Registered No litigation declared Residential / Group Housing project

Arista

By Jitendra Shankerlal Brahmbhatt

RG-MH-24934 · RERA P51800003375 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • 43 complaints at MahaRERA
  • Completion date moved by 63 months
  • 2 extensions taken
  • Rs 69.84 crore secured on the land, in favour of SAMMAAN CAPITAL LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 63 months from the original
27 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 73%
152 of 327Units unsoldnot recorded sold or booked
43Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

Arista is a Residential / Group Housing project by Jitendra Shankerlal Brahmbhatt in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003375 on 5 Aug 2017. Possession is promised by 31 Mar 2028. The completion date has moved by 63 months from the original filing. 175 of the 327 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete. 43 complaints are on record with the regulator.

At a glance

Project

  • NameArista
  • TypeResidential / Group Housing
  • Location
    • S.V.Road
    • Goregaon West
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003375
  • ReraGenie IDRG-MH-24934

Builder

  • NameJitendra Shankerlal Brahmbhatt
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Aug 2017
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 30 Dec 2022)
  • Buildings3 building records
  • Documents filed82 files

Current status

54%175 of 327 units booked
55.1%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA271766066
Wing BNA271766066
Wing CNA56291950195

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 73%.

Wing A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure73%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises38%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks72%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed461

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots461
Closed/Covered461
BuildingClosed/CoveredTotal
Wing A5050
Wing B5555
Wing C356356

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area8,659 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofSAMMAAN CAPITAL LIMITED
Secured amountRs 69.84 crore
CERSAI search filedYes
Declared on10 Mar 2026

Approvals and building plan

Sanctioning authorityMaharashtra Housing And Area Development Authority
Permissible FSI40915.85
Proposed, not sanctioned31,448 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 7, Rustomjee Ozone, Laxmi Singh Complex, Goregaon West, Mumbai - 400062
Estimated costRs 205.44 cr
Cost incurredRs 113.26 cr
Work done55.13%
BuildingWingEstimatedIncurred
Wing CNARs 151.12 crRs 68.79 cr
Wing BNARs 24.02 crRs 24.02 cr
Wing ANARs 20.45 crRs 20.45 cr
-NARs 9.85 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCon Arch India
ArchitectM/s B S Barot
EngineerPRASHANT ANANT PATARE
EngineerJW Consultants LLP
Chartered AccountantMALVIKA & ASSOCIATES
PartnerRole in project
M/s. Sahajanand Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017067Dec 2022 → Dec 2025

Reason as filed by the promoterThe main reason for stalling of project was the health of the promoter. He has faced multiple operations and therapy before resuming in office. The allottees of the ongoing project putting forward their various demands in terms of the possession of the Flat.

EA12032620195Dec 2022 → Mar 2028

Reason as filed by the promoterC wing construction upto 29th floor is started as per the revised CC approved on 25th July 2024. The total provision of C wing is 42 floors & it's construction will finish as per approval received from Mhada. due to this we applied extension till 31/03/2028. In the mean time the Proprietor of the firm is demised due to sever illness of last 3 years that is reason of delayed of the construction work.

