Home / Browse projects / Sindhudurg, Maharashtra / GSR Aanandam
GSR Aanandam
RG-MH-04156 · RERA P52900021376 · Last updated on MahaRERA portal: 3 Jun 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- 14 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GSR Aanandam is a Others project by Rajesh Raghuvir Mantri in Sindhudurg, Maharashtra, registered with MahaRERA as P52900021376 on 24 Jun 2019. Possession was promised by 30 Dec 2022 and is now 46 months past that date. 14 complaints are on record with the regulator.
At a glance
Project
- NameGSR Aanandam
- TypeOthers
- Location
- Shiroda
- Vengurla
- Sindhudurg
- 416518
- Pincode416518
- RERA no.P52900021376
- ReraGenie IDRG-MH-04156
Builder
- NameRajesh Raghuvir Mantri
- Entity typeIndividual
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Jun 2019
- Promised completion30 Dec 2022
- Revised completionNone
- Buildings1 building record
- Documents filed34 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GSR Aanandam | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GSR Aanandam: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed55
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mandar D Ambekar |
| Engineer | Mandar D Ambekar |
| Chartered Accountant | Sagar Gajanan Teli |
| Partner | Role in project |
|---|---|
| Rajesh Raghuvir Mantri | - |
Complaints filed with MahaRERA14
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000171908 | Shailesh Pandhare | Rajesh Raghuvir MAntri | 19/12/2019 |
| CC006000000194103 | Suresh Sawant | Rajesh Raghuvir Mantri | 28/09/2020 |
| CC006000000195662 | Jayant Parshuram Patankar | Rakesh Raghuvir Mantri | 07/01/2022 |
| CC006000000195742 | Rajendra Kambli | RAjesh Raghuvir Mantri | 05/02/2021 |
| CC006000000195737 | Vinayak Gopal Malvankar | Rajesh Raghuvir Mantri | 15/02/2021 |
| CC006000000195743 | Prathamesh Kishor Chindarkar | Rajesh Raghuvir Mantri | 14/02/2021 |
| CC006000000195745 | Haresh Ramakant Prabhuzantye | Rajesh Raghuvir Mantri | 05/02/2021 |
| CC006000000195740 | Shabana Shafi Khan | Rajesh Raghuvir Mantri | 04/02/2021 |
| CC006000000195741 | Ramlal Sadanand Redkar | Rajesh Raghuvir Mantri | 04/02/2021 |
| CC006000000195770 | Ujjayani Narayan Manjarekar | Rajesh Raghuvir Mantri | 04/02/2021 |
| CC006000000195738 | Mrs Shweta Narayan Prabhu | Rajesh Raghuvir Mantri | 15/02/2021 |
| CC006000000195751 | Gajanan Vengurlekar | Rajesh Raghuvir Mantri | 05/02/2021 |
| CC006000000195771 | Subhash Nagesh Swar | Rajesh Raghuvir Mantri | 04/02/2021 |
| CC006000000195823 | LAxmikant Gawade | Rajesh Raghuvir Mantri | 02/09/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jun 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Jun 2024
Documents filed34
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GSR Anandam Grampanchayat OC 03Oct2023.pdf | 3 Jun 2024 |
| Other - TechnicalFile: Final Order.pdf | 28 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1528_GSR ANANDAM FORM 2A QUALITY ASSURANCE CERTIFICATE 2020.pdf | 26 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1528_GSR ANANDAM FORM 2A QUALITY ASSURANCE CERTIFICATE 2021.pdf | 26 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1528_GSR ANANDAM FORM 2A QUALITY ASSURANCE CERTIFICATE 2022.pdf | 26 Apr 2023 |
| Layout approvalFile: Kaagaz_20230421_101449431473.pdf | 21 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: Kaagaz_20230421_101449431473.pdf | 21 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: GSR ANANDAM SHIRODA GRAMPANCHAYAT NA ORDER_001.pdf | 21 Apr 2023 |
| Certificates of CA (Form 3)File: GSR Anandam Form 3 CA Certificate 2019-2022.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GSR Anandam FORM 5 - Annual Report 2019-20.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GSR Anandam FORM 5 - Annual Report 2020-21.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: GSR Anandam FORM 5 - Annual Report 2021-22.pdf | 3 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 15102022.pdf | 29 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 16102022.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: CA cerificate 30092022.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: CA Certificate 30092021 GSR.pdf | 28 Apr 2022 |
| Certificates of CA (Form 3)File: CA Certificate 31122021 GSR.pdf | 28 Apr 2022 |
| Certificates of CA (Form 3)File: CA Certificate March 2021.pdf | 3 Sep 2021 |
| Certificates of CA (Form 3)File: CA Certificate June 2021.pdf | 3 Sep 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 7 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf | 2 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Anandam.pdf | 17 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Anadam.pdf | 17 Jun 2019 |
| Certificates of CA (Form 3)File: C A Certificate Aanadam.pdf | 17 Jun 2019 |
| Copy of the legal title reportFile: Search Report Compress.pdf | 12 Jun 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf | 12 Jun 2019 |
| Building plan approvalFile: NA Order.pdf | 6 Jun 2019 |
| Layout approvalFile: Sanction Plan.pdf | 6 Jun 2019 |
| PAN CardFile: PAN Card Rajesh.PDF | 6 Jun 2019 |
| Details of encumbrancesFile: No Encumbrances.pdf | 6 Jun 2019 |
| Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf | 6 Jun 2019 |
| Building Plan Approval (IOD)File: NA Order.pdf | 6 Jun 2019 |
| Declaration in FORM BFile: Form B - Prashant Khanvilkar.pdf | 6 Jun 2019 |
| Proforma of Allotment letterFile: Model Agreement Marathi.pdf | 6 Jun 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 34 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GSR Aanandam on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shiroda530+ in Sindhudurg
DREAMZ GOA
LEVEL UP CONSTRUCTIONS
DREAMZ GOA PHASE II
LEVEL UP CONSTRUCTIONS
PERTO DE GOA PHASE 4
Rushikesh Atul Labhshetwar
PERTO DE GOA - PHASE 3
ANKIT VASTU CREATIONS PVT. LTD.
Bhumaiyya Park
Dattaraj Constructions
Siddhivinayak Complex
Prasad Pramod Khot
See every Sindhudurg project, with the district possession charts
Builder: Rajesh Raghuvir Mantri
Rajesh Raghuvir Mantri has 2 registrations on MahaRERA, including 54 Anandwan Sankul and GSR Aanandam. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What does it mean that GSR Aanandam shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GSR Aanandam is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GSR Aanandam?
The registered promoter entity is Rajesh Raghuvir Mantri, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GSR Aanandam?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GSR Aanandam?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GSR Aanandam?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GSR Aanandam?
The professionals named in the filing: Architect: Mandar D Ambekar; Engineer: Mandar D Ambekar; Chartered Accountant: Sagar Gajanan Teli. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GSR Aanandam?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.