Home / Browse projects / Nagpur, Maharashtra / HARIHAR NAGAR ZARI PHASE - I

Registered No litigation declared Residential / Group Housing project

HARIHAR NAGAR ZARI PHASE - I

By HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED

RG-MH-00567 · RERA P50500000975 · Last updated on MahaRERA portal: 18 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 143 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Sep 2033Possession promisedmoved 143 months from the original
44 of 1771Construction stages doneacross 161 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 271 documents Report an error

HARIHAR NAGAR ZARI PHASE - I is a Residential / Group Housing project by HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500000975 on 25 Jul 2017. Possession is promised by 2 Sep 2033. The completion date has moved by 143 months from the original filing.

At a glance

Project

  • NameHARIHAR NAGAR ZARI PHASE - I
  • TypeResidential / Group Housing
  • Location
    • Zari
    • Nagpur (rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500000975
  • ReraGenie IDRG-MH-00567

Builder

  • NameHARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED
  • Entity typeCompany
  • CINU45400MH2007PLC176371
  • Managing DirectorsMANISH ARVIND BADIYANI, AMIT ARVIND BADIYANI
  • ChairpersonARVIND HARIDAS BADIYANI
  • Other registrations4 more →
  • Completed1 of 5
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseOct 2021Revised toSep 2033

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jul 2017
  • Promised completion2 Sep 2033
  • Revised completionRevised to 2 Sep 2033 (originally 30 Oct 2021)
  • Buildings161 building records
  • Documents filed271 files

Current status

22.2%Work done, per cost certificate

Figures as on 18 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
G1/01NA10000
G1/02NA10000
G1/03NA10000
G1/04NA10000
G1/05NA10000
G1/06NA10000
G1/07NA10000
G1/08NA10000
G1/09NA10000
G1/10NA10000
G1/11NA10000
G1/12NA10000
G1/13NA10000
G1/14NA10000
G2/01NA10000
G2/02NA10000
G2/03NA10000
G2/04NA10000
G2/05NA10000
G2/06NA10000
G2/07NA10000
G2/08NA10000
G2/09NA10000
G2/10NA10000
G2/11NA10000
G2/12NA10000
G2/13NA10000
G2/14NA10000
G3/01NA10000
G3/02NA10000
G3/03NA10000
G3/04NA10000
G3/05NA10000
G3/06NA10000
G3/07NA10000
G3/08NA10000
G3/09NA10000
G3/10NA10000
G3/11NA10000
G3/12NA10000
G3/13NA10000
G3/14NA10000
G4/01NA10000
G4/02NA10000
G4/04NA10000
G4/05NA10000
G4/06NA10000
G4/07NA10000
G4/03NA10000
G4/08NA10000
G4/09NA10000
G4/10NA10000
G4/11NA10000
G4/12NA10000
G4/13NA10000
G4/14NA10000
G5/01NA10000
G5/02NA10000
G5/03NA10000
G5/04NA10000
G5/05NA10000
G5/06NA10000
G5/07NA10000
G5/08NA10000
G5/09NA10000
G5/10NA10000
G5/11NA10000
G5/12NA10000
G5/13NA10000
G5/14NA10000
G6/01NA10000
G6/02NA10000
G6/03NA10000
G6/04NA10000
G6/05NA10000
G6/06NA10000
G6/08NA10000
G6/07NA10000
G6/09NA10000
G6/10NA10000
G6/11NA10000
G6/12NA10000
G6/13NA10000
G6/14NA10000
H/01NA10000
H/02NA10000
H/03NA10000
H/04NA10000
H/05NA10000
H/06NA10000
H/07NA10000
H/08 and H/09NA10000
B/14NA10000
H/10NA10000
I/01NA10000
I/02NA10000
I/03NA10000
I/04NA10000
I/05NA10000
I/06NA10000
I/07NA10000
I/08NA10000
I/09NA10000
I/10NA10000
I/11NA10000
I/12NA10000
I/13NA10000
I/14NA10000
I/15NA10000
I/16NA10000
I/17NA10000
I/18NA10000
I/19NA10000
I/20NA10000
I/21NA10000
I/22NA10000
I/23NA10000
I/24NA10000
I/25NA10000
I/26NA10000
I/27NA10000
I/28NA10000
I/29NA10000
I/30NA10000
I/31NA10000
I/32NA10000
I/33NA10000
I/34NA10000
I/35NA10000
I/36NA10000
J/01NA10000
J/02NA10000
J/03NA10000
J/04NA10000
J/05NA10000
J/06NA10000
J/07NA10000
J/08NA10000
J/09NA10000
J/10NA10000
J/11NA10000
K/01NA10000
K/02NA10000
K/03NA10000
K/04NA10000
K/05NA10000
K/06NA10000
K/07NA10000
K/08NA10000
K/09NA10000
K/10NA10000
K/11NA10000
K/12NA10000
K/13NA10000
K/14NA10000
K/15NA10000
K/16NA10000
K/17NA10000
K/18NA10000
K/19NA10000
K/20NA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 161 buildings; the table lists the first 20.

