Home / Browse projects / Raigarh, Maharashtra / HIRAYS OLEANDER
HIRAYS OLEANDER
RG-MH-21018 · RERA P52000005407 · Last updated on MahaRERA portal: 31 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 57 months
- 5 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 4 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HIRAYS OLEANDER is a Residential / Group Housing project by JAGANNATH DASHARATH HIRAY in Raigarh, Maharashtra, registered with MahaRERA as P52000005407 on 11 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 57 months from the original filing. 13 of the 44 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameHIRAYS OLEANDER
- TypeResidential / Group Housing
- Location
- SECTOR-23
- NAVI MUMBAI
- Ulawe
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000005407
- ReraGenie IDRG-MH-21018
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed120 files
Current status
Figures as on 31 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HIRAYS OLEANDER | NA | 16 | 13 | 44 | 0 | 44 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
HIRAYS OLEANDER: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed19
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| HIRAYS OLEANDER | NA | Rs 7.55 cr | Rs 7.40 cr |
| - | NA | Rs 48.25 lakh | Rs 24.12 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Hemant Dhavale |
| Engineer | Vilas Agharkar |
| Chartered Accountant | Sachin Dubey |
| Partner | Role in project |
|---|---|
| JAGANNATH DASHARATH HIRAY | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe had applied for the plinth completion certificate on 31/08/2018. We have received the plinth completion certificate on 30/09/2020. The reason behind this delay is there was some issue with regards to the Maveja in CIDCO as CIDCO is the approving authority for all the permissions. Because of which the process was stopped in CIDCO due to this issue. Also, due to COVID Pandemic, there was a significant addition in the delay to obtain the plinth completion certificate. So, we request you to extend the date of completion of this project till December 2024 as there are more challenges with regard
Reason as filed by the promoterDear Team, We want to apply for an extension due to the delay caused because of shortage of labor after the covid lockdown and the strike of material suppliers. 1. The labor resources required for construction are still not available in the real estate field. After the covid pandemic, there has been a good amount of shortage of manpower in the real estate development sector. 2. The procurement of material was not easily available after the Covid pandemic which also severely affected the timeline of the project. The procurement of materials was very difficult as there was a shortage of material
Reason as filed by the promoterDear Maharera Authorities, I hope this email finds you well. We are writing to formally request a nine-month extension for our ongoing construction project Hiray’s Oleander having RERA registration no. P52000005407. The project is in the last stage of construction. The project work is affected because of a shortage of skilled and unskilled labor. Also, we are facing delays in the procurement of the construction materials. The delays in construction material procurement is affecting our supply chain, hindering seamless progress. Even though we are facing issues in labour and material procuremen
Reason as filed by the promoterDear Sir/Madam, I, Mr. Jagannath D. Hiray, writing you regarding the extension for the project Hiray’s Oleander having RERA registration no. P52000005407 and extension application no. EXT52000025653. The project extension is required as the construction is in its final stage. We have already finished RCC works, brickwork and plaster, outer painting works, interior works like gypsum, bathroom and kitchen tiling, plumbing, flooring, fire pump room construction, etc. The only works which are pending are lift installation works, parking tiling works, and ground drainage works which are currently g
Reason as filed by the promoterRespected Sir/Madam, I, Mr Jagannath D. Hiray, Promoter of the project “Hiray’s Oleander”, situated at Plot No. 179, Sector 23, Ulwe, Navi Mumbai, respectfully submit the following reasons for applying again on the MahaRERA portal along with the updated CPM schedule. At present, the project construction is fully completed in all respects, including RCC structure, masonry, plaster, internal finishes, flooring, plumbing, electrical works, lifts installation, compound wall, parking, and all allied development works. The only approval presently pending is the Fire Department NOC from the concerned
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600744 | sandeep hausaram kharkar | JAGANNATH DASHARATH HIRAY | 09/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed120
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architech Form 1 .pdf | 31 Mar 2026 |
| Withdrawal Update Form 2File: Engineer Form 2.pdf | 31 Mar 2026 |
| Withdrawal Update Form 3File: CA Form 3.pdf | 31 Mar 2026 |
| Withdrawal Update Form 1File: Architech Form 1 .pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: Engineer Form 2.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: CA Form 3.pdf | 23 Jan 2026 |
| Form 1File: Architech Certificate.pdf | 25 Dec 2025 |
| Form 2File: Engineer Certificate_compressed.pdf | 25 Dec 2025 |
| Form 3File: CA Certificate_compressed.pdf | 25 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed (1).pdf | 25 Dec 2025 |
| Form 1File: Architect RERA Certificate.pdf | 24 Aug 2025 |
| Form 2File: RCC RERA Certificate.pdf | 24 Aug 2025 |
| Form 3File: RERA form 3 - Hiray Ent 13-8-2025_compressed.pdf | 24 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed.pdf | 24 Aug 2025 |
| Declaration in FORM BFile: Form B Oleander.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 19 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 .pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Details .pdf | 19 Apr 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration About RERA Designated Bank Account.pdf | 19 Apr 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real.pdf | 19 Apr 2025 |
| Declaration in FORM BFile: Form B declaration format (for owned land).pdf | 26 Mar 2025 |
| Other - TechnicalFile: CPM and PERT.pdf | 26 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - From Site Engineer.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect - Form 1.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC - Form 2.pdf | 20 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA - Form 5.pdf | 20 Feb 2025 |
| Declaration in FORM BFile: Form B .pdf | 13 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf | 13 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate .pdf | 13 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC Consultant's Certificate.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Unsold Inventory .pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Engineer's Quality Assurance Certificate20250113_18293118.pdf | 13 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA form 5.pdf | 13 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf | 19 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 - CA certificate 24-6-2024-compressed.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: CA Certificate - RERA form 3-compressed.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 19 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 11 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINNER CERTIFICATE.pdf | 11 May 2024 |
| Certificates of CA (Form 3)File: CA certificare-compressed.pdf | 11 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Hiray Enterprises FY 22-23.pdf | 11 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE Dec 2023.pdf | 31 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec 2023.pdf | 31 Dec 2023 |
| Certificates of CA (Form 3)File: CA Certificate Dec 202320231221_11341621.pdf | 31 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 179-23.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate .pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: CA certificate compressed.pdf | 13 Oct 2023 |
| Declaration in FORM BFile: Form B Hirays Oleander.pdf | 1 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 2019-20.pdf | 1 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21.pdf | 1 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf | 1 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf | 1 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory Details.pdf | 1 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 23 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE compressed.pdf | 23 Mar 2023 |
| Certificates of CA (Form 3)File: CA Certificate_compressed.pdf | 23 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 2017-18.pdf | 23 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf | 23 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf | 23 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf | 23 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Civil Engineer Certificate_compressed.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 29122021.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE_compressed.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf | 22 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 22 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 22 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificate 29122021.pdf | 22 Jan 2023 |
| Certificates of CA (Form 3)File: RERA Form 3 -CA certificate.pdf | 22 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificate_compressed.pdf | 22 Jan 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| HIRAYS NISHIGANDHA | PLOT NO 160 SECTOR 23 ULWE NAVI MUMBAI | 32 | Completed | Jun 2016 | Jun 2016 |
| HIRAYS MOGARA | PLOT NO 136 SECTOR-02 ULWE NAVI MUMBAI | 28 | Completed | Jun 2014 | Jun 2014 |
| HIRAYS ABOLI | PLOT NO 154 SECTOR 02 ULWE NAVI MUMBAI | 39 | Completed | May 2014 | May 2014 |
| HIRAYS PARIJAT | PLOT NO 37 SECTOR 19 ULWE NAVI MUMBAI | 20 | Completed | Jan 2013 | Jan 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 120 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HIRAYS OLEANDER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAVI MUMBAI5,900+ in Raigarh
Filed coordinates, straight-line distance. 127 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: JAGANNATH DASHARATH HIRAY
JAGANNATH DASHARATH HIRAY has 3 registrations on MahaRERA, including HIRAYS ANGELICA and HIRAYS OLEANDER. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that HIRAYS OLEANDER shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if HIRAYS OLEANDER is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HIRAYS OLEANDER?
The registered promoter entity is JAGANNATH DASHARATH HIRAY, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HIRAYS OLEANDER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HIRAYS OLEANDER?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HIRAYS OLEANDER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HIRAYS OLEANDER?
The professionals named in the filing: Architect: Hemant Dhavale; Engineer: Vilas Agharkar; Chartered Accountant: Sachin Dubey. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HIRAYS OLEANDER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback