Home / Browse projects / Raigarh, Maharashtra / HIRAYS OLEANDER

Registration lapsed No litigation declared Residential / Group Housing project

HIRAYS OLEANDER

By JAGANNATH DASHARATH HIRAY

RG-MH-21018 · RERA P52000005407 · Last updated on MahaRERA portal: 31 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 57 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
31 of 44Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

HIRAYS OLEANDER is a Residential / Group Housing project by JAGANNATH DASHARATH HIRAY in Raigarh, Maharashtra, registered with MahaRERA as P52000005407 on 11 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 57 months from the original filing. 13 of the 44 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHIRAYS OLEANDER
  • TypeResidential / Group Housing
  • Location
    • SECTOR-23
    • NAVI MUMBAI
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000005407
  • ReraGenie IDRG-MH-21018

Builder

  • NameJAGANNATH DASHARATH HIRAY
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

7 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed120 files

Current status

30%13 of 44 units booked
95.1%Work done, per cost certificate

Figures as on 31 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HIRAYS OLEANDERNA161344044

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

HIRAYS OLEANDER: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered18
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area998 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCity and Industrial Development Corporation of Maharashtra
Permissible FSI1495.68
Proposed, not sanctioned1,496 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 5 TO 10, SHABI COMPLEX, PLOT NO 110 AND 111, SECTOR-12, VASHI, NAVI MUMBAI
Estimated costRs 8.04 cr
Cost incurredRs 7.64 cr
Work done95.12%
BuildingWingEstimatedIncurred
HIRAYS OLEANDERNARs 7.55 crRs 7.40 cr
-NARs 48.25 lakhRs 24.12 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHemant Dhavale
EngineerVilas Agharkar
Chartered AccountantSachin Dubey
PartnerRole in project
JAGANNATH DASHARATH HIRAY-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000008468Jun 2021 → Dec 2022

Reason as filed by the promoterWe had applied for the plinth completion certificate on 31/08/2018. We have received the plinth completion certificate on 30/09/2020. The reason behind this delay is there was some issue with regards to the Maveja in CIDCO as CIDCO is the approving authority for all the permissions. Because of which the process was stopped in CIDCO due to this issue. Also, due to COVID Pandemic, there was a significant addition in the delay to obtain the plinth completion certificate. So, we request you to extend the date of completion of this project till December 2024 as there are more challenges with regard

EXT52000016751Jun 2021 → Mar 2024

Reason as filed by the promoterDear Team, We want to apply for an extension due to the delay caused because of shortage of labor after the covid lockdown and the strike of material suppliers. 1. The labor resources required for construction are still not available in the real estate field. After the covid pandemic, there has been a good amount of shortage of manpower in the real estate development sector. 2. The procurement of material was not easily available after the Covid pandemic which also severely affected the timeline of the project. The procurement of materials was very difficult as there was a shortage of material

EXT52000019312Jun 2021 → Dec 2024

Reason as filed by the promoterDear Maharera Authorities, I hope this email finds you well. We are writing to formally request a nine-month extension for our ongoing construction project Hiray’s Oleander having RERA registration no. P52000005407. The project is in the last stage of construction. The project work is affected because of a shortage of skilled and unskilled labor. Also, we are facing delays in the procurement of the construction materials. The delays in construction material procurement is affecting our supply chain, hindering seamless progress. Even though we are facing issues in labour and material procuremen

EXT52000025653Jun 2021 → Dec 2025

Reason as filed by the promoterDear Sir/Madam, I, Mr. Jagannath D. Hiray, writing you regarding the extension for the project Hiray’s Oleander having RERA registration no. P52000005407 and extension application no. EXT52000025653. The project extension is required as the construction is in its final stage. We have already finished RCC works, brickwork and plaster, outer painting works, interior works like gypsum, bathroom and kitchen tiling, plumbing, flooring, fire pump room construction, etc. The only works which are pending are lift installation works, parking tiling works, and ground drainage works which are currently g

EA27122519058Jun 2021 → Mar 2026

Reason as filed by the promoterRespected Sir/Madam, I, Mr Jagannath D. Hiray, Promoter of the project “Hiray’s Oleander”, situated at Plot No. 179, Sector 23, Ulwe, Navi Mumbai, respectfully submit the following reasons for applying again on the MahaRERA portal along with the updated CPM schedule. At present, the project construction is fully completed in all respects, including RCC structure, masonry, plaster, internal finishes, flooring, plumbing, electrical works, lifts installation, compound wall, parking, and all allied development works. The only approval presently pending is the Fire Department NOC from the concerned

