Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
HIGH CREST APARTMENTS is a Residential/Group Housing project by PROPERTY INFRA TECH INDIA PVT. LTD. in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/190219/002409 on 19 Feb 2019. Possession is promised by 15 May 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameHIGH CREST APARTMENTS
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/190219/002409
- ReraGenie IDRG-KA-77336
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Feb 2019
- Promised completion15 May 2022
- Revised completionRevised to 15 May 2022 (originally 15 Aug 2021)
- Buildings1 building record
- Documents filed49 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HIGH CREST APARTMENT | - | - | - | 41 | 0 | 41 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR. SURESH KUMAR |
| Engineer | MR. K. ANIL HEGDE |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed49
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/190219/002409 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: 2Certificate of Inc PIPL.PDF | - |
| 11BUILDING LICENCE(COMMENCEMENT) | - |
| 12APPROVED BUILDING PLAN | - |
| 13APPROVED LAYOUT PLAN (SINGLE SITE) | - |
| 22PROFORMA FOR SALE DEED | - |
| 21PROFORMA OF AGREENENT FOR SALE | - |
| 15SALE DEED | - |
| 28APPROVED SECTION OF BLDG | - |
| 14AREA DEVELOPMENT PLAN | - |
| 23PROFORMA OF ALLOTMENT LETTER | - |
| 24BROCHURE OF CURRENT PROJECT | - |
| 25PROJECT SPECIFICATION | - |
| 18ENCUMBRANCE CERTIFICATE | - |
| CA Certi & Affidavit | - |
| 17KHATA | - |
| 16JOINT DEVELOPMENT AGMT | - |
| 19CONVERSION ORDER | - |
| 30RELINQUISHMENT DEED | - |
| 27FIRE NOC-compressed | - |
| 13APPROVED LAYOUT PLAN (SINGLE SITE) | - |
| 28APPROVED SECTION OF BLDG | - |
| 19CONVERSION ORDER | - |
| 29Advocate Search Report | - |
| Balance Sheet 2017 - 2018File: 5BalancaeSheet16-17.PDF | - |
| Balance Sheet 2016 - 2017File: 5Balance Sheet 15-16.PDF | - |
| Balance Sheet 2015 - 2016File: 5BalanceSheet14-15.PDF | - |
| Audited Profit and Loss Statement 2017 - 2018File: 6P&LAccount 16-17.PDF | - |
| Audited Profit and Loss Statement 2016 - 2017File: 6P&LAccount 15-16.PDF | - |
| Audited Profit and Loss Statement 2015 - 2016File: 6P&LAccount 14-15.PDF | - |
| Director's Report 2017 - 2018File: 8Directors report 16-17.pdf | - |
| Director's Report 2016 - 2017File: 8Directors report 15-16.pdf | - |
| Director's Report 2015 - 2016File: 8Directors report 14-15.pdf | - |
| Cash Flow Statement 2017 - 2018File: 7Cashflow 16-17.PDF | - |
| Cash Flow Statement 2016 - 2017File: 7Cashflow 15-16.PDF | - |
| Auditor's Report 2017 - 2018File: 9Auditors Report 16-17.PDF | - |
| Auditor's Report 2016 - 2017File: 9Auditors Report 15-16.PDF | - |
| Auditor's Report 2015 - 2016File: 9Auditors Report 14-15.PDF | - |
| Income Tax Return Acknowledgement 2017 - 2018File: 10IT Acknowledgement 16-17.PDF | - |
| Income Tax Return Acknowledgement 2016 - 2017File: 10IT Acknowledgement 15-16.PDF | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 10IT Acknowledgement 14-15.PDF | - |
| 26DECLARATION IN FORM B | - |
| Prospectus/BrochureFile: High Crest Brochure.pdf | - |
| Advertisement Copy 1File: High Crest Paper Ad.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_190219_002409.xlsx | - |
| Occupancy CertificateFile: High Crest - Completion letter.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: architect -completion.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: ca certificate-completion 4cc.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: affidavit.pdf | - |
| engineer certificateFile: engineer-completion.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep HIGH CREST APARTMENTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 115 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: PROPERTY INFRA TECH INDIA PVT. LTD.
PROPERTY INFRA TECH INDIA PVT LTD has 3 registrations on RERA Karnataka, including CITY SQUARE and HIGH CREST APARTMENTS. Its filings declare 12 earlier projects, 12 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if HIGH CREST APARTMENTS is delayed beyond 15 May 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of HIGH CREST APARTMENTS?
The registered promoter entity is PROPERTY INFRA TECH INDIA PVT. LTD., a company as per the filing. Its CIN U45400KA2010PTC052992 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in HIGH CREST APARTMENTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at HIGH CREST APARTMENTS?
The professionals named in the filing: Architect: MR. SURESH KUMAR; Engineer: MR. K. ANIL HEGDE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HIGH CREST APARTMENTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback