Home / Browse projects / Mumbai City, Maharashtra / GSA GRANDEUR
GSA GRANDEUR
RG-MH-12258 · RERA P51900009097 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 64 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GSA GRANDEUR is a Mixed project by G S A CONSTRUCTIONS in Mumbai City, Maharashtra, registered with MahaRERA as P51900009097 on 19 Aug 2017. Possession is promised by 15 Oct 2026. The completion date has moved by 64 months from the original filing. 62 of the 93 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameGSA GRANDEUR
- TypeMixed
- Location
- Pathanwadi Road
- -
- Mumbai City
- 400102
- Pincode400102
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900009097
- ReraGenie IDRG-MH-12258
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Aug 2017
- Promised completion15 Oct 2026
- Revised completionRevised to 15 Oct 2026 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed188 files
Current status
Figures as on 24 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GSA Grandeur | NA | 27 | 22 | 73 | 19 | 92 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
GSA Grandeur91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA Plot Without StructureNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed11
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GSA Grandeur | NA | Rs 17.07 cr | Rs 17.07 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Duberia & Associates |
| Architect | Duberia & Asssocitaes |
| Engineer | Epicon Consultants Pvt Ltd |
| Engineer | MOHD SHOAIB RAUF PAWAR |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | Pratik D. Jain & Associates |
| Chartered Accountant | Riddhi Dhaval Sheth |
| Partner | Role in project |
|---|---|
| G S A CONSTRUCTIONS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1.We have obtained full occupancy certificate from Brihanmumbai Municipal Corporation Authority dated 17/04/2026 for project “GSA Grandeur”. 2.We have to apply for Application for Correction and then need to go for Completion Update. Therefore, we are applying for Extension in Project Completion date till 15/10/2026. 3.The photos of present status of project are enclosed herewith.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000054972 | MANOJ SHUKLA | M/S GSA Constructions | 19/06/2018 |
| CC006000000054646 | SIMPLE NIMKAR | M/s GSA Constructions | 25/05/2018 |
| CC006000000161301 | KALYANI AVINASH HENDRE | GSA Constructions | 07/02/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 15 Oct 2026
Documents filed188
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 188 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: AR - Dec 22.pdf | 24 Jun 2026 |
| Form 2File: ER Dec-22.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Dec 22-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 22.pdf | 24 Jun 2026 |
| Form 1File: AR - Dec 23 .pdf | 24 Jun 2026 |
| Form 2File: ER Dec-23.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Dec 23-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 23.pdf | 24 Jun 2026 |
| Form 1File: AR - Dec 24 .pdf | 24 Jun 2026 |
| Form 2File: ER Dec-24.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Dec 24-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 24.pdf | 24 Jun 2026 |
| Form 1File: AR - June 22.pdf | 24 Jun 2026 |
| Form 2File: ER June-22.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ June 22-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 22.pdf | 24 Jun 2026 |
| Form 1File: AR - June 23.pdf | 24 Jun 2026 |
| Form 2File: ER June-23.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ June 23-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 23.pdf | 24 Jun 2026 |
| Form 1File: AR - June 24.pdf | 24 Jun 2026 |
| Form 2File: ER June-24.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ June 24 -Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 24.pdf | 24 Jun 2026 |
| Form 1File: AR -March 22 .pdf | 24 Jun 2026 |
| Form 2File: ER Mar-22.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ March 22-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 22.pdf | 24 Jun 2026 |
| Form 1File: AR - march 23 .pdf | 24 Jun 2026 |
| Form 2File: ER Mar-23.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ March 23-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 23.pdf | 24 Jun 2026 |
| Form 1File: AR - March 24.pdf | 24 Jun 2026 |
| Form 2File: ER Mar-24.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ March 24_-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 24.pdf | 24 Jun 2026 |
| Form 1File: AR - March 25 .pdf | 24 Jun 2026 |
| Form 2File: ER Mar-25.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ March 25-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf | 24 Jun 2026 |
| Form 1File: AR - Sept 22 .pdf | 24 Jun 2026 |
| Form 2File: ER Sep-22.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Sept 22-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Sept 22.pdf | 24 Jun 2026 |
| Form 1File: AR - Sept 23.pdf | 24 Jun 2026 |
| Form 2File: ER Sep-23.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Sept 23-Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Sept 23 .pdf | 24 Jun 2026 |
| Form 1File: AR - Sept 24 .pdf | 24 Jun 2026 |
| Form 2File: ER Sep-24.pdf | 24 Jun 2026 |
| Form 3File: CA Certificate_ Sept 24 -Final.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Sept 24.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: AR - June 25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: AR - Sept 25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: AR - Dec 25 .pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: AR - March 26.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: ER June-25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: ER Sep-25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: ER Dec-25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: ER Mar-26.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: CA Certificate_ June 25 -Final.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: CA Certificate_Sept 25 -Final.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: CA Certificate_Dec 25 -Final.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: CA Certificate_March-26-Final.pdf | 24 Jun 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - March 23.pdf | 24 Jun 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - March 24.pdf | 24 Jun 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25 .pdf | 24 Jun 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - March 26 .pdf | 24 Jun 2026 |
| Form 2A (FY 2026-2027)File: Form 2A - March 27 .pdf | 24 Jun 2026 |
| Form 5 (FY 2022-2023)File: Rera Audit 2022-23.pdf | 24 Jun 2026 |
| Form 5 (FY 2023-2024)File: Rera Audit 2023-24.pdf | 24 Jun 2026 |
| Form 5 (FY 2024-2025)File: Rera Audit 2024-25.pdf | 24 Jun 2026 |
| Form 1File: AR -March 22 .pdf | 8 Jun 2026 |
| Form 2File: ER Mar-22.pdf | 8 Jun 2026 |
| Form 3File: CA Certificate_ March 22-Final.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 22.pdf | 8 Jun 2026 |
| Form 1File: AR - March 18.pdf | 8 Jun 2026 |
| Form 2File: ER Mar-18.pdf | 8 Jun 2026 |
| Form 3File: CA - March 18 -Final.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 18.pdf | 8 Jun 2026 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| GSA SERENE | PLOT NO 21 PUSHTIKAR SOCIETY JOGESHWARI WEST MUMBAI-400102 | 21 | Completed | Dec 2015 | Late, Nov 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 188 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GSA GRANDEUR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -780+ in Mumbai City
ROSWALT ZAIDEN
A S HIGHTECH LLP
Dream Signature
Prime Realtors
Sayba Noor
Star Raises
Gurukrupa Ekam
GURUKRUPA REALCON INFRABUILD LLP
The Westpark Phase-1
WESTPARK DEVELOPERS PRIVATE LIMITED
Kalpataru Hrushikesh
Kalpataru Townships Private Limited
See every Mumbai City project, with the district possession charts
Builder: G S A CONSTRUCTIONS
G S A CONSTRUCTIONS has 2 registrations on MahaRERA, including GSA GRANDEUR and GSA GRANDEUR A and B Wing. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if GSA GRANDEUR is delayed beyond 15 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GSA GRANDEUR?
The registered promoter entity is G S A CONSTRUCTIONS, a partnership as per the filing. Its GSTIN 27AAIFG1103G1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GSA GRANDEUR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GSA GRANDEUR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GSA GRANDEUR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GSA GRANDEUR?
The professionals named in the filing: Architect: Duberia & Associates; Architect: Duberia & Asssocitaes; Engineer: Epicon Consultants Pvt Ltd; Engineer: MOHD SHOAIB RAUF PAWAR; Chartered Accountant: RSPH & Associates; Chartered Accountant: Pratik D. Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GSA GRANDEUR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback