hillcrest appartments
RG-MH-84236 · RERA P51700012086 · Last updated on MahaRERA portal: 3 Aug 2017
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 34 complaints at MahaRERA
- Completion date moved by 105 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
hillcrest appartments is a Residential / Group Housing project by aasanghar construction in Thane, Maharashtra, registered with MahaRERA as P51700012086 on 1 Sep 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 105 months from the original filing. 34 complaints are on record with the regulator.
At a glance
Project
- Namehillcrest appartments
- TypeResidential / Group Housing
- Location
- Titwala
- Kalyan
- Thane
- 421605
- Pincode421605
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700012086
- ReraGenie IDRG-MH-84236
Builder
- Nameaasanghar construction
- Entity typePartnership
- Partnerssantosh kashinath tare, sandeep daryasingh patil, vasant ramchandra jadhav
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Sep 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 18 Mar 2018)
- Buildings2 building records
- Documents filed14 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| hillcrest appartments A | NA | 8 | 0 | 0 | 0 | 0 |
| hillcrest appartments B | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 3 Aug 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 80%.
hillcrest appartments A66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
hillcrest appartments B66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 3 Aug 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | Yes | 0% |
Parking filed17
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| hillcrest appartments A | 0 | 4 | 4 |
| hillcrest appartments B | 1 | 12 | 13 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | rajeev taishete |
| Engineer | Darshan kasture |
| Partner | Role in project |
|---|---|
| aasanghar construction | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRespected sir We are a partnership firm registered with RERA on 3rd aug17. (REA51700019651). Request you that if you go through our submitted documents you will notice that we are already a loss making firm. As we are located in the out skirts of mumbai the rate per square foot is very low. We had taken 80% booking on pre launching at Rs1800psqf(carpet) in 2011and the construction cost was Rs 950/psqft. There after our project file was put up for necessary sanctions to the authorities, you can notice that the time gap between IOD(20/07/12) & CC(27/11/13 and 17/09/14) is very big because of "NA
Reason as filed by the promoterDue to lockdown financial condition has gone very weak.customers also are unable to help. flats had been sold at very cheap rates. Few flats are remaining for sale
Complaints filed with MahaRERA34
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000055993 | SANDEEP D DHUMAL | SANDEEP D DHUMAL | 29/08/2018 |
| CC006000000078552 | SANDEEP DHUMAL | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000055994 | JAGDISH KISAN LONE | jagdish kisan lone | 29/08/2018 |
| CC006000000078554 | JAGDISH LONE | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000055997 | ARJUN EKNATH SHINGARE | ARJUN EKNATH SHINGARE | 29/08/2018 |
| CC006000000078546 | ARJUN SHINGARE | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000056003 | SHUBHANGI NITIN SAIDANE | shubhangi nitin saidane | 29/08/2018 |
| CC006000000078513 | SHUBHANGI NITIN SAIDANE | ASANGHAR CONSTRUCTION | 20/03/2019 |
| CC006000000056001 | BALU SUKHA DAMSE | BALU SUKHA DAMSE | 30/08/2018 |
| CC006000000078548 | BALU DAMSE | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000056006 | Sandeep Dnyaneshwar Dhumal | DASHARATH NAGU BAGIT | 30/08/2018 |
| CC006000000078555 | DASHRATH BAGIT | AASAN GHAR CONSTRUCTIONS | 21/03/2019 |
| CC006000000056007 | GANESH LIMBAJI | GANESH PUNJAJI GAIKWAD | 29/08/2018 |
| CC006000000078547 | GANESH GAIKWAD | AASAN GHAR CONTRUCTIONS | 20/03/2019 |
| CC006000000056008 | BAJIRAO PUNJAJI BORDE | BAJIRAO PUNJAJI BORDE | 29/08/2018 |
| CC006000000078558 | BAJIRAO BORDE | AASAN GHAR CONSTRATION | 20/03/2019 |
| CC006000000056010 | RAKESH PURUSHOTTAMBHAI PATEL | RAKESH PURUSHOTTAMBHAI PATEL | 30/08/2018 |
| CC006000000078519 | RAKESH PURUSHOTTAMBHAI PATEL | ASANGHAR CONSTRUCTION | 20/03/2019 |
| CC006000000056009 | MAHESH LAXMAN KOR | MAHESH LAXMAN KOR | 29/08/2018 |
| CC006000000078550 | MAHESH KOR | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000078516 | MANISH PAWAR | AASAN GHAR CONSTRUCTION | 21/03/2019 |
| CC006000000078518 | VISHWANATH JADHAV | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000078514 | ANIL BHADEKAR | AASAN GHAR CONSTRUCTIONS | 21/03/2019 |
| CC006000000078521 | ABHIJIT MOHITE | AASAN GHAR CONSTRUCTIONS | 21/03/2019 |
| CC006000000078520 | AMIT DANAIT | aasan ghar construction | 20/03/2019 |
| CC006000000078522 | VIBHA DANAIT | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000078523 | RATNAPRABHANAGRALE | AASAN GHAR CONTRUCTIONS | 20/03/2019 |
| CC006000000078527 | PRALHAD MAHADIK | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000078528 | CHETAN PATL | AASAN GHAR CONSTRUCTIONS | 21/03/2019 |
| CC006000000078560 | PRASHANT GUJAR | AASAN GHAR CONSTRUCTIONS | 20/03/2019 |
| CC006000000078562 | SANDEEP GHODE | AASAN GHAR CONSTRUCTION | 21/03/2019 |
| CC006000000078564 | PRAMOD GAWDE | AASAN GHAR CONSTRUCTIONS | 21/03/2019 |
| CC006000000078563 | SACHIN TUKARAM JADHAV | ASANGHAR CONSTRUCTION | 21/03/2019 |
| CC006000000078622 | ASHOKKUMAR PANDEY | AASAN GHAR CONTRUCTIONS | 28/03/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed14
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: iod.pdf | 3 Aug 2017 |
| Layout approvalFile: layout.pdf | 3 Aug 2017 |
| PAN CardFile: DOC.pdf | 3 Aug 2017 |
| Copy of the legal title reportFile: DOC000.pdf | 3 Aug 2017 |
| Details of encumbrancesFile: formbb.pdf | 3 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 3 Aug 2017 |
| Building Plan Approval (IOD)File: iod.pdf | 3 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: DOC001.pdf | 3 Aug 2017 |
| Declaration in FORM BFile: formbb.pdf | 3 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS_FORM.pdf | 3 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: kast eng.pdf | 3 Aug 2017 |
| Certificates of CA (Form 3)File: ca.pdf | 3 Aug 2017 |
| Proforma of Allotment letterFile: ag3.pdf | 3 Aug 2017 |
| Proforma of Allotment letterFile: ag9.pdf | 3 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 14 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep hillcrest appartments on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Titwala7,600+ in Thane
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
KALAS DARSHAN
JAY GANESH DEVELOPERS
Charms Padamavati Royal Phase 2
Charms Developers
SILVER LINE PHASE - 1
HOME CONSULTANCY
Padamavati Royal Phase 2
Sujeet Kumar Singh
Charms Padamavati Royal Phase 1
Charms Developers
RUSTTAGI AARAMBHA PHASE-III
RUSTAGI ESTATES PRIVATE LIMITED
See every Thane project, with the district possession charts
Builder: aasanghar construction
aasanghar construction has 1 registration on MahaRERA, including hillcrest appartments. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if hillcrest appartments is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of hillcrest appartments?
The registered promoter entity is aasanghar construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in hillcrest appartments?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against hillcrest appartments?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for hillcrest appartments?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at hillcrest appartments?
The professionals named in the filing: Architect: rajeev taishete; Engineer: Darshan kasture. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in hillcrest appartments?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback