Registration approved No litigation declared Residential/Group Housing project

LivingTree by Kalyani Developers

By Kalyani Tech Park Private Limited

RG-KA-04304 · RERA PRM/KA/RERA/1251/309/PR/260924/007084 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 4 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Sep 2029Possession promisedno revision filed
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 64%
449 of 2,736Units unsoldnot recorded sold or booked
4Complaints at RERA Karnatakaon this registration
Jump to the 128 documents Report an error

LivingTree by Kalyani Developers is a Residential/Group Housing project by Kalyani Tech Park Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/260924/007084 on 26 Sep 2024. Possession is promised by 15 Sep 2029. 2,287 of the 2,736 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameLivingTree by Kalyani Developers
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560064
  • Pincode560064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/260924/007084
  • ReraGenie IDRG-KA-04304

Builder

  • NameKalyani Tech Park Private Limited
  • Entity typeCompany
  • CINU45202KA2006PTC038320
  • GSTIN29AACCK8194Q4ZF
  • Authorized SignatoryA Mohan Raju
  • DirectorsA Mohan Raju, Mohan Raju
  • Project HeadShiva Reddy

Key dates

this monthRegisteredSep 2024PromisedSep 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Sep 2024
  • Promised completion15 Sep 2029
  • Revised completionNone
  • Buildings6 building records
  • Documents filed128 files

Current status

84%2287 of 2,736 units booked
62.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1---4400440
Building 2---4900490
Building 3---4800480
Building 4---5700570
Building 5---2830283
Building 6---4730473

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 64%.

Building: 40% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure64%
Masonry Construction64%
Plastering inside , outside & Ceiling20%
Joinery: Doors, Windows, Ventilators etc20%
Basic work of Water supply, Sanitary and Electrification8%
Dadoing, Skirting, Flooring, Tiles work (All types)20%
Railing and Grill fixing20%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes30%
Water conservation/rain water harvesting/recharge of ground waterYes30%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes10%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes10%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes51%
LiftsYes51%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area101,171 sq m
Named landowners1
LandownerVillageDistrict
KALYANI TECHPARK PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 775.25 cr
Cost incurredRs 485.80 cr
Spent of the estimate62.66%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 617.53 crRs 324.50 cr
On-site expenditure-Site OverheadRs 85.90 crRs 88.32 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 71.82 crRs 72.97 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB K Muralidhara
EngineerPruthviraja
Chartered AccountantVenkatesh Kamath

Complaints filed with RERA Karnataka4

Case no.ComplainantRespondentFiled
01221/2025-Kalyani Tech Park Private Limited24/09/2025
00714/2026-Kalyani Tech Park Private Limited22/06/2026
00831/2026-Kalyani Tech Park Private Limited17/07/2026
01005/2026-Kalyani Tech Park Private Limited14/08/2026

Documents filed128

As listed on the registration, under the names the promoter filed them with; the newest 80 of 128 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/260924/007084 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Kalyani Q2_Sd.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect ( Oct 26) (1).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Form-6 Q2.pdf15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1_SD.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (June 26).pdf15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Mar 26 sd.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate Form 6.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Signed.pdf20 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5- Architect certificate_sd.pdf20 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate.pdf20 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Jan 2026
Q3 2025-26 KPTCL- BESCOM20 Jan 2026
Q3 2025-26 Fire and Safety20 Jan 2026
Q3 2025-26 Airport Authority of India20 Jan 2026
Bank Affidavit UpdatedFile: Bank Affidavit.pdf19 Sep 2024
SEIAA EC UpdatedFile: Kalyani-EIA.pdf19 Sep 2024
Site PlanFile: 01 KAR R7 - SITE PLAN (2).pdf19 Sep 2024
PlanFile: 02 KAR R7 - 2ND BASEMENT FLOOR PLAN (1).pdf19 Sep 2024
Plan 1File: 03 KAR R7 - 1ST BASEMENT FLOOR PLAN (1).pdf19 Sep 2024
Plan 2File: 04 KAR R7 - CLUB HOUSE 1 (1).pdf19 Sep 2024
Plan 3File: 05 KAR R7 - CLUB HOUSE 2 (3).pdf19 Sep 2024
Plan 4File: 06 KAR R7 - BUILDING 1 - SHEET 1 OF 3-GF FF & TYP FLOOR.pdf19 Sep 2024
Plan 5File: 07 KAR R7 - BUILDING 1 - SHEET 2 OF 3-19TH TER & SECTION.pdf19 Sep 2024
Plan 6File: 08 KAR R7 - BUILDING 1 - SHEET 3 OF 3-ELEVATION.pdf19 Sep 2024
Plan 7File: 09 KAR R7 - BUILDING 2 - SHEET 1 OF 3-GF FF & TYP FLOOR.pdf19 Sep 2024
Plan 8File: 09 KAR R7 - BUILDING 2 - SHEET 1 OF 3-GF FF & TYP FLOOR.pdf19 Sep 2024
Plan 9File: 10 KAR R7 - BUILDING 2 - SHEET 2 OF 3-19TH TER & SECTION.pdf19 Sep 2024
Plan 10File: 11 KAR R7 - BUILDING 2 - SHEET 3 OF 3-ELEVATION.pdf19 Sep 2024
Plan 11File: 12 KAR R7 - BUILDING 3 - SHEET 1 OF 3-GF FF & TYP FLOOR.pdf19 Sep 2024
Plan 12File: 13 KAR R7 - BUILDING 3 - SHEET 2 OF 3-TYP 19TH & TERRACE.pdf19 Sep 2024
Plan 13File: 14 KAR R7 - BUILDING 3 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Plan 14File: 15 KAR R7 - BUILDING 4 - SHEET 1 OF 3-GF FF & 2ND TO 4TH FLOOR.pdf19 Sep 2024
Plan 15File: 16 KAR R7 - BUILDING 4 - SHEET 2 OF 3-19TH TER & SECTION.pdf19 Sep 2024
Plan 16File: 17 KAR R7 - BUILDING 4 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Plan 17File: 18 KAR R7 - BUILDING 5 - SHEET 1 OF 3-GF FF & TYP FLOOR.pdf19 Sep 2024
Plan 18File: 19 KAR R7 - BUILDING 5 - SHEET 2 OF 3-19TH TER & SECTION.pdf19 Sep 2024
Plan 19File: 20 KAR R7 - BUILDING 5 - SHEET 3 OF 3--ELEVATION.pdf19 Sep 2024
Plan 20File: 21 KAR R7 - BUILDING 6 - SHEET 1 OF 2-GF FF TYP & 19TH.pdf19 Sep 2024
Plan 21File: 22 KAR R7 - BUILDING 6 - SHEET 2 OF 2-TER, ELEVATION & SECTION (2).pdf19 Sep 2024
Plan 22File: 23 KAR R7 - BUILDING 7 - SHEET 1 OF 3-GF FF & 2ND TO 4TH.pdf19 Sep 2024
Plan 23File: 24 KAR R7 - BUILDING 7 - SHEET 2 OF 3- TYP 19TH & TER.pdf19 Sep 2024
Plan 24File: 25 KAR R7 - BUILDING 7 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Plan 25File: 26 KAR R7 - BUILDING 8 - SHEET 1 OF 3-GF FF & 2ND TO 4TH.pdf19 Sep 2024
Plan 26File: 27 KAR R7 - BUILDING 8 - SHEET 2 OF 3-TYP 19TH & TER.pdf19 Sep 2024
Plan 27File: 28 KAR R7 - BUILDING 8 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Plan 28File: 29 KAR R7 - BUILDING 9 - SHEET 1 OF 3-GF & FF FLOOR.pdf19 Sep 2024
Plan 29File: 30 KAR R7 - BUILDING 9 - SHEET 2 OF 3-TYP 19TH & TER.pdf19 Sep 2024
Plan 30File: 31 KAR R7 - BUILDING 9 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Plan 31File: 32 KAR R7 - BUILDING 10 - SHEET 1 OF 3-GF & FF FLOOR.pdf19 Sep 2024
Plan 32File: 33 KAR R7 - BUILDING 10 - SHEET 2 OF 3-TYP 19TH & TER.pdf19 Sep 2024
Plan 33File: 34 KAR R7 - BUILDING 10 - SHEET 3 OF 3-ELEVATION & SECTION.pdf19 Sep 2024
Building PlanFile: Building plan permit.pdf19 Sep 2024
Allotment LetterFile: Allotment Letter - Final Upload.pdf19 Sep 2024
STPFile: Kalyani - STP Feasibility Report.pdf19 Sep 2024
STP DrawingFile: KALYANI -MOEF SANCTION DRAWING 01.pdf19 Sep 2024
Section Plan BuildingFile: Building section plan.pdf19 Sep 2024
Building ApprovalFile: Building approval plan.pdf19 Sep 2024
CA COPFile: Kamath Sir Certificate COP.pdf19 Sep 2024
BESCOMFile: BESCOM NOC[1].pdf19 Sep 2024
Sec 3 AffidavitFile: 3(1) Affidavit.PDF19 Sep 2024
Form B UpdatedFile: Form B (2).pdf19 Sep 2024
No Litigation affidavitFile: Non Litigation affidavit.PDF19 Sep 2024
Village MapFile: village map -R7.PDF19 Sep 2024
KSPCBFile: KSPCB.pdf19 Sep 2024
RTC, survey 430,452' 453''454' 455' 456' 457' 458' 459. 463 and 177 (Block No, 8, 9,10,11,12 &13)-
Mutation, survey 430,452' 453''454' 455' 456' 457' 458' 459. 463 and 177 (Block No, 8, 9,10,11,12 &13)-

How this compares with Bengaluru Urban

84%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep LivingTree by Kalyani Developers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmLivingTree by Kalyani DeOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Kalyani Tech Park Private Limited

Kalyani Tech Park Private Limited has 1 registration on RERA Karnataka, including LivingTree by Kalyani Developers. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if LivingTree by Kalyani Developers is delayed beyond 15 Sep 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LivingTree by Kalyani Developers?

The registered promoter entity is Kalyani Tech Park Private Limited, a company as per the filing. Its CIN U45202KA2006PTC038320 and GSTIN 29AACCK8194Q4ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LivingTree by Kalyani Developers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LivingTree by Kalyani Developers?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at LivingTree by Kalyani Developers?

The professionals named in the filing: Architect: B K Muralidhara; Engineer: Pruthviraja; Chartered Accountant: Venkatesh Kamath. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LivingTree by Kalyani Developers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LivingTree by Kalyani Developers. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LivingTree by Kalyani Developers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.