ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Haware My First Home Shil Phata Phase 2 Bldg 2

Registered No litigation declared Others project

Haware My First Home Shil Phata Phase 2 Bldg 2

By Haware Properties LLP

RG-MH-06971 · RERA P51700053915 · Last updated on MahaRERA portal: 19 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 9 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Stilt Floor, 85%
5 of 516Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Haware My First Home Shil Phata Phase 2 Bldg 2 is a Others project by Haware Properties LLP in Thane, Maharashtra, registered with MahaRERA as P51700053915 on 11 Dec 2023. Possession is promised by 31 Dec 2030. 511 of the 516 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameHaware My First Home Shil Phata Phase 2 Bldg 2
  • TypeOthers
  • Location
    • Plot no 86/3
    • 87/1A
    • 87/2A
    • 87/2B and 89/1 Shil Village
    • On Shil Phata Junction
    • Shil Phata Thane
    • Thane (M Corp.)
    • Thane
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700053915
  • ReraGenie IDRG-MH-06971

Builder

  • NameHaware Properties LLP
  • Entity typePartnership
  • LLPINAAJ-9305
  • GSTIN27AAKFH5456M1ZS
  • LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • PartnerAmit Suresh Haware
  • Other registrations9 more →

Key dates

this monthRegisteredDec 2023PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Dec 2023
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed75 files

Current status

99%511 of 516 units booked
29.0%Work done, per cost certificate

Figures as on 19 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 2 - also called Tower 4NA21215160516

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 85%.

Building 2 - also called Tower 4: 49% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor85%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,790 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Patel Wood Works and Timber MartNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI44403.01
Proposed, not sanctioned12,403 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 1 Shree Ganesh CHS Sec 1 Vashi Navi Mumbai 400705
Estimated costRs 36.66 cr
Cost incurredRs 10.62 cr
Work done28.98%
BuildingWingEstimatedIncurred
Building 2 - also called Tower 4NARs 35.19 crRs 10.62 cr
-NARs 1.47 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaakaar Architects
ArchitectPB Associates
EngineerParas Consultants
EngineerSK Consultants & Engineers
Chartered AccountantSharat Jain
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
Haware Properties LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Nov 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Haware My First Home Shil Phata Phase 2 Bldg 2 (1).pdf19 Apr 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 31-03-2026.pdf19 Apr 2026
Withdrawal Update Form 3File: Form 3 SP2 B2 as on 31st Mar 2026.pdf19 Apr 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025-Signed.pdf24 Feb 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025-Signed.pdf24 Feb 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025 - Signed.pdf24 Feb 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025- Signed.pdf24 Feb 2026
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf24 Feb 2026
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025 - Signed.pdf24 Feb 2026
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025 - Signed.pdf24 Feb 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Dec 2025.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on Sep 2025 (revised).pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on June 2025.pdf18 Dec 2025
Withdrawal Update Form 2File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on June 2025.pdf18 Dec 2025
Withdrawal Update Form 3File: Form 3 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on June 2025.pdf18 Dec 2025
Layout approvalFile: Layout.pdf18 Nov 2025
Building plan approvalFile: Building Plan.pdf18 Nov 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Shilphata Phase 2 Bldg 2 Form 2A (2023-24) Signed.pdf20 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032024.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062024.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092024.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122024.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032025.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122023.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 As on 30-09-2024.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 31-03-2025.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 As on 31-12-2024.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 As on 30-06-2024.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 As on 31-03-2024.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shil Phata Ph2 Bldg 2 As on 31-12-2023.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on dec 2023.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on march 2024.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on june 2024.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on sep 2024.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on dec 2024.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Haware My First Home Shil Phata Phase 2 Bldg 2 as on March 2025.pdf4 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Shil Phata P2 B2 31-03-2024.pdf4 May 2025
Other - TechnicalFile: MYSCAN_20230818_0004_compressed (2).pdf30 Nov 2023
Other - TechnicalFile: MYSCAN_20230818_0009_compressed.pdf30 Nov 2023
Declaration about Commencement CertificateFile: Form D - DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf23 Nov 2023
Layout approvalFile: Phase 2 Bldg 1 Layout_compressed (1).pdf18 Nov 2023
Building plan approvalFile: DEVELOPMENT CERTIFICATE.pdf18 Nov 2023
Building plan approvalFile: MYSCAN_20230818_0002_compressed.pdf18 Nov 2023
Building plan approvalFile: MYSCAN_20230818_0003_compressed (1).pdf18 Nov 2023
Building plan approvalFile: MYSCAN_20230818_0007_compressed.pdf18 Nov 2023
PAN CardFile: Haware Properties LLP Pan Card_compressed.pdf18 Nov 2023
Copy of the legal title reportFile: Legal Title Report Phase 2 Sep 2023_compressed.pdf18 Nov 2023
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Encumbrances FInancial - MY FIRST HOME SHIL PHATA PHASE 1 BLDG 18 Nov 2023
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Encumbrances - MY FIRST HOME SHIL PHATA PHASE 1 BLDG 2.pdf18 Nov 2023
Details of encumbrances concerned to LegalFile: Self Declaration Regarding Encumbrances FInancial - MY FIRST HOME SHIL PHATA PHASE 1 BLDG 18 Nov 2023
Details of encumbrances concerned to LegalFile: Self Declaration Regarding Encumbrances - MY FIRST HOME SHIL PHATA PHASE 1 BLDG 2.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: Phase 2 Bldg 1 Layout_compressed (1).pdf18 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: DEVELOPMENT CERTIFICATE.pdf18 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20230818_0002_compressed.pdf18 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20230818_0003_compressed (1).pdf18 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20230818_0007_compressed.pdf18 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: DEVELOPMENT CERTIFICATE.pdf18 Nov 2023
Declaration in FORM BFile: FORM B - Haware Properties LLP - MY FIRST HOME SHIL PHATA PHASE 2 BLDG 2.pdf18 Nov 2023
CERSAI detailsFile: DECLARATION ABOUT CERSAI.pdf18 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MY FIRST HOME SHIL PHATA PHASE 2 BLDG 2-23Nov23_compressed.pdf18 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf18 Nov 2023
Proforma of Agreement for saleFile: HAWARE MY FIRST HOME SHIL PHATA PHASE 2 Bldg 2 AGREEMENT FOR SALE Draft.pdf18 Nov 2023
Proforma of Allotment letterFile: PROFORMA ALLOTMENT LETTER.pdf18 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf18 Nov 2023
Deviation Report with respect to Allotment letterFile: Deviation Report for Model Allotment Letter.pdf18 Nov 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report for Model Agreement.pdf18 Nov 2023

How this compares with Thane

99%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Haware My First Home Shil Phata Phase 2 Bldg on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shil Phata Thane7,600+ in Thane

2 kmHaware My First Home ShiCompleted 34Lapsed / revoked 16Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: Haware Properties LLP

Haware Properties LLP has 10 registrations on MahaRERA, including Haware My First Home Shil Phata Phase 1 Bldg 1 and Haware My First Home Shil Phata Phase 1 Bldg 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Haware My First Home Shil Phata Phase 2 Bldg 2 is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Haware My First Home Shil Phata Phase 2 Bldg 2?

The registered promoter entity is Haware Properties LLP, a partnership as per the filing. Its LLPIN AAJ-9305 and GSTIN 27AAKFH5456M1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Haware My First Home Shil Phata Phase 2 Bldg 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Haware My First Home Shil Phata Phase 2 Bldg 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Haware My First Home Shil Phata Phase 2 Bldg 2?

The professionals named in the filing: Architect: Saakaar Architects; Architect: PB Associates; Engineer: Paras Consultants; Engineer: SK Consultants & Engineers; Chartered Accountant: Sharat Jain; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Haware My First Home Shil Phata Phase 2 Bldg 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Haware My First Home Shil Phata Phase 2 Bldg 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Haware My First Home Shil Phata Phase 2 Bldg to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.