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600744sandeep hausaram kharkarJAGANNATH DASHARATH HIRAY09/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architech Form 1 .pdf31 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2.pdf31 Mar 2026
Withdrawal Update Form 3File: CA Form 3.pdf31 Mar 2026
Withdrawal Update Form 1File: Architech Form 1 .pdf23 Jan 2026
Withdrawal Update Form 2File: Engineer Form 2.pdf23 Jan 2026
Withdrawal Update Form 3File: CA Form 3.pdf23 Jan 2026
Form 1File: Architech Certificate.pdf25 Dec 2025
Form 2File: Engineer Certificate_compressed.pdf25 Dec 2025
Form 3File: CA Certificate_compressed.pdf25 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed (1).pdf25 Dec 2025
Form 1File: Architect RERA Certificate.pdf24 Aug 2025
Form 2File: RCC RERA Certificate.pdf24 Aug 2025
Form 3File: RERA form 3 - Hiray Ent 13-8-2025_compressed.pdf24 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed.pdf24 Aug 2025
Declaration in FORM BFile: Form B Oleander.pdf19 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf19 Apr 2025
Certificates of CA (Form 3)File: Form 3_compressed.pdf19 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 .pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Details .pdf19 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration About RERA Designated Bank Account.pdf19 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real.pdf19 Apr 2025
Declaration in FORM BFile: Form B declaration format (for owned land).pdf26 Mar 2025
Other - TechnicalFile: CPM and PERT.pdf26 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - From Site Engineer.pdf26 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect - Form 1.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC - Form 2.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA - Form 5.pdf20 Feb 2025
Declaration in FORM BFile: Form B .pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf13 Jan 2025
Certificates of CA (Form 3)File: Form 3 CA Certificate .pdf13 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC Consultant's Certificate.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Unsold Inventory .pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Engineer's Quality Assurance Certificate20250113_18293118.pdf13 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA form 5.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf19 Dec 2024
Certificates of CA (Form 3)File: FORM 3 - CA certificate 24-6-2024-compressed.pdf19 Dec 2024
Certificates of CA (Form 3)File: CA Certificate - RERA form 3-compressed.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf11 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINNER CERTIFICATE.pdf11 May 2024
Certificates of CA (Form 3)File: CA certificare-compressed.pdf11 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Hiray Enterprises FY 22-23.pdf11 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE Dec 2023.pdf31 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec 2023.pdf31 Dec 2023
Certificates of CA (Form 3)File: CA Certificate Dec 202320231221_11341621.pdf31 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 179-23.pdf13 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate .pdf13 Oct 2023
Certificates of CA (Form 3)File: CA certificate compressed.pdf13 Oct 2023
Declaration in FORM BFile: Form B Hirays Oleander.pdf1 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 2019-20.pdf1 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21.pdf1 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf1 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf1 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory Details.pdf1 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE compressed.pdf23 Mar 2023
Certificates of CA (Form 3)File: CA Certificate_compressed.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 2017-18.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf23 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Civil Engineer Certificate_compressed.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 29122021.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE_compressed.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf22 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf22 Jan 2023
Certificates of CA (Form 3)File: CA Certificate.pdf22 Jan 2023
Certificates of CA (Form 3)File: CA Certificate.pdf22 Jan 2023
Certificates of CA (Form 3)File: CA Certificate 29122021.pdf22 Jan 2023
Certificates of CA (Form 3)File: RERA Form 3 -CA certificate.pdf22 Jan 2023
Certificates of CA (Form 3)File: CA Certificate_compressed.pdf22 Jan 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
HIRAYS NISHIGANDHAPLOT NO 160 SECTOR 23 ULWE NAVI MUMBAI32CompletedJun 2016Jun 2016
HIRAYS MOGARAPLOT NO 136 SECTOR-02 ULWE NAVI MUMBAI28CompletedJun 2014Jun 2014
HIRAYS ABOLIPLOT NO 154 SECTOR 02 ULWE NAVI MUMBAI39CompletedMay 2014May 2014
HIRAYS PARIJATPLOT NO 37 SECTOR 19 ULWE NAVI MUMBAI20CompletedJan 2013Jan 2013

How this compares with Raigarh

30%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 57 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HIRAYS OLEANDER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAVI MUMBAI5,900+ in Raigarh

2 kmHIRAYS OLEANDERCompleted 79Lapsed / revoked 19Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: JAGANNATH DASHARATH HIRAY

JAGANNATH DASHARATH HIRAY has 3 registrations on MahaRERA, including HIRAYS ANGELICA and HIRAYS OLEANDER. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that HIRAYS OLEANDER shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HIRAYS OLEANDER is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HIRAYS OLEANDER?

The registered promoter entity is JAGANNATH DASHARATH HIRAY, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HIRAYS OLEANDER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HIRAYS OLEANDER?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HIRAYS OLEANDER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HIRAYS OLEANDER?

The professionals named in the filing: Architect: Hemant Dhavale; Engineer: Vilas Agharkar; Chartered Accountant: Sachin Dubey. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HIRAYS OLEANDER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HIRAYS OLEANDER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HIRAYS OLEANDER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.