Home / Browse projects / Pune, Maharashtra / Guardian Wind Shire Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Guardian Wind Shire Phase 2

By Guardian Landmarks LLP

RG-MH-09875 · RERA P52100002080 · Last updated on MahaRERA portal: 5 Oct 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 8%
2Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

Guardian Wind Shire Phase 2 is a Residential / Group Housing project by Guardian Landmarks LLP in Pune, Maharashtra, registered with MahaRERA as P52100002080 on 31 Jul 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGuardian Wind Shire Phase 2
  • TypeResidential / Group Housing
  • Location
    • Kirkatwadi-Nandoshi Road
    • Nandoshi
    • Haveli
    • Pune
    • 411024
  • Pincode411024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002080
  • ReraGenie IDRG-MH-09875

Builder

  • NameGuardian Landmarks LLP
  • Entity typePartnership
  • PartnerManish Murlidhar Sabade
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

40 months past promisethis monthRegisteredJul 2017PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C3NA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Oct 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 8%.

C3: 37% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks4%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Oct 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed80

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots80
Closed/Covered80

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,929 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Dnyaneshwar Marutrao ShirwalkarParvatiPune

Approvals and building plan

Permissible FSI6858.0
Proposed, not sanctioned5,445 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKothrud

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil Vartak & Associates
EngineerSpectrum Consultants
PartnerRole in project
Guardian Landmarks LLP-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000127125Ramsingh Hilal PatilGuardian Landmarks LLP19/05/2022
CC005000000127127pravinsing Jaysing RajputGuardian Landmark LLP21/05/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: WS-2 Architect Certificate-Sept 19.pdf5 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: WS-2 Engineer Certificate-Sept 19.pdf2 Oct 2019
Form 2AFile: WS-2 Quality Assurance -Sept 19.pdf2 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: WSArchPh2.pdf14 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: WS Ph2 Engg.pdf14 Aug 2019
Certificates of CA (Form 3)File: WSCAPh2.pdf14 Aug 2019
Certificates of CA (Form 5)File: Wind Shire Ph-2-A.pdf15 Jul 2019
Form 2AFile: WS_Phase-2 QA.pdf1 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Wind Shire Ph-2-A.pdf1 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wind Shire Ph-2-E.pdf1 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Wind shire Phase-2 Archtect certificate.pdf8 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wind Shire Engineer Certificate dec 18.pdf8 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Wind Shire Phase 2 Architect 250118 Upload.pdf13 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Wind Shire ph 2 Engineer 250118.pdf13 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Wind Shire Phase 2 Architect 2.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wind Shire Ph2 Engineer 2.pdf31 Oct 2017
Copy of the legal title reportFile: Title GAT no 189P.pdf27 Jul 2017
Copy of the legal title reportFile: Title GAT no 190.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Wind Shire Phase 2 Engineer 1.pdf27 Jul 2017
Certificates of CA (Form 3)File: Wind Shire Phase 2 CA Part 1.pdf27 Jul 2017
Certificates of CA (Form 3)File: Wind Shire Phase 2 CA Part 2.pdf27 Jul 2017
Proforma of Allotment letterFile: Wind Shire Phase 2 Agreement Draft.pdf27 Jul 2017
Proforma of Allotment letterFile: Allotment_Letter_ Draft OK.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Wind Shire Phase 2 Architect Certificate.pdf21 Jul 2017
Building plan approvalFile: Layout.pdf18 Jul 2017
Layout approvalFile: Layout.pdf18 Jul 2017
PAN CardFile: Pan Card LLP.PDF18 Jul 2017
Details of encumbrancesFile: Letter of Encumbrance_Wind Shire.pdf18 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf18 Jul 2017
Building Plan Approval (IOD)File: Layout.pdf18 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Nandoshi.pdf18 Jul 2017
Declaration in FORM BFile: Wind shire phase 2 for promoter_Form B_Promoter.pdf18 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Guardian Wind Shire Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nandoshi13,700+ in Pune

2 kmGuardian Wind Shire PhasCompleted 4Lapsed / revoked 10Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: Guardian Landmarks LLP

Guardian Landmarks LLP has 2 registrations on MahaRERA, including Guardian Wind Shire Phase 1 and Guardian Wind Shire Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Guardian Wind Shire Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Guardian Wind Shire Phase 2 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Guardian Wind Shire Phase 2?

The registered promoter entity is Guardian Landmarks LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Guardian Wind Shire Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Guardian Wind Shire Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Guardian Wind Shire Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Guardian Wind Shire Phase 2?

The professionals named in the filing: Architect: Sunil Vartak & Associates; Engineer: Spectrum Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Guardian Wind Shire Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Guardian Wind Shire Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Guardian Wind Shire Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.