Home / Browse projects / Thane, Maharashtra / HAWARE LEELA HOMES

Registered No litigation declared Residential / Group Housing project

HAWARE LEELA HOMES

By Pravin Kashinath Haware

RG-MH-84956 · RERA P51700046165 · Last updated on MahaRERA portal: 26 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 35 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 35 months from the original
0 of 330Construction stages doneacross 30 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

HAWARE LEELA HOMES is a Residential / Group Housing project by Pravin Kashinath Haware in Thane, Maharashtra, registered with MahaRERA as P51700046165 on 20 Jun 2022. Possession is promised by 31 Dec 2028. The completion date has moved by 35 months from the original filing.

At a glance

Project

  • NameHAWARE LEELA HOMES
  • TypeResidential / Group Housing
  • Location
    • INDRA NAGAR GHOT SAI ROAD
    • NR. GREATER VALLEY INTERNATIONAL SCHOOL
    • Ghotsai
    • Kalyan
    • Thane
    • 421605
  • Pincode421605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700046165
  • ReraGenie IDRG-MH-84956

Builder

  • NamePravin Kashinath Haware
  • Entity typeIndividual
  • GSTIN27AARPH3639K1Z7
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJun 2022First promiseJan 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Jan 2026)
  • Buildings30 building records
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA80000
B WingNA90000
C WingNA90000
D WingNA90000
E WingNA90000
F WingNA90000
G WingNA90000
H WingNA90000
I WingNA90000
J WingNA90000
K WingNA90000
L WingNA90000
M WingNA90000
N WingNA90000
O WingNA90000
P WingNA90000
Q WingNA90000
R WingNA90000
S WingNA80000
T WingNA80000
U wingNA80000
V WingNA80000
W WingNA80000
X WingNA80000
Y wingNA80000
Z WingNA80000
AANA80000
BB WingNA80000
CC WingNA80000
DD WingNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 26 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 30 buildings; the table lists the first 20.

0 of 330 construction stages are filed complete across 30 buildings. The stage furthest along is Excavation, at 0%.

A Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
F Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
J Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
K Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
L Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
M Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
N Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
O Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
P Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Q Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
S Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
T Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17
BuildingClosed/CoveredTotal
B Wing11
C Wing11
D Wing11
E Wing11
F Wing11
G Wing11
H Wing11
I Wing11
J Wing11
K Wing11
L Wing11
M Wing11
N Wing11
O Wing11
P Wing11
Q Wing11
R Wing11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area35,385 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
HAWARE LEELA HOMESNavi Mumbai (M Corp.)Thane

Approvals and building plan

Permissible FSI50399.0
Proposed, not sanctioned50,399 sq m
Buildings approved30
Buildings sanctioned30

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Pravin Kashinath Haware-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024770Jan 2026 → Dec 2028

Reason as filed by the promoterI was planning to expand the project but there was delay in receiving sanction plan from the authority. This Setback has postpone our project timeline as we need the official approval to proceed with expansion

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31-03-2025 Signed.pdf26 May 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Rera Format A.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf23 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold Booked Invertory.pdf23 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 30-09-2024_compressed.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 31-12-2024_compressed.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 30-09-2024_compressed.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 31-12-2024_compressed.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-2025_compressed.pdf13 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-03-06-24.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-03-09-24.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-31-12-24.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Home-31-03-25.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Letter.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Letter.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Letter.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A2023.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A2024.pdf1 May 2025
Declaration in FORM BFile: Form B.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf15 Mar 2025
Declaration about Commencement CertificateFile: Format D Commencement Certificate.pdf15 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: AnnexureA.pdf15 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf15 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Real Estate.pdf15 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-03-23.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-12-22.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-09-22.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-06-23.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -30-09-23.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-12-23.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Haware Leela Homes -31-03-24.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Dec 2022_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Mar 2023_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware June 2023_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 30 Sep 2023_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware Dec 2023_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 31 Mar 2024_11zon.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 Haware 30 June 2024_11zon.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Haware form 5_ 2022-23.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate12.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Date.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineers certificate.pdf30 Jul 2024
Details of encumbrancesFile: No Encumbrance Certificatee.pdf10 Jan 2022
Declaration in FORM BFile: Affidavit Cum Declaration (1)_compressed.pdf10 Jan 2022
Declaration about Commencement CertificateFile: MAHARERA Headquarters - Format-D Titwala.pdf28 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report_200226786510_For_Asset_Based_Search_28_12_2021_17_14_19_343.pdf28 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificatee.pdf28 Dec 2021
Declaration in FORM BFile: Affidavit Cum Declaration 1.pdf22 Dec 2021
Details of encumbrancesFile: Encumbrance Certificate.pdf20 Dec 2021
Copy of the legal title reportFile: Titwala Legal title report 1.pdf17 Dec 2021
Building plan approvalFile: 1 (2)-compressed.pdf9 Nov 2021
Layout approvalFile: 1 (2)-compressed.pdf9 Nov 2021
Copy of Layout Approval (in case of layout)File: 1 (2)-compressed.pdf9 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: 1 (2)-compressed.pdf9 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: RERA - MHAHA TIWALA-1_compressed (1).pdf9 Nov 2021
Proforma of Allotment letterFile: Allotment Letter_Haware_Titwala-converted.pdf9 Nov 2021
PAN CardFile: IMG_20191217_0005.pdf3 Nov 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 35 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HAWARE LEELA HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NR. GREATER VALLEY INTERNATIONAL SCHOOL7,600+ in Thane

2 kmHAWARE LEELA HOMESCompleted 37Lapsed / revoked 25Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 95 registered projects within 2 km.

Builder: Pravin Kashinath Haware

Pravin Kashinath Haware has 2 registrations on MahaRERA, including Leelaangan and HAWARE LEELA HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if HAWARE LEELA HOMES is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAWARE LEELA HOMES?

The registered promoter entity is Pravin Kashinath Haware, an individual as per the filing. Its GSTIN 27AARPH3639K1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAWARE LEELA HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAWARE LEELA HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in HAWARE LEELA HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAWARE LEELA HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAWARE LEELA HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.