44 of 1771 construction stages are filed complete across 161 buildings. The stage furthest along is Excavation, at 0%.

G1/010%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/020%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/030%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/040%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/050%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/060%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/070%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/080%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/090%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/100%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/110%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/120%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/130%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G1/140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/010%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/020%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/030%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/040%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/050%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G2/060%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes70%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area35,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on8 Jul 2025

Approvals and building plan

Sanctioning authorityNagpur Improvement Trust
Permissible FSI15651.85
Proposed, not sanctioned15,652 sq m
Buildings approved161
Buildings sanctioned161

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch345 SHREEMOHINI COMPLEX KINGSWAY NAGPUR
Estimated costRs 5,435.05 cr
Cost incurredRs 1,209.28 cr
Work done22.25%
BuildingWingEstimatedIncurred
G1/01NARs 33.70 crRs 7.49 cr
G1/02NARs 33.70 crRs 7.49 cr
G1/03NARs 33.70 crRs 7.49 cr
G1/04NARs 33.70 crRs 7.49 cr
G1/05NARs 33.70 crRs 7.49 cr
G1/06NARs 33.70 crRs 7.49 cr
G1/07NARs 33.70 crRs 7.49 cr
G1/08NARs 33.70 crRs 7.49 cr
G1/09NARs 33.70 crRs 7.49 cr
G1/10NARs 33.70 crRs 7.49 cr
G1/11NARs 33.70 crRs 7.49 cr
G1/12NARs 33.70 crRs 7.49 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnant Shrikant Raole
EngineerRahul Suresh Yelekar
Chartered AccountantAVSR & ASSOCIATES CHARTERED ACCOUNTANT
Chartered AccountantSanjay Lalwani
Chartered AccountantAshishkumar Khapekar
Chartered AccountantAnkit Malani
Chartered AccountantPrincy Pankaj Chawla
PartnerRole in project
HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500017522Oct 2021 → Sep 2033

Reason as filed by the promoterwe are appending the project extension application and the required documents like CA certficate and Architects Certificate and consent of the 83% customers for your perusal.Moreover we have applied for OC to NMRDA .We request you to extend the project by 10 years.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 2 Sep 2033

Documents filed271

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 271 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2018-2019)File: ZariPhase1_Form 5_31032018.pdf18 Apr 2026
Form 5 (FY 2019-2020)File: ZariPhase1_Form 5_31032020.pdf18 Apr 2026
Form 5 (FY 2020-2021)File: ZariPhase1_Form 5_31032021.pdf18 Apr 2026
Form 5 (FY 2021-2022)File: ZariPhase1_Form 5_31032022.pdf18 Apr 2026
Form 5 (FY 2022-2023)File: ZariPhase1_Form 5_31032023.pdf18 Apr 2026
Form 5 (FY 2023-2024)File: ZariPhase1_Form 5_31032024.pdf18 Apr 2026
Form 5 (FY 2024-2025)File: Form 5_HNZ Phase I_upto Sept 2025.pdf18 Apr 2026
Form 2A (FY 2017-2018)File: ZariPhase1_Form 2A_10042018.pdf15 Apr 2026
Form 2A (FY 2018-2019)File: ZariPhase1_Form 2_12042019.pdf15 Apr 2026
Form 2A (FY 2019-2020)File: ZariPhase1_Form 2A_14042020.pdf15 Apr 2026
Form 2A (FY 2020-2021)File: ZariPhase1_Form 2A_10042021.pdf15 Apr 2026
Form 2A (FY 2021-2022)File: ZariPhase1_Form 2A_13042022.pdf15 Apr 2026
Form 2A (FY 2022-2023)File: ZariPhase1_Form 2A_14042023.pdf15 Apr 2026
Form 2A (FY 2023-2024)File: ZariPhase1_Form 2A_29042024.pdf15 Apr 2026
Form 2A (FY 2024-2025)File: ZariPhase1_Form 2A_04042025.pdf15 Apr 2026
Form 2A (FY 2025-2026)File: HNZPHI_Form 2A_Apr 2026.pdf15 Apr 2026
Form 5 (FY 2017-2018)File: ZariPhase1_Form 5_31032018.pdf15 Apr 2026
Withdrawal Update Form 1File: HNZPHI_Form 1_Apr 2026.pdf14 Apr 2026
Withdrawal Update Form 2File: HNZPHI_Form 2_Apr 2026.pdf14 Apr 2026
Withdrawal Update Form 3File: HNZPHI_Form 3_Apr 2026_compressed.pdf14 Apr 2026
Withdrawal Update Form 1File: FORM1HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 1File: FORM1HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 1File: FORM1HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 2File: FORM2HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 2File: FORM2HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 2File: FORM2HNZPHIUPTODEC2025.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM3HNZPHIUPTODEC2025_compressed.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM3HNZPHIUPTODEC2025_compressed.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM3HNZPHIUPTODEC2025_compressed.pdf14 Jan 2026
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_FIRST.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_FIRST.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_First.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_10042018.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032018.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Second.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12012018.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032018.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Third.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_10042018.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032018.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_31032018.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_10042018.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032018.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_31032018.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_10042018.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_10042018.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032018.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_Form 5_31032018.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_12042019.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12042019.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Third.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032019.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_12042019.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12042019.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032019.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Fourth.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_12042019.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12042019.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032019.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Fourth.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_12042019.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12042019.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032019.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Fourth.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_12042019.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_12042019.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032019.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_Fourth.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_14042020.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_14042020.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032020.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: ZariPhase1_SoldUnsold_31032020.pdf31 Jul 2025
Form 1File: ZariPhase1_Form 1_14042020.pdf31 Jul 2025
Form 2File: ZariPhase1_Form 2_14042020.pdf31 Jul 2025
Form 3File: ZariPhase1_Form 3_31032020.pdf31 Jul 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHANTI HEIGHTS BESAAT POST BESA NAGPUR76CompletedDec 2010Dec 2010
SHANTI PARK BESAAT POST BESA-CompletedMar 2007Mar 2007

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 143 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARIHAR NAGAR ZARI PHASE - I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nagpur (rural)2,800+ in Nagpur

2 kmHARIHAR NAGAR ZARI PHASECompleted 22Lapsed / revoked 6Other 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED

HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED has 5 registrations on MahaRERA, including HARIHAR NAGAR ZARI PHASE - I and GOKULPARK TOWER NO 1. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if HARIHAR NAGAR ZARI PHASE - I is delayed beyond 2 Sep 2033?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARIHAR NAGAR ZARI PHASE - I?

The registered promoter entity is HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED, a company as per the filing. Its CIN U45400MH2007PLC176371 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARIHAR NAGAR ZARI PHASE - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HARIHAR NAGAR ZARI PHASE - I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARIHAR NAGAR ZARI PHASE - I?

The professionals named in the filing: Architect: Anant Shrikant Raole; Engineer: Rahul Suresh Yelekar; Chartered Accountant: AVSR & ASSOCIATES CHARTERED ACCOUNTANT; Chartered Accountant: Sanjay Lalwani; Chartered Accountant: Ashishkumar Khapekar; Chartered Accountant: Ankit Malani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARIHAR NAGAR ZARI PHASE - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARIHAR NAGAR ZARI PHASE - I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARIHAR NAGAR ZARI PHASE - I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.