HAWARE LEELA HOMES
RG-MH-84956 · RERA P51700046165 · Last updated on MahaRERA portal: 26 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 35 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HAWARE LEELA HOMES is a Residential / Group Housing project by Pravin Kashinath Haware in Thane, Maharashtra, registered with MahaRERA as P51700046165 on 20 Jun 2022. Possession is promised by 31 Dec 2028. The completion date has moved by 35 months from the original filing.
At a glance
Project
- NameHAWARE LEELA HOMES
- TypeResidential / Group Housing
- Location
- INDRA NAGAR GHOT SAI ROAD
- NR. GREATER VALLEY INTERNATIONAL SCHOOL
- Ghotsai
- Kalyan
- Thane
- 421605
- Pincode421605
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700046165
- ReraGenie IDRG-MH-84956
Builder
- NamePravin Kashinath Haware
- Entity typeIndividual
- GSTIN27AARPH3639K1Z7
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Jun 2022
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 31 Jan 2026)
- Buildings30 building records
- Documents filed72 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 8 | 0 | 0 | 0 | 0 |
| B Wing | NA | 9 | 0 | 0 | 0 | 0 |
| C Wing | NA | 9 | 0 | 0 | 0 | 0 |
| D Wing | NA | 9 | 0 | 0 | 0 | 0 |
| E Wing | NA | 9 | 0 | 0 | 0 | 0 |
| F Wing | NA | 9 | 0 | 0 | 0 | 0 |
| G Wing | NA | 9 | 0 | 0 | 0 | 0 |
| H Wing | NA | 9 | 0 | 0 | 0 | 0 |
| I Wing | NA | 9 | 0 | 0 | 0 | 0 |
| J Wing | NA | 9 | 0 | 0 | 0 | 0 |
| K Wing | NA | 9 | 0 | 0 | 0 | 0 |
| L Wing | NA | 9 | 0 | 0 | 0 | 0 |
| M Wing | NA | 9 | 0 | 0 | 0 | 0 |
| N Wing | NA | 9 | 0 | 0 | 0 | 0 |
| O Wing | NA | 9 | 0 | 0 | 0 | 0 |
| P Wing | NA | 9 | 0 | 0 | 0 | 0 |
| Q Wing | NA | 9 | 0 | 0 | 0 | 0 |
| R Wing | NA | 9 | 0 | 0 | 0 | 0 |
| S Wing | NA | 8 | 0 | 0 | 0 | 0 |
| T Wing | NA | 8 | 0 | 0 | 0 | 0 |
| U wing | NA | 8 | 0 | 0 | 0 | 0 |
| V Wing | NA | 8 | 0 | 0 | 0 | 0 |
| W Wing | NA | 8 | 0 | 0 | 0 | 0 |
| X Wing | NA | 8 | 0 | 0 | 0 | 0 |
| Y wing | NA | 8 | 0 | 0 | 0 | 0 |
| Z Wing | NA | 8 | 0 | 0 | 0 | 0 |
| AA | NA | 8 | 0 | 0 | 0 | 0 |
| BB Wing | NA | 8 | 0 | 0 | 0 | 0 |
| CC Wing | NA | 8 | 0 | 0 | 0 | 0 |
| DD Wing | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 26 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 30 buildings; the table lists the first 20.
0 of 330 construction stages are filed complete across 30 buildings. The stage furthest along is Excavation, at 0%.
A Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
F Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
G Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
H Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
I Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
J Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
K Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
M Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
N Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
O Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
P Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Q Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
R Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed17
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B Wing | 1 | 1 |
| C Wing | 1 | 1 |
| D Wing | 1 | 1 |
| E Wing | 1 | 1 |
| F Wing | 1 | 1 |
| G Wing | 1 | 1 |
| H Wing | 1 | 1 |
| I Wing | 1 | 1 |
| J Wing | 1 | 1 |
| K Wing | 1 | 1 |
| L Wing | 1 | 1 |
| M Wing | 1 | 1 |
| N Wing | 1 | 1 |
| O Wing | 1 | 1 |
| P Wing | 1 | 1 |
| Q Wing | 1 | 1 |
| R Wing | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| HAWARE LEELA HOMES | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Pravin Kashinath Haware | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterI was planning to expand the project but there was delay in receiving sanction plan from the authority. This Setback has postpone our project timeline as we need the official approval to proceed with expansion
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed72
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31-03-2025 Signed.pdf | 26 May 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Rera Format A.pdf | 26 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 23 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold Booked Invertory.pdf | 23 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 30-09-2024_compressed.pdf | 13 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 31-12-2024_compressed.pdf | 13 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 30-09-2024_compressed.pdf | 13 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 31-12-2024_compressed.pdf | 13 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-2025_compressed.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory.pdf | 13 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 1 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-03-06-24.pdf | 1 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-03-09-24.pdf | 1 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-31-12-24.pdf | 1 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-31-03-25.pdf | 1 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Letter.pdf | 1 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Letter.pdf | 1 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Letter.pdf | 1 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A2023.pdf | 1 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A2024.pdf | 1 May 2025 |
| Declaration in FORM BFile: Form B.pdf | 15 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf | 15 Mar 2025 |
| Declaration about Commencement CertificateFile: Format D Commencement Certificate.pdf | 15 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: AnnexureA.pdf | 15 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 15 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Real Estate.pdf | 15 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-03-23.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-12-22.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-09-22.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-06-23.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-09-23.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-12-23.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-03-24.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Dec 2022_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Mar 2023_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware June 2023_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 30 Sep 2023_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Dec 2023_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 31 Mar 2024_11zon.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 30 June 2024_11zon.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Haware form 5_ 2022-23.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate12.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf | 30 Jul 2024 |
| Details of encumbrancesFile: No Encumbrance Certificatee.pdf | 10 Jan 2022 |
| Declaration in FORM BFile: Affidavit Cum Declaration (1)_compressed.pdf | 10 Jan 2022 |
| Declaration about Commencement CertificateFile: MAHARERA Headquarters - Format-D Titwala.pdf | 28 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226786510_For_Asset_Based_Search_28_12_2021_17_14_19_343.pdf | 28 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificatee.pdf | 28 Dec 2021 |
| Declaration in FORM BFile: Affidavit Cum Declaration 1.pdf | 22 Dec 2021 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 20 Dec 2021 |
| Copy of the legal title reportFile: Titwala Legal title report 1.pdf | 17 Dec 2021 |
| Building plan approvalFile: 1 (2)-compressed.pdf | 9 Nov 2021 |
| Layout approvalFile: 1 (2)-compressed.pdf | 9 Nov 2021 |
| Copy of Layout Approval (in case of layout)File: 1 (2)-compressed.pdf | 9 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 (2)-compressed.pdf | 9 Nov 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: RERA - MHAHA TIWALA-1_compressed (1).pdf | 9 Nov 2021 |
| Proforma of Allotment letterFile: Allotment Letter_Haware_Titwala-converted.pdf | 9 Nov 2021 |
| PAN CardFile: IMG_20191217_0005.pdf | 3 Nov 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 72 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep HAWARE LEELA HOMES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NR. GREATER VALLEY INTERNATIONAL SCHOOL7,600+ in Thane
Filed coordinates, straight-line distance. 95 registered projects within 2 km.
KALAS DARSHAN
JAY GANESH DEVELOPERS
Charms Padamavati Royal Phase 2
Charms Developers
SILVER LINE PHASE - 1
HOME CONSULTANCY
Padamavati Royal Phase 2
Sujeet Kumar Singh
Charms Padamavati Royal Phase 1
Charms Developers
RUSTTAGI AARAMBHA PHASE-III
RUSTAGI ESTATES PRIVATE LIMITED
See every Thane project, with the district possession charts
Builder: Pravin Kashinath Haware
Pravin Kashinath Haware has 2 registrations on MahaRERA, including Leelaangan and HAWARE LEELA HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if HAWARE LEELA HOMES is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HAWARE LEELA HOMES?
The registered promoter entity is Pravin Kashinath Haware, an individual as per the filing. Its GSTIN 27AARPH3639K1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HAWARE LEELA HOMES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HAWARE LEELA HOMES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in HAWARE LEELA HOMES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback