Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
4 of 44Construction stages doneacross 4 buildings; furthest along: Basement (if any), 50%
1Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

HARI SIDDHI is a Residential / Group Housing project by NARESH JAGUMAL KARDA in Nashik, Maharashtra, registered with MahaRERA as P51600009519 on 22 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 30 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHARI SIDDHI
  • TypeResidential / Group Housing
  • Location
    • NASHIK
    • CHEHEDI BK
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600009519
  • ReraGenie IDRG-MH-08081

Builder

  • NameNARESH JAGUMAL KARDA
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Dec 2021)
  • Buildings4 building records
  • Documents filed80 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA90000
BUILDING BNA90000
BUILDING CNA90000
BUILDING DNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 50%.

BUILDING A25%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor10%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed117

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots117
Closed/Covered70
Open Space47
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A201434
BUILDING B201434
BUILDING C161026
BUILDING D14923

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
AMBADAS POPAT TAJANAPURENashik RoadNashik
PRAVIN PRAKASH TAJANPURECHEHEDI BKNashik
SAGAR KISAN TAJANPURENashik RoadNashik

Approvals and building plan

Permissible FSI7700.0
Proposed, not sanctioned5,537 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 10 - 18, Sai Plaza, Poona Road, Near Bytco College, Nashik, Maharashtra 422214

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANKHALA ASSOCIATES
PartnerRole in project
NARESH JAGUMAL KARDA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600011259Dec 2021 → Jun 2022

Reason as filed by the promoterThere has been delay in construction because of unavoidable problems faced due to pandemic of COVID-19. Hence we hereby request you to allow the extension of a period of 12 months

EXT51600012319Dec 2021 → Jun 2024

Reason as filed by the promoterThe project construction work is being delayed due to unviability of raw material .

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC001000000060312Tushar Shirish PatilNaresh Jagumal Karda09/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: HARI SIDDHI.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf26 Apr 2024
Details of encumbrancesFile: Encumbrance certificate (1)_page-0001.pdf24 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001.pdf24 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001.pdf24 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details_page-0001.pdf24 Feb 2024
Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001.pdf24 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001.pdf24 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: hari Siddhi.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SIDDHI.pdf8 Aug 2022
Disclosure of sold/ booked inventoryFile: HARI SIDDHI.pdf29 Apr 2022
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf14 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A certifcate.pdf18 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A certifcate.pdf18 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A certifcate.pdf18 Jan 2022
Disclosure of sold/ booked inventoryFile: H SIDDHI.pdf18 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Siddhi.pdf14 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Siddhi.pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf9 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Siddi Final.pdf9 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Siddhi.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Siddhi.pdf7 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KC- Hari Siddhi_compressed.pdf30 Sep 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE-Siddhi.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A - 19-20-Siddhi.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A - 20-21-Siddhi.pdf15 Aug 2021
Certificates of CA (Form 5)File: Form 5-Siddhi-2019-20.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5-Siddhi-2018-19.pdf30 Sep 2020
Building plan approvalFile: default (2).pdf25 Dec 2019
Building plan approvalFile: default 0001.pdf25 Dec 2019
Building plan approvalFile: default 0003.pdf25 Dec 2019
Building plan approvalFile: default 0004.pdf25 Dec 2019
Building plan approvalFile: default 0005.pdf25 Dec 2019
Building plan approvalFile: default 0006.pdf25 Dec 2019
Building plan approvalFile: default 0002.pdf25 Dec 2019
Building Plan Approval (IOD)File: default (2).pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0001.pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0003.pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0004.pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0005.pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0006.pdf25 Dec 2019
Building Plan Approval (IOD)File: default 0002.pdf25 Dec 2019
Details of encumbrancesFile: Enc cert.pdf10 Oct 2019
Certificates of CA (Form 5)File: Form 5_Hari Siddhi.pdf30 Sep 2019
Certificates of CA (Form 5)File: Form 5 - Hari Siddhi.pdf30 Sep 2018
Building plan approvalFile: Siddhi-1.pdf1 Aug 2017
Building plan approvalFile: Siddhi-2.pdf1 Aug 2017
Building plan approvalFile: Siddhi-3.pdf1 Aug 2017
Building plan approvalFile: Siddhi-5.pdf1 Aug 2017
Building plan approvalFile: Siddhi-5.pdf1 Aug 2017
Building plan approvalFile: Siddhi-6.pdf1 Aug 2017
Layout approvalFile: Siddhi-1.pdf1 Aug 2017
PAN CardFile: Naresh Karda.pdf1 Aug 2017
Copy of the legal title reportFile: Siddhi-Search report.pdf1 Aug 2017
Details of encumbrancesFile: Siddhi-Encumbrance certificate.pdf1 Aug 2017
Copy of Layout Approval (in case of layout)File: Siddhi-1.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-1.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-2.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-3.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-5.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-5.pdf1 Aug 2017
Building Plan Approval (IOD)File: Siddhi-6.pdf1 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Siddhi-Commencement.pdf1 Aug 2017
Declaration in FORM BFile: Siddhi-FORM B -PROMOTER.pdf1 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Siddhi-Engineers certificate.pdf1 Aug 2017
Certificates of CA (Form 3)File: Siddhi-CA certificate.pdf1 Aug 2017
Proforma of Allotment letterFile: Siddhi-Agreement.pdf1 Aug 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
HARI SHRADHADEOLALIGAON NASHIK-422101135CompletedFeb 2017Late, Apr 2017
HARI KRISHNA PHASE IIARTILARY CENTRE ROAD NASHIK ROAD NASHIK-42210165CompletedJan 2017Late, Apr 2017
HARI KRISHNANEAR MAHESHWARI BHAWAN ARTILARY CENTRE ROAD NASHIK ROAD-42210184CompletedMar 2013Late, Jun 2013

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 30 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARI SIDDHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASHIK4,100+ in Nashik

2 kmHARI SIDDHICompleted 9Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: NARESH JAGUMAL KARDA

NARESH JAGUMAL KARDA has 3 registrations on MahaRERA, including HARI KRISHNA PHASE III and HARI SIDDHI. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that HARI SIDDHI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARI SIDDHI is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARI SIDDHI?

The registered promoter entity is NARESH JAGUMAL KARDA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARI SIDDHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HARI SIDDHI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HARI SIDDHI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARI SIDDHI?

The professionals named in the filing: Architect: SANKHALA ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARI SIDDHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARI SIDDHI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARI SIDDHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.