HANUMAN NAGAR
By ZODIAC DEVELOPERS PRIVATE LIMITED
RG-MH-69430 · RERA P51800015181 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HANUMAN NAGAR is a Residential / Group Housing project by ZODIAC DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800015181 on 2 Feb 2018. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 36 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameHANUMAN NAGAR
- TypeResidential / Group Housing
- Location
- GULMOHAR ROAD
- HANUMAN NAGAR ANDHERI WEST
- Andheri
- Mumbai Suburban
- 400058
- Pincode400058
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800015181
- ReraGenie IDRG-MH-69430
Builder
- NameZODIAC DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorRAMESH VIRJI SHAH
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Feb 2018
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed74 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HANUMAN NAGAR BUILDING NO 7 | NA | 19 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 66%.
HANUMAN NAGAR BUILDING NO 7: 88% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 66% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 66% |
| Sanitary Fittings within the flats / premises | 66% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 66% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities21
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| SWIMMING POOL | Yes | 50% |
| SOCIETY OFFICE | Yes | 0% |
| MULTI PURPOSE ROOM | Yes | 0% |
| MTNL ROOM | Yes | 100% |
| GYMNASIUM | Yes | 0% |
| CHANGING ROOM | Yes | 0% |
Parking filed141
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SAMIR NARAIN BHOJWANI | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MS CONSULTANTS COMBINED |
| Engineer | M/S SHIRISH PATEL & ASSOCIATES CONSULTANTS PVT LTD |
| Chartered Accountant | KRUPA UDAY BALIA |
| Partner | Role in project |
|---|---|
| ZODIAC DEVELOPERS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere have been several delays in the said project due to the Covid-19 pandemic and also due to ongoing litigation.We request you to for extension of time limit up to 31st December,2023 for completion of the project and obtaining Occupation Certificate for the said project.
Litigation declared3
| Case | Court | Status |
|---|---|---|
| SUIT NO 2811/2016/2016 | CITY CIVIL COURT | PENDING |
| SUIT NO 9835/1999/1999 | CITY CIVIL COURT | PENDING |
| LND/1024/2017/2017 | ADDITIONAL COMMISSIONER KONKAN DIVISION | PENDING |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000079102 | abhishek jhaveri | Zodiac developers private limited, ramesh virji shah, jimit ramesh shah | 03/05/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Dec 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Dec 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Jan 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed74
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form_1_HN_Architects Certificate - 07-01-2023_FY 22-23_Q3.pdf | 3 Jun 2026 |
| Form 2File: Form_2_HN_Engineer s Certificate_31Dec22.pdf | 3 Jun 2026 |
| Form 3File: Form 3_Dec _2022_Final Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Dec 2022_Signed.pdf | 3 Jun 2026 |
| Form 1File: HN_Form_1_Architect_Certificate _March 2023_Signed.pdf | 3 Jun 2026 |
| Form 2File: HN_Form_2_Engineers Certificate March 2023_Signed.pdf | 3 Jun 2026 |
| Form 3File: form 3_March 203_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Mar 2023_Signed.pdf | 3 Jun 2026 |
| Form 1File: 3 HN_Form_1_Architect_Certificate _June 2023_Signed.pdf | 3 Jun 2026 |
| Form 2File: HN_Form_2_Engineers Certificate June 2023_Signed.pdf | 3 Jun 2026 |
| Form 3File: Final Form_3_Jun 2023_Final_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Jun 2023_Signed.pdf | 3 Jun 2026 |
| Form 1File: 4 HN_Form_1_Architect_Certificate _Sep 2023_Signed.pdf | 3 Jun 2026 |
| Form 2File: HN_Form_2_Engineers Certificate Sep 2023_Signed.pdf | 3 Jun 2026 |
| Form 3File: Final Form_3_Sep 2023_Final_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Sep 2023_Signed.pdf | 3 Jun 2026 |
| Form 1File: 5 HN_Form_1_Architect_Certificate _Dec 2023_Signed.pdf | 3 Jun 2026 |
| Form 2File: HN_Form_2_Engineers Certificate Dec 2023_Signed.pdf | 3 Jun 2026 |
| Form 3File: Final Form_3_Dec 2023_Final_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Dec 2023_Signed.pdf | 3 Jun 2026 |
| Form 1File: 6 HN_Form_1_Architect_Certificate _March 2024_Signed.pdf | 3 Jun 2026 |
| Form 2File: HN_Form_2_Engineers Certificate March 2024_Signed.pdf | 3 Jun 2026 |
| Form 3File: Final Form_3_March 2024_Final_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Mar 2024_Signed.pdf | 3 Jun 2026 |
| Form 1File: 7 HN_Form_1_Architect_Certificate _June 2024_Signed.pdf | 3 Jun 2026 |
| Form 2File: 4 HN_Form_2_Engineers Certificate_June 2024_Signed.pdf | 3 Jun 2026 |
| Form 3File: Final Form_3_June24_Final_Signed.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Jun 2024_Signed.pdf | 3 Jun 2026 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 march 22.pdf | 2 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-07-2022.pdf | 29 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-10-2022.pdf | 29 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_30June22.pdf | 29 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_30Sept22.pdf | 29 May 2023 |
| Certificates of CA (Form 3)File: form 3_with annexure.pdf | 29 May 2023 |
