is SHRADDHARPAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HUM SUB CHSL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HUM SUB CHSL?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HUM SUB CHSL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HUM SUB CHSL?
The professionals named in the filing: Architect: S B Associates; Engineer: Nexus Project Solution Private Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HUM SUB CHSL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback