Home / Browse projects / Sangli, Maharashtra / HARIKRUPA APARTMENT
HARIKRUPA APARTMENT
By DEEPAK VASANTRAO SURYAWANSHI
RG-MH-08982 · RERA P53100000961 · Last updated on MahaRERA portal: 10 Apr 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 5 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HARIKRUPA APARTMENT is a Residential / Group Housing project by DEEPAK VASANTRAO SURYAWANSHI in Sangli, Maharashtra, registered with MahaRERA as P53100000961 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 May 2018.
At a glance
Project
- NameHARIKRUPA APARTMENT
- TypeResidential / Group Housing
- Location
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100000961
- ReraGenie IDRG-MH-08982
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on25 Jul 2017
- Promised completion30 May 2018
- Revised completionNone
- Buildings1 building record
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HARIKRUPA APARTMENT | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
HARIKRUPA APARTMENT: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 10 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMBARNATH SHINDE |
| Partner | Role in project |
|---|---|
| DEEPAK VASANTRAO SURYAWANSHI | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 8 Apr 2023
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of ConveyanceFile: PC declaration deed.pdf | 10 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLITION.pdf | 8 Apr 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: form 4 harikrupa.pdf | 8 Apr 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: harikrupa form 4.pdf | 15 Jul 2022 |
| Status of ConveyanceFile: status of conveynce.pdf | 15 Jul 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: harikrupa form 4.pdf | 4 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20-21.pdf | 21 Aug 2021 |
| Status of ConveyanceFile: ghaisas index.pdf | 21 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A ( Quality Assurance) Harikrupa (1).pdf | 7 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A ( Quality Assurance) Harikrupa (1).pdf | 7 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Harikrupa 19-20.pdf | 7 Aug 2021 |
| Declaration about Commencement CertificateFile: declaration harikrupa.pdf | 6 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: sold unsold harikripa.pdf | 6 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 harikrupa 18-19.pdf | 3 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: revise completion certificate.pdf | 3 Aug 2021 |
| Certificates of CA (Form 5)File: form 5 harikrupa.pdf | 10 Apr 2019 |
| OtherFile: COMPLETION CERTIFICATE.pdf | 29 May 2018 |
| Status of Formation of Legal EntityFile: harikrupa decleration.pdf | 10 Mar 2018 |
| Status of ConveyanceFile: harikrupa decleration.pdf | 10 Mar 2018 |
| Details of encumbrancesFile: Deepak_Certificate (1).pdf | 21 Jul 2017 |
| Proforma of Allotment letterFile: gadgil pdf agrement.pdf | 21 Jul 2017 |
| Proforma of Allotment letterFile: allotment.pdf | 21 Jul 2017 |
| Declaration in FORM BFile: declaration in form b (2).pdf | 14 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATES OF ENGINEER (FORM 2).pdf | 14 Jul 2017 |
| Certificates of CA (Form 3)File: CERTIFICATES OF CA (FORM 3).pdf | 14 Jul 2017 |
| Layout approvalFile: cts map.pdf | 13 Jul 2017 |
| PAN CardFile: Pan card.pdf | 13 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: cts map.pdf | 13 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: certificates of architect (form 1).pdf | 13 Jul 2017 |
| Building plan approvalFile: Copy of Building approval.PDF | 9 Jul 2017 |
| Copy of the legal title reportFile: Copy of legal title report.pdf | 9 Jul 2017 |
| Building Plan Approval (IOD)File: Copy of Building approval.PDF | 9 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: commencment certificates.pdf | 9 Jul 2017 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHRIPAD SAHANIWAS | SANGLI MAHARASHTRA 416416 | 11 | Completed | Nov 2016 | Jun 2016 |
| VASANT RAM | KHANBHAG SANGLI MAHARASHTRA | 10 | Completed | Jun 2016 | Feb 2016 |
| Shivsangam | Haripur road Sangli | 18 | Completed | Jun 2016 | Mar 2016 |
| Vasant Palavi | Abhay nagar Sangli | 21 | Completed | Feb 2016 | Dec 2015 |
| RADHEY SAHANIWAS | KHANBHAG SANGLI | 33 | Completed | Aug 2015 | Mar 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
Keep HARIKRUPA APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sangli Miraj Kupwad (M Corp.)790+ in Sangli
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: DEEPAK VASANTRAO SURYAWANSHI
DEEPAK VASANTRAO SURYAWANSHI has 7 registrations on MahaRERA, including HARIKRUPA APARTMENT and SINDHURWARNA. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What are my rights if HARIKRUPA APARTMENT is delayed beyond 30 May 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HARIKRUPA APARTMENT?
The registered promoter entity is DEEPAK VASANTRAO SURYAWANSHI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HARIKRUPA APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HARIKRUPA APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HARIKRUPA APARTMENT?
The professionals named in the filing: Architect: AMBARNATH SHINDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HARIKRUPA APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback