Home / Browse projects / Bengaluru Urban, Karnataka / HM Eterno
HM Eterno
By HM Infratech Private Limited
RG-KA-85994 · RERA PRM/KA/RERA/1251/309/PR/171126/009105 · Last updated on RERA Karnataka portal: 6 Nov 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Nothing adverse is on this record. The buyer report still lays out every unit and the land chain as filed and places this filing against the promoter's other registrations.
See what the report covers Free either way: .Saved.
HM Eterno is a Residential/Group Housing project by HM Infratech Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171126/009105 on 17 Nov 2026. Possession is promised by 30 Apr 2028.
At a glance
Project
- NameHM Eterno
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/309/PR/171126/009105
- ReraGenie IDRG-KA-85994
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Nov 2026
- Promised completion30 Apr 2028
- Revised completionNone
- Buildings9 building records
- Documents filed162 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A | - | - | - | 8 | 0 | 8 |
| Block B | - | - | - | 10 | 0 | 10 |
| Block C | - | - | - | 10 | 0 | 10 |
| Block D | - | - | - | 15 | 0 | 15 |
| Block E | - | - | - | 15 | 0 | 15 |
| Block F | - | - | - | 10 | 0 | 10 |
| Block G | - | - | - | 10 | 0 | 10 |
| Block H | - | - | - | 9 | 0 | 9 |
| Block J | - | - | - | 8 | 0 | 8 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 6 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 6 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Smt R Lakshmi Devamma | - | - |
| Mr.Manju M S | - | - |
| Kumari Chinmayi B | - | - |
| Mrs.G Rangalakshmi | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 47.03 cr | - |
| On-site expenditure-Salaries of workers | Rs 2.36 cr | - |
| On-site expenditure-Consultants Fees | Rs 1.03 cr | - |
| Payment of taxes | Rs 28.30 lakh | - |
| Payment of cess | Rs 28.30 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RB Associates |
| Engineer | Syed Adan Khader |
| Chartered Accountant | S. JANARDHAN & ASSOCIATES |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed162
As listed on the registration, under the names the promoter filed them with; the newest 80 of 162 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171126/009105 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Amalgamation Deed_compressed (1).pdf | 6 Nov 2026 |
| title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Gift Deedcompressed.pdf | 6 Nov 2026 |
| There is entry of agreement of sale in EC, pls clarify.File: ToWhomsoeveritmayconcern_Entry of sale agreement in EC_compressed.pdf | 6 Nov 2026 |
| Podi MR from 15/3 to 15/5.File: Phodi_compressed.pdf | 6 Nov 2026 |
| RTCFile: RTC (1).pdf | 6 Nov 2026 |
| MRFile: Screenshot (1284).png | 6 Nov 2026 |
| MRFile: Screenshot (1285).png | 6 Nov 2026 |
| MRFile: Screenshot (1286).png | 6 Nov 2026 |
| MRFile: Screenshot (1287).png | 6 Nov 2026 |
| MRFile: Screenshot (1288).png | 6 Nov 2026 |
| title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Amalgamation Deed_compressed (1).pdf | 3 Nov 2026 |
| title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Gift Deedcompressed.pdf | 3 Nov 2026 |
| There is entry of agreement of sale in EC, pls clarify.File: Entry of agreement of sale in E_compressed.pdf | 3 Nov 2026 |
| Podi MR from 15/3 to 15/5.File: Phodi_compressed.pdf | 3 Nov 2026 |
| title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: To whomsover it may concern_Title deed_IHC order.pdf | 29 Sep 2026 |
| There is entry of agreement of sale in EC, pls clarify.File: To whomsover it may concern_EC Clarification.pdf | 29 Sep 2026 |
| Advocate search report for all present sr nos in the name of owners.File: Advocate_Search Report_all survey nos compress.pdf | 29 Sep 2026 |
| Podi MR from 15/3 to 15/5.File: Podi.pdf | 29 Sep 2026 |
| Gift DeedFile: Gift Deedcompressed.pdf | 29 Sep 2026 |
| title deed of the current landowner as per latest transaction IN SR NO 15/3,File: title deed 15_3.pdf | 8 Sep 2026 |
| title deed of the current landowner as per latest transaction IN SR NO 15/3,File: title deed 15-3.pdf | 8 Sep 2026 |
| title deed of the current landowner as per latest transaction IN SR NO 15/7,File: title deed 15-7.pdf | 8 Sep 2026 |
| Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_3_compressed.pdf | 8 Sep 2026 |
| Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_3_converted_compressed.pdf | 8 Sep 2026 |
| Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_5_compressed.pdf | 8 Sep 2026 |
| Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_6_compressed.pdf | 8 Sep 2026 |
| Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_7_compressed.pdf | 8 Sep 2026 |
| Advocate search report for all present sr nosFile: Advocate Search Report_15_3.pdf | 8 Sep 2026 |
| Advocate search report for all present sr nosFile: Advocate Search Report_15_5.pdf | 8 Sep 2026 |
| Advocate search report for all present sr nosFile: Advocate Search Report_15_6.pdf | 8 Sep 2026 |
| Advocate search report for all present sr nosFile: Advocate Search Report_15_7.pdf | 8 Sep 2026 |
| Podi MR from 15/3 to 15/5.File: Podi MR 15-7.pdf | 8 Sep 2026 |
| Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: Towhomsoever_Single Plot Plan.pdf | 8 Sep 2026 |
| Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: Towhomsoever_Single Plot Plan_Order.pdf | 8 Sep 2026 |
| Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: Master Plan_compressed.pdf | 8 Sep 2026 |
| Demarcation of proposed land in original Village map certified by the competent authority.File: Towhomsoever_Demarcation_Village map.pdf | 8 Sep 2026 |
| Approval/NOC under section 14 or 69 of the KTCP Act from competent AuthorityFile: Towhomsoever_NOC_KTCP_Act.pdf | 8 Sep 2026 |
| Updated built up area is not matching to approved plan,kindly update the same as per actual/as per aFile: Updated .pdf | 8 Sep 2026 |
| Carpet area entered in area details and development details are different,once again informed to kinFile: Updated .pdf | 8 Sep 2026 |
| In the Development Details (Flat Dimension wise break up) subsection of project details page ,flat dFile: Updated .pdf | 8 Sep 2026 |
| Kindly upload project specifications with signatureFile: Specifiations.pdf | 8 Sep 2026 |
| Amalgamation DeedFile: Amalgamation Deed_compressed.pdf | 8 Sep 2026 |
| PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Architect Certificate_compressed.pdf | 19 Aug 2026 |
| PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Chartered Accountant Certificate_compressed.pdf | 19 Aug 2026 |
| PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Engineering Certificate_compressed (1).pdf | 19 Aug 2026 |
| PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: A Block.jpeg | 19 Aug 2026 |
| PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: B Block.jpeg | 19 Aug 2026 |
| Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: Chartered Accountant Certificate_compressed.pdf | 19 Aug 2026 |
| Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Collection account-Pass Book 100_compressed.pdf | 19 Aug 2026 |
| Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Designated account-Pass Book 70_compressed.pdf | 19 Aug 2026 |
| Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Utilisation account-Pass Book 30_compressed.pdf | 19 Aug 2026 |
| Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: Bank Affidavit_compressed.pdf | 19 Aug 2026 |
| Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Collection account-Pass Book 100_compressed.pdf | 19 Aug 2026 |
| Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Designated account-Pass Book 70_compressed.pdf | 19 Aug 2026 |
| Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Utilisation account-Pass Book 30_compressed.pdf | 19 Aug 2026 |
| What are all the sources of funds to complete the project? With supporting documents.File: Sources of Fund_compressed.pdf | 19 Aug 2026 |
| authenticated copy of connected MR showing flow of titles in favour of landowner before conversionFile: Authenticated copy of connected MR showing flow of titles in favour of the landowner befor | 19 Aug 2026 |
| title deed of the current landowner as per latest transaction in all sr nosFile: Title deed of the current landowner as per latest transaction in all Sy Nos 1_compressed.p | 19 Aug 2026 |
| JDA between land owner and promoter in sr no 15/7File: JDA Between Landowner and Promoter_compressed.pdf | 19 Aug 2026 |
| Defect free EC from 1-4-2011 to till dateFile: ECC-03082026-4010061_compressed.pdf | 19 Aug 2026 |
| Advocate search reportFile: Advocate Search Report _compressed.pdf | 19 Aug 2026 |
| Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: Single Plot layout Approved by the competent authority (Original and clearly visible).pdf | 19 Aug 2026 |
| Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: Single Plot layout Approved by the competent authority (Original and clearly visible).pdf | 19 Aug 2026 |
| ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Certified Survey sketch Certifying the Boundary of the Proposed land- Original survey | 19 Aug 2026 |
| Location details of the project , with clear demarcation of land dedicated for the project along witFile: Location_latitude&Longitude_end points_compressed.pdf | 19 Aug 2026 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: Original sanctioned drawings, floor plan, sectional drawings and elevations.pdf | 19 Aug 2026 |
| Area/ No of units of KSPCB noc is not matching with sanction planFile: To Whom so ever it may concern_KSPCB_compressed.pdf | 19 Aug 2026 |
| Demarcation of proposed land in Approved Master plan Certified by the competent authority.File: Demarcation of proposed land in Approved Master plan Certified by the competent authority. | 19 Aug 2026 |
| Latitude and Longitude of the proposed project does not match with the project locationFile: Location_latitude&Longitude_end points_compressed.pdf | 19 Aug 2026 |
| Kindly update the project address as per approved plan.(sy nos)File: Updated .pdf | 19 Aug 2026 |
| Kindly update the total built up area as per approved plan.File: Total Builtup Area as per the approved plan.pdf | 19 Aug 2026 |
| Carpet area entered in area details and development details are different,kindly update the same asFile: Updated carpet area.pdf | 19 Aug 2026 |
| In the Development Details (Flat Dimension wise break up) subsection of project details page ,flat dFile: Development details - updated.pdf | 19 Aug 2026 |
| Updated project schedule is not matching with project start date ,kindly update the same as per theFile: Updated .pdf | 19 Aug 2026 |
| Uploaded engineer licence validity is expired,kindly upload the renewed one.File: Structrual Engineer_Renewed Certificate_compressed.pdf | 19 Aug 2026 |
| Kindly upload the form-6 engineer certificate for ongoing project duly signed by engineer whose haviFile: Form_6_Engineer Certificate_compressed.pdf | 19 Aug 2026 |
| Updated total project cost is not matching to CA.File: Chartered Accountant Certificate_compressed.pdf | 19 Aug 2026 |
| Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: Structural Stability Certificate_compressed.pdf | 19 Aug 2026 |
| Kindly upload project specifications with signatureFile: Specifications_HM Eterno_compressed.pdf | 19 Aug 2026 |
| Updated possession date in allotment letter is already lapsed,kindly update it properlyFile: Booking-cum-Allotment Letter_compressed.pdf | 19 Aug 2026 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| HM Scottsville | BBMP Khatha No.1546/34/2, carved out of Survey No.34/2, situated at Junnasandra Village, Varthur Hobli, Bangalore East Taluk | Ongoing | Jun 2027 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Free monthly report: Bengaluru on RERA Karnataka, month by month. What registered each month, the flat types and carpet areas being built, the taluks and the completion pipeline, from these same filings.
Buyer report
Built from this project's RERA Karnataka filing, in plain language.
- Red flags and clear checks, the possession story and who you are dealing with
- Every unit as filed, tower by tower: carpet area, undivided share of the land and parking, with the sizes placed against the other projects of the taluk
- The land chain survey by survey: conversion order, deed, khata and joint development, in date order
- Joined against the promoter's other registrations on RERA Karnataka, which the register never shows together
- What to check before you book, drawn from this filing
Not included: the filed documents themselves (the report lists which are on file and does not read them) and a project watch.
Keep HM Eterno on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: HM Infratech Private Limited
HM Infratech Private Limited has 2 registrations on RERA Karnataka, including HM Eterno and HM Scottsville. Its filings declare 3 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if HM Eterno is delayed beyond 30 Apr 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of HM Eterno?
The registered promoter entity is HM Infratech Private Limited, a company as per the filing. Its GSTIN 29AACCH0523J1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in HM Eterno?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at HM Eterno?
The professionals named in the filing: Architect: RB Associates; Engineer: Syed Adan Khader; Chartered Accountant: S. JANARDHAN & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HM Eterno?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback