Home / Browse projects / Dakshina Kannada, Karnataka / GTI MARIGOLD

Registration approved Residential/Group Housing project

GTI MARIGOLD

By M/S GENERAL TRUST INFRASTRUCTURE

RG-KA-44616 · RERA PRM/KA/RERA/1257/334/PR/181010/002043 · Last updated on RERA Karnataka portal: 22 Dec 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2023Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 70 documents Report an error

GTI MARIGOLD is a Residential/Group Housing project by M/S GENERAL TRUST INFRASTRUCTURE in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/181010/002043 on 10 Oct 2018. Possession is promised by 19 Sep 2023. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameGTI MARIGOLD
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/181010/002043
  • ReraGenie IDRG-KA-44616

Builder

  • NameM/S GENERAL TRUST INFRASTRUCTURE
  • Entity typePartnership Firm
  • Authorized SignatoryDEEMANTH SUVARNA

Key dates

this monthRegisteredOct 2018First promiseDec 2021Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Oct 2018
  • Promised completion19 Sep 2023
  • Revised completionRevised to 19 Sep 2023 (originally 19 Dec 2021)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GTI MARIGOLD---22022

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 22 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 22 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,113 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHESH M KULSHEKAR
EngineerK. ANIL HEGDE

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1257/334/PR/230119/002043Sep 2022 → Sep 2023

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed70

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/181010/002043 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
bank change request approved confirmationFile: bank chnage request approved confirmation.pdf22 Dec 2022
affidavit for water &power nocFile: affidavit for water noc & mescom noc.pdf22 Dec 2022
mescom noc application letterFile: mescom noc application.jpeg22 Dec 2022
clarificationFile: clarification.jpeg22 Dec 2022
CertificateFile: REGISTRATION CERTIFICATE.pdf-
Architect Certificate for Work Completion Schedule till DateFile: architect certificate -work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: engineer certificate for work completed.jpg-
CA Certificate for Funds UtilizationFile: Form-Ex3 fund utilized.PDF-
Architect Certificate for Pending Work Completion Schedule.File: architect certificate work pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: engineer certificate work pending.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 fund required.PDF-
AffidavitFile: affidavit-seeking extension_compressed.pdf-
Latest Encumbrance CertificateFile: EC 1992-2022_compressed.pdf-
Consent letter from 2/3rd of AllotteesFile: consent letter_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: covid extension certificate.pdf-
Document 2File: affidavit-paying componsation.pdf-
Document 3File: ALLOTMENT LETTER.pdf-
Document 4File: consent letter.pdf-
Document 5File: list of allottes.pdf-
Document 6File: list of consent.pdf-
Document 7File: form b.pdf-
NO 9 LICENCE-
No10APPROVED PLAN-
No10APPROVED PLAN-
18 SALE PROFORMA-
12AGREEMENT FOR SALE-
NO 13 SALE DEED-
No10APPROVED PLAN-
AREA SCHEDULE_MARIGOLD-
ALLOTMENT LETTER-
NO19 SPECIFICATION-
ENCUMBRANCE CERTIFICATE-
NO22KHATHA-
NO 20JDA-
OTHER NA-
CONVERSION3-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
NO 27 FIRE NOC-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
Unnamed document-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
OTHER NA-
NO 45 STRUCTURAL-
No10APPROVED PLAN-
No10APPROVED PLAN-
No10APPROVED PLAN-
OTHER NA-
47ADVOCATE SEARCH-
FORM B-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_181010_002043.xlsx-
Occupancy CertificateFile: OC.jpeg-
Architect certificate for having completed the work(in format no 5)File: COMPLETION_FORM 5_MARIGOLD.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: form 4 cc_compressed.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion affidavit.pdf-
engineer certificateFile: COMPLETION_FORM 6_MARIGOLD.pdf-
completion certificateFile: completion certiifcate.jpeg-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 21 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep GTI MARIGOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: M/S GENERAL TRUST INFRASTRUCTURE

M/S GENERAL TRUST INFRASTRUCTURE has 1 registration on RERA Karnataka, including GTI MARIGOLD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if GTI MARIGOLD is delayed beyond 19 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GTI MARIGOLD?

The registered promoter entity is M/S GENERAL TRUST INFRASTRUCTURE, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GTI MARIGOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GTI MARIGOLD?

The professionals named in the filing: Architect: MAHESH M KULSHEKAR; Engineer: K. ANIL HEGDE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GTI MARIGOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GTI MARIGOLD. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GTI MARIGOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.