Complaints filed with MahaRERA43

Case no.ComplainantRespondentFiled
CC006000000194746M/s. Big Imports & GiftJitendra S. Brahmbhatt Proprietor of M/s. Sahajanand Developers19/11/2020
CC006000000171622RAMAKANTI SINGHJITENDRA SHANKERLAL BRAHMBHATT21/11/2019
CC006000000192705T Square Enterprises Pvt LtdJitendra Shankarlal Brahmbhatt Proprietor Sahajanand Developers21/02/2020
CC006000000197079Chaturbhuj GuptaSahajanand Developers29/05/2021
CC006000000197080Rajesh Chaturbhuj GuptaSahajanand Developers29/05/2021
CC006000000197081Vinay Chaturbhuj GuptaSahajanand Developers29/05/2021
CC006000000198659DHS Info System Private LimitedSahajanand Developers12/10/2021
CC006000000333921Sahajanand Arista C Wing Flat Owners AssociationSahajanand Developers10/01/2023
CC006000000195041Mr. Chaturbhuj Gupta, Mr. Rajesh Chaturbhuj Gupta, Mr. Vinay Chaturbhuj GuptaMr. Jitendra Shankerlal Bramabhatt27/11/2020
CC006000000195268Raul Anthony Peireira & Romulus Jude PeireiraSahjanand Developers Corp Pvt Ltd- Jitendra Shankerlal Brahmbhatt & Viranchi Jitendra Brahmbhatt19/12/2020
CC006000000198121AVNEET KAILASH MAHESHWARISahajanand Developers28/08/2021
CC006000000198787Sonal Dharmesh Shah And Radha Dhiral ShahMr. Jitendra Brahmbhatt Prop: Sahajanand Developers25/10/2021
CC006000000199122PRANIT ASHOK NARVEKARM/s Sahajanand Developers06/12/2021
CC006000000199137Salil HasabnisViranchi Brahmabhatt27/12/2021
CC006000000262085Ali Akbar Shroff ShroffSahajanand Developers26/07/2022
CC006000000303565Parimal ShethM/s Sahajanand Developers20/12/2022
CC006000000303672VARSHA SURANAM/S SAHAJANAND DEVELOPERS02/01/2023
CC006000000334111Pradeep Singh Ajitsingh ValliaSahajanand Developers26/01/2023
CC006000000395950Abhijit NarvekarSahajanand Developers through its Proprietor Mr Jitendra Brahmbhatt26/05/2023
CC006000000396941Pralhad Ganapati Desai and Asmita Pralhad DesaiJitendra Shankar Brahmbhatt Proprietor Sahajanand Developers02/08/2023
CC006000000397193Tilak raj Sohanlal SahniJitendra Shankerlal Brahmbhatt21/08/2023
CC006000000397269Denver Paul BarrettoSahajanand Developers28/08/2023
CC006000000397698Aashiesh SharmaM/s. Sahajanand Developers through its sole proprietor Mr. Jitendra Shankertal Brambhatt03/10/2023
CC006000000397700Aashiesh SharmaM/s. Sahajanand Developers through its sole proprietor Mr. Jitendra Shankertal Brambhatt03/10/2023
CC006000000429527Shashinand NagoriSahajanand Developers through Sole Proprietor Jitendra Brahmbhatt04/03/2024
CC006000000439638Santosh Singh ChauhanSahajanand Developers15/03/2024
CC006000000580879Kirtikumar Ishwarbhai MasuriaJitendra Shankarlal Brahmbhatt Proprietor M/s Sahajanand Developers22/06/2024
CC006000000580881Ismail Kasamali Bhimani and Gulshan Ismail BhimaniJitendra Shankarlal Brahmbhatt Proprietor Sahajanand Developers22/06/2024
CC006000000580913ASHA PRAVIN AGARWALSahajanand Developers25/06/2024
CC12400904Samit Bhaskar ShettyJitendra Shankerlal Brahmbhatt27/11/2024
CC12503765Yusuf Habibullah KhanJitendra Shankerlal Brahmbhatt28/10/2025
CC12600251Shivalingam Yama NadarJitendra Shankerlal Brahmbhatt14/01/2026
CC12600083Amit Digambar MeshramJitendra Shankerlal Brahmbhatt05/01/2026
CC12600789Arikkat Thomas AbrahamJitendra Shankerlal Brahmbhatt11/02/2026
CC12600818Piyush S ShahJitendra Shankerlal Brahmbhatt13/02/2026
CC12600995Denver Paul BarrettoJitendra Shankerlal Brahmbhatt23/02/2026
CC12601946chandrakant Ramanlal ShahJitendra Shankerlal Brahmbhatt02/04/2026
CC12603613ARISHT NATHMAL JAINM/s. Sahajanand Developers11/06/2026
CC12604226Manisha Sanjay MehtaM/s. Sahajanand Developers06/07/2026
CC12604227Hinesh Rameshchandra DoshiM/s. Sahajanand Developers06/07/2026
CC12604429Rajesh Anilkumar ShahM/s. Sahajanand Developers16/07/2026
CC12604754Jafarulla Ali ParkarM/s. Sahajanand Developers28/07/2026
CC12605171Altaf Nissar MadraswallaM/s. Sahajanand Developers13/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arista Form1.pdf5 May 2026
Withdrawal Update Form 2File: Form 2 (1).pdf5 May 2026
Withdrawal Update Form 3File: Sahajanand Developers Rera Certificate - Form 3.pdf5 May 2026
Withdrawal Update Form 1File: form 1 ar.pdf24 Mar 2026
Withdrawal Update Form 2File: Form 2 ar.pdf24 Mar 2026
Withdrawal Update Form 3File: Arista Form 3 .pdf24 Mar 2026
Form 2A (FY 2023-2024)File: h.pdf24 Mar 2026
Withdrawal Update Form 1File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf12 Mar 2026
Withdrawal Update Form 1File: form 1 m.pdf12 Mar 2026
Withdrawal Update Form 1File: Arista Form 1_Architect Certificate.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 as on 30-09-2025 (1).pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 as on 31-12-2025.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 as on 31-12-2025.pdf12 Mar 2026
Withdrawal Update Form 3File: Arista Form 3.pdf12 Mar 2026
Withdrawal Update Form 3File: Arista Form - 3 (1).pdf12 Mar 2026
Withdrawal Update Form 3File: Arista Form - 3 (1).pdf12 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A as on 30-09-2025.pdf11 Mar 2026
Form 1File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (2).pdf10 Mar 2026
Form 2File: 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1).pdf10 Mar 2026
Form 3File: 5 Certificates of CA (Form 3) (1).pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory (1).pdf10 Mar 2026
Withdrawal Update Form 1File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf10 Mar 2026
Withdrawal Update Form 1File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2 Sept 25.pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2 Sept 25.pdf10 Mar 2026
Withdrawal Update Form 3File: Arista Form 3.pdf10 Mar 2026
Withdrawal Update Form 3File: Arista Form 3.pdf10 Mar 2026
Form 5 (FY 2024-2025)File: Arista Form-5.pdf10 Mar 2026
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf10 Mar 2026
Certificates of CA (Form 3)File: Arista Certificates of CA (Form 3)- 31-03-2025.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arista - Certificates of Architect (Form 1) - 19-11-2024.pdf22 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arista - Certificates of Engineer (Form 2) - 2024_compressed.pdf22 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Arista - Engineers Certificate on Quality Assurance- 2024_compressed.pdf22 Nov 2024
Certificates of CA (Form 3)File: Arista - Certificates of CA (Form 3).pdf19 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Arista FCC 25-07-24.pdf30 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Arista March 2020.pdf24 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARISTA _2021.pdf24 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ARISTA _2022.pdf24 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ARISTA _2023.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: Arista - Disclosure of sold booked inventory.pdf24 Aug 2023
Declaration about Commencement CertificateFile: Format D - Circular 32 - Arista.pdf22 Aug 2023
Declaration in FORM BFile: Arista Form B.pdf22 Aug 2023
Declaration in FORM BFile: Arista Form - B.pdf22 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARISTA.pdf9 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARISTA 30-6-2023.pdf9 Aug 2023
Certificates of CA (Form 3)File: Sahajanand Developers Arista project.pdf9 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report on statement of account 21-22 arista.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: From 5-18-19.pdf11 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: From 5-19-20.pdf11 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: From 5-20-21.pdf11 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Arista - Society Registration Certificate.pdf20 Jun 2022
Building plan approvalFile: Arista IOD 25-05-2022.pdf1 Jun 2022
Building Plan Approval (IOD)File: Arista IOD 25-05-2022.pdf1 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Arista CC 061119.pdf8 Nov 2019
Building plan approvalFile: Arista IOD.pdf22 Oct 2019
Building Plan Approval (IOD)File: Arista IOD.pdf22 Oct 2019
Certificates of CA (Form 5)File: Form - 5.pdf8 Apr 2019
Certificates of CA (Form 3)File: CA Certificate-Arista C.pdf20 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arista_Engineer_Certificate_Dec17 C.pdf17 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Arista C.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arista_Engineer Certificate_Registration_Sept17 C.pdf31 Oct 2017
Certificates of CA (Form 3)File: Certification Of RERA Certificate of ''Arista'' C.pdf31 Oct 2017
Layout approvalFile: Layout Arista.pdf28 Jul 2017
Building plan approvalFile: A and B Wing.pdf28 Jul 2017
Building plan approvalFile: C Wing 1-10.pdf28 Jul 2017
Building plan approvalFile: C Wing 11.pdf28 Jul 2017
Building plan approvalFile: IOD Arista.pdf28 Jul 2017
PAN CardFile: Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate Arista C.pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance Arista.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Arista.pdf28 Jul 2017
Building Plan Approval (IOD)File: A and B Wing.pdf28 Jul 2017
Building Plan Approval (IOD)File: C Wing 1-10.pdf28 Jul 2017
Building Plan Approval (IOD)File: C Wing 11.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Arista.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Jul 2017
Declaration in FORM BFile: Form B Arista C.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Arista-C.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arista_Engineer Certificate C.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA certificate Arista C.pdf28 Jul 2017

How this compares with Mumbai Suburban

54%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 63 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Arista on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon West6,700+ in Mumbai Suburban

2 kmAristaCompleted 143Lapsed / revoked 83Abeyance 1Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 379 registered projects within 2 km.

Builder: Jitendra Shankerlal Brahmbhatt

Jitendra Shankerlal Brahmbhatt has 3 registrations on MahaRERA, including HIMBINDU and Athena. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Arista is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Arista?

The registered promoter entity is Jitendra Shankerlal Brahmbhatt, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Arista?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Arista?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Arista?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Arista?

The professionals named in the filing: Architect: Con Arch India; Architect: M/s B S Barot; Engineer: PRASHANT ANANT PATARE; Engineer: JW Consultants LLP; Chartered Accountant: MALVIKA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Arista?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Arista. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Arista to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.