| Certificates of CA (Form 3)File: form 3_with annxure.pdf | 29 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-07-2021.pdf | 25 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-10-2021.pdf | 25 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-01-2022.pdf | 25 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_HN_Architects Certificate - 07-04-2022.pdf | 25 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_30June21.pdf | 25 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_30Sept21.pdf | 25 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_31Dec21.pdf | 25 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_HN_Engineer's Certificate_31March22.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: form 3 with annexure.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: form 3 with annexure.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: form 3 with annexure.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: form 3 with annexure.pdf | 25 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Letter for Engineers Certificate_.pdf | 27 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Letter for Engineers Certificate_.pdf | 27 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_CA Certificate_2017-18.pdf | 27 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_CA Certificate_2018-19.pdf | 27 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_CA Certificate_2019-20.pdf | 27 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_CA Certificate_2020-21.pdf | 27 Oct 2021 |
| Declaration about Commencement CertificateFile: form D.pdf | 22 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold booked Inventory.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: form 3.pdf | 23 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Architect_Certificate.PDF | 14 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Engineer's Certificate.pdf | 14 Jul 2021 |
| Building plan approvalFile: Hanuman_Nagar_Sale_Building_7_Plans.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Hanuman_Nagar_Sale_Building_7_Plans.pdf | 23 Jan 2018 |
| OtherFile: Disclosure_Final.pdf | 17 Jan 2018 |
| Copy of the legal title reportFile: Title_Certificate_DSK_Legal_28-07-20151.pdf | 28 Dec 2017 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 28 Dec 2017 |
| Details of encumbrancesFile: HN_Encumbrance_Certificate_27-12-2017.pdf | 27 Dec 2017 |
| Declaration in FORM BFile: HN_Affidavit_Cum_Declaration_RVS-_27-12-2017.pdf | 27 Dec 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HN_Architect_Certificate_Cons_Comb_22-12-2017.pdf | 27 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20171227165924.pdf | 27 Dec 2017 |
| Proforma of Allotment letterFile: HN_Letter_to_Maha_RERA_27-12-2017.pdf | 27 Dec 2017 |
| Layout approvalFile: HN_Layout_01-06-2015- 1.pdf | 26 Dec 2017 |
| Building plan approvalFile: HN_LOI_Revised_30-11-2015.pdf | 26 Dec 2017 |
| PAN CardFile: HN_PAN_ZDPL.pdf | 26 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: HN_Layout_01-06-2015- 1.pdf | 26 Dec 2017 |
| Building Plan Approval (IOD)File: HN_LOI_Revised_30-11-2015.pdf | 26 Dec 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: HN_Sale_Building_No_7_CC.pdf | 26 Dec 2017 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Gandhi Nagar (Bandra) | Mercury Co-op. Hsg. Soc.Ltd. Opp. Hallmark Plaza,Bandra East,Mumbai-400051. | Completed | Jun 2020 | Late, Sep 2020 |
| Hanuman Nagar SRA (Juhu) | Bldg. No.5 Off.Gulmohar Road,Juhu,Vile Parle West,Mumbai-400049. | Completed | Mar 2017 | Late, Apr 2017 |
| Kushinara SRA (Bandra) | C.T.S. D- 998, D-1013 & D-1078 of village Bandra (West), Mumbai For Kushinara Co-op. Hsg. Society | Completed | Mar 2007 | Late, Apr 2007 |
| Hanuman Nagar SRA (Juhu) | Bldg. No.1 Off.Gulmohar Road,Juhu,Vile Parle West,Mumbai-400049. | Completed | Jun 2006 | Jun 2006 |
| Hanuman Nagar SRA (Juhu) | Bldg. No.2 Off.Gulmohar Road,Juhu,Vile Parle West,Mumbai-400049. | Completed | Sep 2005 | Late, Oct 2005 |
| Venus (Vile Parle) | Plot bearing FP No.506,TPS V, Vile Parle East, Mumbai-400056 | Completed | Dec 2002 | Nov 2002 |
| Jupiter CHS (Vile Parle) | Plot bearing O.P.No.485,FP No.505,TPS V, Vile Parle East, Mumbai-400056 | Completed | Jul 2001 | Jul 2001 |
| Hanuman Nagar SRA (Juhu) | Bldg. No.3 Off.Gulmohar Road,Juhu,Vile Parle West,Mumbai-400049. | Completed | Dec 2000 | Nov 2000 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 74 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HANUMAN NAGAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near HANUMAN NAGAR ANDHERI WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 271 registered projects within 2 km.
PEARL UNIVERSE
CHANDIWALA ENTERPRISES PRIVATE LIMITED
PRANAMI BLISS
Pranami Neev Realty Limited
Alpine Primo
ALPINE INFRAHEIGHTS LLP
NAMAN HABITAT
SHREE NAMAN DEVELOPERS PVT LTD
Vantage
Rolland Spaces Private Limited
Nasar Enclave Sale Building A and B Wing
M/s. Nasar Associates
See every Mumbai Suburban project, with the district possession charts
Builder: ZODIAC DEVELOPERS PRIVATE LIMITED
ZODIAC DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including HANUMAN NAGAR. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that HANUMAN NAGAR shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if HANUMAN NAGAR is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HANUMAN NAGAR?
The registered promoter entity is ZODIAC DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HANUMAN NAGAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HANUMAN NAGAR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HANUMAN NAGAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HANUMAN NAGAR?
The professionals named in the filing: Architect: MS CONSULTANTS COMBINED; Engineer: M/S SHIRISH PATEL & ASSOCIATES CONSULTANTS PVT LTD; Chartered Accountant: KRUPA UDAY BALIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HANUMAN NAGAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback