HM Eterno

By HM Infratech Private Limited

RG-KA-85994 · RERA PRM/KA/RERA/1251/309/PR/171126/009105 · Last updated on RERA Karnataka portal: 6 Nov 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared

Nothing adverse is on this record. The buyer report still lays out every unit and the land chain as filed and places this filing against the promoter's other registrations.

See what the report covers Free either way: .
Apr 2028Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 162 documents Report an error

HM Eterno is a Residential/Group Housing project by HM Infratech Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171126/009105 on 17 Nov 2026. Possession is promised by 30 Apr 2028.

At a glance

Project

  • NameHM Eterno
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171126/009105
  • ReraGenie IDRG-KA-85994

Builder

  • NameHM Infratech Private Limited
  • Entity typeCompany
  • GSTIN29AACCH0523J1ZQ
  • Authorized SignatoryMr.HJ Siwani and Mr.MJ Siwani
  • DirectorsMr.HJ Siwani & Mr.MJ Siwani
  • DirectorsMr. HJ Siwani, Mr. MJ Siwani
  • Project HeadYathi Chandra P
  • Other registrations1 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredNov 2026PromisedApr 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Nov 2026
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings9 building records
  • Documents filed162 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---808
Block B---10010
Block C---10010
Block D---15015
Block E---15015
Block F---10010
Block G---10010
Block H---909
Block J---808

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 6 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
Smt R Lakshmi Devamma--
Mr.Manju M S--
Kumari Chinmayi B--
Mrs.G Rangalakshmi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 50.98 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 47.03 cr-
On-site expenditure-Salaries of workersRs 2.36 cr-
On-site expenditure-Consultants FeesRs 1.03 cr-
Payment of taxesRs 28.30 lakh-
Payment of cessRs 28.30 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRB Associates
EngineerSyed Adan Khader
Chartered AccountantS. JANARDHAN & ASSOCIATES

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed162

As listed on the registration, under the names the promoter filed them with; the newest 80 of 162 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171126/009105 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Amalgamation Deed_compressed (1).pdf6 Nov 2026
title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Gift Deedcompressed.pdf6 Nov 2026
There is entry of agreement of sale in EC, pls clarify.File: ToWhomsoeveritmayconcern_Entry of sale agreement in EC_compressed.pdf6 Nov 2026
Podi MR from 15/3 to 15/5.File: Phodi_compressed.pdf6 Nov 2026
RTCFile: RTC (1).pdf6 Nov 2026
MRFile: Screenshot (1284).png6 Nov 2026
MRFile: Screenshot (1285).png6 Nov 2026
MRFile: Screenshot (1286).png6 Nov 2026
MRFile: Screenshot (1287).png6 Nov 2026
MRFile: Screenshot (1288).png6 Nov 2026
title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Amalgamation Deed_compressed (1).pdf3 Nov 2026
title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: Gift Deedcompressed.pdf3 Nov 2026
There is entry of agreement of sale in EC, pls clarify.File: Entry of agreement of sale in E_compressed.pdf3 Nov 2026
Podi MR from 15/3 to 15/5.File: Phodi_compressed.pdf3 Nov 2026
title deed of the current landowner as per latest transaction in sr no 15/3, 15/7.File: To whomsover it may concern_Title deed_IHC order.pdf29 Sep 2026
There is entry of agreement of sale in EC, pls clarify.File: To whomsover it may concern_EC Clarification.pdf29 Sep 2026
Advocate search report for all present sr nos in the name of owners.File: Advocate_Search Report_all survey nos compress.pdf29 Sep 2026
Podi MR from 15/3 to 15/5.File: Podi.pdf29 Sep 2026
Gift DeedFile: Gift Deedcompressed.pdf29 Sep 2026
title deed of the current landowner as per latest transaction IN SR NO 15/3,File: title deed 15_3.pdf8 Sep 2026
title deed of the current landowner as per latest transaction IN SR NO 15/3,File: title deed 15-3.pdf8 Sep 2026
title deed of the current landowner as per latest transaction IN SR NO 15/7,File: title deed 15-7.pdf8 Sep 2026
Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_3_compressed.pdf8 Sep 2026
Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_3_converted_compressed.pdf8 Sep 2026
Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_5_compressed.pdf8 Sep 2026
Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_6_compressed.pdf8 Sep 2026
Defect free EC from 1-4-2011 to till date in all sr nos seperatelyFile: ECC for 15_7_compressed.pdf8 Sep 2026
Advocate search report for all present sr nosFile: Advocate Search Report_15_3.pdf8 Sep 2026
Advocate search report for all present sr nosFile: Advocate Search Report_15_5.pdf8 Sep 2026
Advocate search report for all present sr nosFile: Advocate Search Report_15_6.pdf8 Sep 2026
Advocate search report for all present sr nosFile: Advocate Search Report_15_7.pdf8 Sep 2026
Podi MR from 15/3 to 15/5.File: Podi MR 15-7.pdf8 Sep 2026
Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: Towhomsoever_Single Plot Plan.pdf8 Sep 2026
Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: Towhomsoever_Single Plot Plan_Order.pdf8 Sep 2026
Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: Master Plan_compressed.pdf8 Sep 2026
Demarcation of proposed land in original Village map certified by the competent authority.File: Towhomsoever_Demarcation_Village map.pdf8 Sep 2026
Approval/NOC under section 14 or 69 of the KTCP Act from competent AuthorityFile: Towhomsoever_NOC_KTCP_Act.pdf8 Sep 2026
Updated built up area is not matching to approved plan,kindly update the same as per actual/as per aFile: Updated .pdf8 Sep 2026
Carpet area entered in area details and development details are different,once again informed to kinFile: Updated .pdf8 Sep 2026
In the Development Details (Flat Dimension wise break up) subsection of project details page ,flat dFile: Updated .pdf8 Sep 2026
Kindly upload project specifications with signatureFile: Specifiations.pdf8 Sep 2026
Amalgamation DeedFile: Amalgamation Deed_compressed.pdf8 Sep 2026
PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Architect Certificate_compressed.pdf19 Aug 2026
PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Chartered Accountant Certificate_compressed.pdf19 Aug 2026
PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: HM Scottsville_Engineering Certificate_compressed (1).pdf19 Aug 2026
PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: A Block.jpeg19 Aug 2026
PRM/KA/RERA/1251/310/PR/180516/001711 Upload quarterly report of the previous projectFile: B Block.jpeg19 Aug 2026
Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: Chartered Accountant Certificate_compressed.pdf19 Aug 2026
Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Collection account-Pass Book 100_compressed.pdf19 Aug 2026
Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Designated account-Pass Book 70_compressed.pdf19 Aug 2026
Upload chartered accountant certificate (CA) in prescribed format form -01.M. ( Please upload 3 bankFile: RERA Utilisation account-Pass Book 30_compressed.pdf19 Aug 2026
Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: Bank Affidavit_compressed.pdf19 Aug 2026
Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Collection account-Pass Book 100_compressed.pdf19 Aug 2026
Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Designated account-Pass Book 70_compressed.pdf19 Aug 2026
Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as perFile: RERA Utilisation account-Pass Book 30_compressed.pdf19 Aug 2026
What are all the sources of funds to complete the project? With supporting documents.File: Sources of Fund_compressed.pdf19 Aug 2026
authenticated copy of connected MR showing flow of titles in favour of landowner before conversionFile: Authenticated copy of connected MR showing flow of titles in favour of the landowner befor19 Aug 2026
title deed of the current landowner as per latest transaction in all sr nosFile: Title deed of the current landowner as per latest transaction in all Sy Nos 1_compressed.p19 Aug 2026
JDA between land owner and promoter in sr no 15/7File: JDA Between Landowner and Promoter_compressed.pdf19 Aug 2026
Defect free EC from 1-4-2011 to till dateFile: ECC-03082026-4010061_compressed.pdf19 Aug 2026
Advocate search reportFile: Advocate Search Report _compressed.pdf19 Aug 2026
Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: Single Plot layout Approved by the competent authority (Original and clearly visible).pdf19 Aug 2026
Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: Single Plot layout Approved by the competent authority (Original and clearly visible).pdf19 Aug 2026
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Certified Survey sketch Certifying the Boundary of the Proposed land- Original survey19 Aug 2026
Location details of the project , with clear demarcation of land dedicated for the project along witFile: Location_latitude&Longitude_end points_compressed.pdf19 Aug 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: Original sanctioned drawings, floor plan, sectional drawings and elevations.pdf19 Aug 2026
Area/ No of units of KSPCB noc is not matching with sanction planFile: To Whom so ever it may concern_KSPCB_compressed.pdf19 Aug 2026
Demarcation of proposed land in Approved Master plan Certified by the competent authority.File: Demarcation of proposed land in Approved Master plan Certified by the competent authority.19 Aug 2026
Latitude and Longitude of the proposed project does not match with the project locationFile: Location_latitude&Longitude_end points_compressed.pdf19 Aug 2026
Kindly update the project address as per approved plan.(sy nos)File: Updated .pdf19 Aug 2026
Kindly update the total built up area as per approved plan.File: Total Builtup Area as per the approved plan.pdf19 Aug 2026
Carpet area entered in area details and development details are different,kindly update the same asFile: Updated carpet area.pdf19 Aug 2026
In the Development Details (Flat Dimension wise break up) subsection of project details page ,flat dFile: Development details - updated.pdf19 Aug 2026
Updated project schedule is not matching with project start date ,kindly update the same as per theFile: Updated .pdf19 Aug 2026
Uploaded engineer licence validity is expired,kindly upload the renewed one.File: Structrual Engineer_Renewed Certificate_compressed.pdf19 Aug 2026
Kindly upload the form-6 engineer certificate for ongoing project duly signed by engineer whose haviFile: Form_6_Engineer Certificate_compressed.pdf19 Aug 2026
Updated total project cost is not matching to CA.File: Chartered Accountant Certificate_compressed.pdf19 Aug 2026
Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: Structural Stability Certificate_compressed.pdf19 Aug 2026
Kindly upload project specifications with signatureFile: Specifications_HM Eterno_compressed.pdf19 Aug 2026
Updated possession date in allotment letter is already lapsed,kindly update it properlyFile: Booking-cum-Allotment Letter_compressed.pdf19 Aug 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
HM ScottsvilleBBMP Khatha No.1546/34/2, carved out of Survey No.34/2, situated at Junnasandra Village, Varthur Hobli, Bangalore East TalukOngoingJun 2027Not due yet

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Free monthly report: Bengaluru on RERA Karnataka, month by month. What registered each month, the flat types and carpet areas being built, the taluks and the completion pipeline, from these same filings.

Keep HM Eterno on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: HM Infratech Private Limited

HM Infratech Private Limited has 2 registrations on RERA Karnataka, including HM Eterno and HM Scottsville. Its filings declare 3 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HM Eterno is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HM Eterno?

The registered promoter entity is HM Infratech Private Limited, a company as per the filing. Its GSTIN 29AACCH0523J1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HM Eterno?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HM Eterno?

The professionals named in the filing: Architect: RB Associates; Engineer: Syed Adan Khader; Chartered Accountant: S. JANARDHAN & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HM Eterno?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HM Eterno. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HM Eterno to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.