Home / Browse projects / Mumbai Suburban, Maharashtra / HIMBINDU

Completed No litigation declared Residential / Group Housing project

HIMBINDU

By Jitendra Shankerlal Brahmbhatt

RG-MH-20109 · RERA P51800003502 · Last updated on MahaRERA portal: 21 Nov 2024

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 41 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2022Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
4Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

HIMBINDU is a Residential / Group Housing project by Jitendra Shankerlal Brahmbhatt in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003502 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 May 2022. The completion date has moved by 41 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameHIMBINDU
  • TypeResidential / Group Housing
  • Location
    • M G Road
    • Goregaon West
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003502
  • ReraGenie IDRG-MH-20109

Builder

  • NameJitendra Shankerlal Brahmbhatt
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toMay 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 May 2022
  • Revised completionRevised to 30 May 2022 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HimbinduNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

Himbindu: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered19
Open Space2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area815 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3858.3
Proposed, not sanctioned2,970 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKohinoor Indl Estate, Goregaon East

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s. B.S.Barot
ArchitectCon Arch India
PartnerRole in project
M/s. Sahajanand Developers-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005249Dec 2018 → May 2020

Reason as filed by the promoterChange in planning authority from MCGM to MHADA, DCPR 2034 and transition policy coming into effect

EXT51800008515Dec 2018 → May 2021

Reason as filed by the promoterDue to Covid-19 and lockdown the work has suffered and also the permissions were delayed because of the lockdown. Also there is a shortage of skilled and unskilled workers because of the pandemic.

EXT51800000903Dec 2018 → May 2020

Reason as filed by the promoterApplied To MHADA For The balance FSI And the same is awaited.

EXT51800009691Dec 2018 → Nov 2021

Reason as filed by the promoterThe promoter is facing my health issues, he is on dialysis from December 2020. He was operated for a block in the artery which carries blood to the brain in February 2021. Further he suffered from COVID 19 in March 2021, because of side effect of COVID 19, he developed gangrene in his right foot and his right leg had to be amputated below the knee. Also because of the COVID 19 pandemic induced various lockdowns, there is a shortage of labourers and materials which is causing delays in project completion.

Litigation declared1

CaseCourtStatus
380/2018High Court at BombayDisposed off

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000001577Himbindu Co-operative Housing SocietyJitendra Shankerlal Brahmbhatt31/10/2017
CC006000000056344Ganesh Ramesh ShanbhagJitendra Shankerlal Brahmbhatt26/09/2018
CC006000000044469Mangesh M TeliJItendra S Brhmabhatt10/05/2018
CC006000000397241Pravin ShahJitendra Shankerlal Brahmabhatt31/08/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Nov 2024

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Himbindu - Architect’s Certificate on Completion of Project (Form 4).pdf21 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Himbindu - Architect’s Certificate on Completion of Project (Form 4).pdf21 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Himbindu OC.pdf12 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Himbindu (Form 2A FY 2019-20) Engineers Certificate on Quality Assurance.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Himbindu (Form 2A FY 2020-21) Engineers Certificate on Quality Assurance.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Himbindu (Form 2A FY 2021-22) Engineers Certificate on Quality Assurance.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Himbindu (Form 2A FY 2022-23) Engineers Certificate on Quality Assurance.pdf21 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Himbindu CC-Full-08-02-2022.pdf15 Sep 2023
Disclosure of sold/ booked inventoryFile: Himbindu - Disclosure of sold booked inventory.pdf15 Sep 2023
Certificates of CA (Form 3)File: Himbindu RERA FORM-3.pdf15 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vivan Developer.pdf9 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Himbindu Engineer Certificate As per Site Progress.pdf9 Aug 2023
Certificates of CA (Form 5)File: Sahajanand Developers Himbindu project.pdf9 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form - 5 - 21-22.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form - 5 - 20-21.pdf11 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Himbindu - Society Registration Certificate.pdf20 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: F Y 2018-19.pdf20 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: F Y 2019-20.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Discolsure of SoldBooked Inventory.pdf25 Jun 2021
Declaration about Commencement CertificateFile: Declaration.pdf24 Jun 2021
Certificates of CA (Form 5)File: Form 5 F Y 2018-19.pdf21 Jun 2021
Certificates of CA (Form 5)File: Form 5 F Y 2019-20.pdf21 Jun 2021
Certificates of CA (Form 5)File: Form - 5.pdf8 Apr 2019
Certificates of CA (Form 5)File: Himbindu Form 5.pdf12 Dec 2018
Certificates of CA (Form 3)File: CA Certification-Vivaant C.pdf20 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vivaant_Engineer_Certificate_Dec17 C.pdf17 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Vivaant C.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vivaant_Engineer Certificate_Registration_Sept17 C.pdf31 Oct 2017
Certificates of CA (Form 3)File: Certification Of RERA Certificate of ''Vivaant''C.pdf31 Oct 2017
Layout approvalFile: IOD.pdf26 Jul 2017
Copy of the legal title reportFile: Title certificate-min.pdf26 Jul 2017
Details of encumbrancesFile: Affidavit cum Declaration Dec 18-min.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD.pdf26 Jul 2017
Declaration in FORM BFile: Affidavit cum Declaration Dec 18-min.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate-min.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vivaant Engineer Certificate min.pdf26 Jul 2017
Certificates of CA (Form 3)File: Vivant Certificate CA-min.pdf26 Jul 2017
Proforma of Allotment letterFile: LOA and Agreement-26-7-17.pdf26 Jul 2017
Building plan approvalFile: IOD.pdf23 Jul 2017
PAN CardFile: 201707231323.pdf23 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AristaP51800003375Goregaon West, Mumbai Suburban314Aug 2017OngoingDec 2025Registered original: Dec 2022Not delivered

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 41 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HIMBINDU on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon West6,700+ in Mumbai Suburban

2 kmHIMBINDUCompleted 144Lapsed / revoked 66Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 361 registered projects within 2 km.

Builder: Jitendra Shankerlal Brahmbhatt

Jitendra Shankerlal Brahmbhatt has 3 registrations on MahaRERA, including HIMBINDU and Athena. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if HIMBINDU is delayed beyond 30 May 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HIMBINDU?

The registered promoter entity is Jitendra Shankerlal Brahmbhatt, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HIMBINDU?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HIMBINDU?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HIMBINDU?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HIMBINDU?

The professionals named in the filing: Architect: M/s. B.S.Barot; Architect: Con Arch India. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HIMBINDU?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HIMBINDU. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HIMBINDU to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.